Title: US CMS Report
1US CMS Report
- Status and Planning for US CMS
- Dan Green
- US CMS Program Manager
- February 24, 2003
2Outline
- Detector - Technical Status
- Detector - Financial Summary
- Research Program Startup
- MO Plans
- SWC Plans
- Issues
3LHC - SM Higgs
The LHC detectors are designed to find the SM
Higgs. Low mass is covered by ??, ttH(bb),
qqH(WW,??). A low mass Higgs has many
accessible decay modes ? couplings measured.
4LHC - SUSY
Energy matters! One month at 1/10 design
luminosity extends mass reach by a lot. LHC
experiments must be ready on week one for new
Physics.
5CMS
6Civil Engineering at USC
Limited first access to USC55 in February 2004
full access on 16 Oct. 2004
7COIL Winding of External Layer of CB-2 Completed
The winding of the coil is critical. Last coil
module (n0 5) to be delivered at CERN in Feb
04. The Completion of the coil at CERN in 2004
and the test of the Magnet on the surface in
early 2005 are on the critical path.
8CMS Tracker
9Pixel Wafer Sensors
Second Submission SINTEF. Purdue
Wafer p-side
Wafer n-side
- 15 wafers delivered 06-12-02
- Tested at Purdue
- Irradiated at ?1015neq/cm2
- Testing of irrad. sensors has started
D/cms\project\base request\2003\sent dg.ppt
10FPix TBM Test Setup
DMill Dual TBM
Stacks
Controls
86 wire bond pads
TBM Test Fixture. Rutgers
Hub
Event Number
Status Info
TBM
Header ID
Trailer ID
D/cms\project\base request\2003\sent dg.ppt
11TOB - Prototype
First small sub-system (outer barrel rod)
equipped with modules
12Robotic Assembly at FNAL UCSB
- FNAL pick and place gantry
- Fully qualified for production
- Presently building modules as part of CMS M200
program - These were used in the May test beam study. CMS
was very happy with the SiDet quality. Ready to
go into production.
13ECAL H4 Test Beam
14ECAL Electronics
- Status of VFE Components
- FPPA Wafers Expected from Intersil on 20 December
02 -
- ADC ADI 9042 Agreed Qualification for Rad
Tolerance - Minnesota 18 day test cycle, neutrons ?s
- CMS must decide to procure ADC before Summer 2003
if FPPA fabrication is successful.
Yield for first 100 parts is 30. Not
affordable
15ECAL Electronics -II
- Status of 0.25µ Back-up VFE Electronics
- ADC Design progresses well at Chipidea
- Specification has been reviewed and agreed
(Power lt 500mW) - Intermediate Design Review December 6 in Lisbon
- Final Design review beginning January 03
- Fabrication early February 03
- MGPA Design progressing well at Imperial College
- Same time scale
US is contributing EDIA from the Yarema group for
evaluation and testing.
16HB Assembly
The assembly of absorber and scintillator tiles
for HB is now complete in SX5 1000 T of
precision detector. There are 2 years before
the next V33 ML1 for HB. On to the commissioning.
17HE-1 Assembly
HE calorimeter
Assembly finished No major problems or
delays Value added to US CMS brass procurement
18HF Fiber Stuffing
HF Assembly in Building 186. Moving ahead of
schedule. HF has caught up.
19HB ECAL Test Beam Layout
Calibrate 4 wedges 02. In May 03 use PPP to
study 40 MHz beam and HE/HB transition region. ME
will also need 40 MHz operation to verify all the
electronics chain. Then into SX5.
20300 GeV Pion H2
Bunch crossing number
The shape of the pulse in time is as expected
due to scint flours and HPD drift. NIM paper in
draft from TB 2002.
21HF in H2 Test beam
All mechanics of HB, HO, HE, HF is complete.
Future is with electronics at test beam and SX5.
22CSC Arrival at CERN
The Final Assembly and Test Sites are operational.
23CSC Installation
Demonstration at FNAL
Installing at CERN
24EMU Integration
- EDR for YE1 on 9,10 Dec
- Gas
- Gas racks in production
- Polish company (Mitek) will begin installing
piping in Jan 03 - Endcap drawings complete sent to Mitek
- Cooling
- YE2 manifold will be delivered in Dec 02
- Cable trays
- Recd bid from French company, will purchase
install in early 03
EMU installation waits on service in SX5. We will
need to push because we are first in the hall.
25Trigger - Receiver
- Full featured final prototype board is in test -
initial results are good. Continue to test
on-board ASICs copper link mezzanine cards. - Phase ASIC and BSCAN ASIC validated
- Moving towards full validation checking all data
paths, BX0 and error handling
Adder
PHASE ASICs
mezz link cards
MLUs
BSCAN ASICs
DC-DC
Top side with 1 of 8 mezzanine cards 2 of 3
Adder ASICs
Bottom side with all Phase Boundary Scan ASICs
26CSC Trigger Slice Test
- Requirements for 3-station 20 degree slice test
(9 chambers) - Need 3 MPC, 1 SP/SR, 1 CCB module, 1 backplane
- Integrate w/3 partially populated peripheral
crates 1 DDU - Schedule
- Apr-02 Prototype 2 designs done
- Nov-02 Prototype 2 construction done
- Apr-03 Prototype 2 testing done
- Sep-03 Final designs done
- CSC Sorter module only 1, design by Jan-04
- Not needed for Slice Test Itrigger out from CCB
- Oct-04 Production done
- Mar-05 Installation begins in USC55
- Slice Test Phase I
- Oct-03 to Oct-04
- Use Prototype 2 modules
- Slice Test Phase II
- Oct-04 to Mar-05
- Use Production Modules ( Proto. Sorter)
Trigger will participate in Slice Tests in 2004.
