Title: OAKY CREEK COAL
1OAKY CREEK COAL
Analyst Investor Briefing by Mike Ryan,
General Manager 26 November 2001
2Oaky Creek
- Majority owned and operated by M.I.M. Holdings
Limited - Located in Queenslands world-renowned Bowen
Basin - Producing two high quality medium volatile coking
coals - Capacity expanded to 10Mtpa product
- Exporting through both Dalrymple Bay and
Gladstone - Highly productive and highly competitive
3Oaky Creek History
- First coal produced in 1983
- Initially a dragline-based open cut mine
- Underground mine (Oaky No.1) commenced in 1989
- Oaky North underground mine commenced longwall
production in February 1999 - Alliance longwall punch mine started in 1997
- Open cut initially ceased production September
1999, production resumed in July 2001
4Oaky Creek Current Status
- Oaky North longwall mine in full operation
- Oaky No1 longwall mine in full operation
- Open Cut mining recommenced July 2001 with 2
draglines - potential for 6 years of operation - Alliance Operation scheduled to finish January
2002 but potential to expand and operate until
2004.
5Oaky Creek Ownership
MIM 75
Sumitomo 15
Itochu 10
6Oaky Creek Coal location
7Oaky Creek Geology
- German Creek coal measures
- One principal coal seam worked - the German Creek
seam - All underground mining in the German Creek seam
- Regional rank gradient results in volatiles
reducing from south (Kestrel, Gregory) to north
(German Creek, Norwich Park) - German Creek coal measures including Aquila are
characterised by excellent plastometric
properties and coke strength at any particular
rank
8Oaky Creek Exploration
- Exploration by surface drilling and 3D Seismic
- 3D Seismic used as criterion for proven reserves
- Drilling used for geotechnical evaluation, coal
quality, insitu gas quantity and validation of
seismic interpretation - Expected exploration expenditure 12.5M for
2001/2002
9 Oaky Creek Stratigraphic Section
10Oaky Creek Organisation Chart
11Oaky No.1 Underground
- Transition year
- New longwall will be commissioned in the
south-east area of the mine in February 2002 - 3D seismic programme in progress to define
structure of Sandy Creek East area - Reserves for gt11 years at 5 Mtpa
12Oaky North Underground
- Currently two longwall blocks developed in front
of current longwall production. Plan to always
maintain two blocks in front. - Longwall production NLW2 commenced March 2000.
- Utilisation of two complete sets of longwall
equipment (apart from shields) to reduce longwall
moves. Planned move time 24 days, last move
completed in 22 days. -
13Oaky North Underground
- Resourced to ensure optimum maintenance at low
cost - Longwall delivering onto high capacity 4,500
tonne per hour belt system for delivery to CPP. - Manning levels minimised to cover core functions.
- Reserves of 40 million tonnes in present area
with further reserves in the eastern area
14Alliance Underground
- A longwall punch operation mining from final
highwalls into otherwise non-recoverable coal - Located in the south-west, with volatiles between
28-29 - Contractor owned and operated equipment
- Potential for LW mining until 2004-2005
- Raw coal washed in Oaky Creek washplant
15Oaky Creek Surface Operations
- Capacity recently upgraded to 1800 tph with the
construction of a fourth module - Fines circuit upgraded to improve overall
metallurgical efficiency - Maintenance philosophy in place to achieve 7600
hours availability - Open Cut Operations recommenced in July to
supplement Raw Coal feed - Capacity now 13.5 Mtpa raw coal feed
16Environmental Initiatives
- Environmental Management System
- Based on ISO14001 framework
- Structured to distribute environmental
responsibilities throughout all OCC departments - Key component is environmental awareness training
for all employees and contractors
17Environmental Initiatives
- Water Management
- Raw water consumption per tonne of clean coal has
reduced by 54 in the last 4 years - 75 of water used in the coal preparation plant
is from recycled sources - Life of mine water management plan and water
balance model is updated and reviewed annually
18Environmental Initiatives
- Rehabilitation
- OCC uses the Internally Drained Rehabilitation
(IDR) technique developed in 1989 - Objectives are long term stability,minimise
offsite impacts, and final land use of native
woodland - IDR methodology was approved by the EPA in 1999
- Method won the 1999 AMEEF Award
19Rehabilitation Specifications
BEFORE
AFTER
20Rehabilitation Success
BEFORE
AFTER
21Environmental Initiatives
- Waste Management
- Total waste management system implemented
November 2001 - All waste is segregated and recycled where
possible (metal, wood, paper, plastics, oil) - Waste tracking and monitoring system used to
assess performance against KPIs
22Oaky Creek Infrastructure
- The workforce is housed in the MIM-built town of
Tieri, 13km from the mine - Rail access by Queensland Rail (QR) to Dalrymple
Bay (DBCT), 297km, and Gladstone, 394km - QR is state government owned but recent third
party access provisions will bring increasing
competition
23Oaky Creek Infrastructure (cont)
- DBCT is operated by a company jointly owned by
the six users - DBCT has 2 berths, 2 shiploaders and a current
capacity of 43.5 Mtpa. It has 2.4 Mt of
stockpile capacity - Gladstone is operated by the Gladstone Port
Authority, a statutory authority - RG Tanna Coal Terminal has 2 berths, 2
shiploaders and a current capacity of 35 Mtpa.
It has 3.5 Mt of stockpile capacity - Barney Point Coal Terminal has a single berth and
shiploader with a capacity of 5mtpa. It has 0.5Mt
stockpile capacity.
24Australian Longwall Mines Total Production
2001
MT
Total ROM Tonnes
Source Joint Coal Board
Year ending 30 June
25Oaky Creek Production (100)
(Quarterly)
Tonnes (000s)
1998
1999
2000
2001
Product coal
Washplant upgrade
Year ending 30 June
26Oaky Creek Production (100)
Capacity 10Mt/yr
Product coal
Year ending 30 June
27Increasing Coal Productivity
Tonnes of coal per employee
Year ending 30 June
28Broad market for coal - 2001
Year ending 30 June
29Increased Oaky Creek EBIT Flat A prices
received
(A/T)
(AM)
(29)
Data is 100
Year ending 30 June
30Competitive coal production
US/t
Quartiles
Source AME 2001 coking coal cash costs adjusted
for current FX A/US 0.5218, US/C 0.6274