27DAQ TDR
- TDR submitted December 15, 2002
- 522 pages
- Describes baseline design for Data Acquisition
from Front End Readout through software
(High-Level) trigger
28Trigger Tables
- Level-1 Trigger at low luminosity (2?1033cm-2s-1)
- Total Rate 50 kHz. Factor 3 safety, allocate
16kHz
Tables exist for 1/5 and design L. Discovery
modes covered well. We think we know how to
trigger CMS and acquire the Physics.
29US-CMS Data Acquisition
- Next major milestone - Dec. 2003
- Event Builder Preseries and DAQ slice ready
- Work focussing on
- front end drivers and links
- integration and event building software
- event manager
This system will be used for the detector slice
tests (test beam?)
30Project Financial Summary
55 months of reporting. Note BA in FY06 (4.2 M)
and FY07 (1.3 M). CD4-a, CD4-b
31US CMS Detector Project
Contingency will be applied to scope if it is
earned. We hope next to apply scope to ECAL (1.7
M) and perhaps then increase scope to cover some
of CMS LV (lt1.5 M). Yarema, Beverly and Huffman
(FNAL EDIA) are estimating costs for the latter.
32Tracking Closely
We retain 49 contingency, or 19.12 M on our
ETC. The Project is 74 complete. It is crucial
not to be fooled. To that end, we brought NSF
tracking up to date (MRE end). We have also seen
other late charges items we announced were
closed and complete. A soft landing will be
hard to accomplish. It is getting harder as time
goes on.
33Lehman Review Dec. 2002
34HCAL - Electronics
35Project Complete -gt MO
MO begins with commissioning and preops in SX5
in FY03. Aim to end Project in FY05, with
completion in FY08 UX5 installation.
36Endgame and CD4
The US CMS deliverables will be 96 complete in
FY05 and finally installed in UX5 by FY07. The BA
has evolved to reflect this fact. Thanks to DOE
for adjusting CD4.
37Scrubbed MO
Added Tier-2 support (NSF) in Physics Analysis
centers. We would like to do more to support US
physicists doing analysis at their home
institutes or at a local PAC. There will be an
external review on April 8-10 of MO.
38US CMS MO Resources
Note the rolloff of construction to MO by FY05.
The major category for MO is physicists -gt base
program.
BaBar Reality check
39ML for RP V33
Tie points from Computing Systems DC Physics
TDR VCRs and PACs. The RP is a unitary plan to
do Physics in the U.S.
40CMS and the PRS Groups
The PRS groups are part of the detector groups
and part of the Physics Subsystem. The plan is to
tie Physics analysis to the detector builders and
to the analysis teams.
41Jet, MET Group and Physics TDR
Need to decide on a few Physics processes to
explore in depth for the Physics TDR qqH(WW),
SUSY ?? Then seed the Data Challenge data with
events from these reactions.
42G4 and Test Beam
The Jet/Met group is involved in analysis and
simulation of the test beam data
43LHC Physics in the US
In US CMS, planning is in place for a
collaboratory or virtual laboratory. Elements
are Virtual Control Room (commissioning, shifts)
and Physics Analysis Centers ( teleconf, analysis
groups). This support will go directly and solely
to US HEP physicists.
44Main US CMS SWC Activities
- Develop the US CMS T1/T2 system into a working
Data Grid - high throughput data transfers
- Grid-wide job scheduling
- monitoring
- Middleware is VDT Condor, Globus et al
- US CMS-developed DPE toolkit and procedures,
underlying the - standard CMS production environment (Impala,
RefDB etc) - Integration Grid Testbed (IGT) was very
successful first large-scale Grid - Next steps preparing the US CMS Production Grid
- Major coming milestones
- participation in the CMS 5 data challenge DC04
- be operational as part of LCG Production Grid
in June 2003 - Major development efforts are still needed for
those milestones - Providing a viable storage management solution
for multi-Terabytes data sets - building on dCache, SRM, etc
- End-to-end throughput with the goal of TBs/day
sustained rates from mass storage to mass
storage - Interfacing the Grid VO system to the local user
registration/security requirements - Consolidating the production system, data bases,
production configuration and meta-data systems
(MC_Runjob, catalogs, scheduling)
45FY02 Actual Costs of Work Performed
- FY02 BA and ACWP for US CMS SC
- (Numbers in italics are BCWS, as no invoices were
received for NSF-funded efforts)
46Accomplishments
- Prototyped Tier-1 and Tier-2 centers and deployed
a Grid System - Participated in a world-wide 20TB data production
for HLT studies - US CMS delivered key components IMPALA, DAR
- Made available large data samples (Objectivity
and nTuples) to the physics community - ? successful submission of the CMS DAQ TDR
- Worked with Grid Projects and VDT to harden
middleware products - Integrated the VDT middleware in CMS production
system - Deployed Integration Grid Testbed and used for
real productions - Decoupled CMS framework from Objectivity
- allows to write data persistently as ROOT/IO
Files - Released a fully functional Detector Description
Database - Released Software Quality and Assessment Plan
47USCMS Contributions to CMS Software
- Contributions to CMS Manpower in Computing and
Core Software (CCS) - CERN Members State contributions mainly coming in
through LCG AA - The U.S. is providing a fair share contribution
48US Contribution to CMS Production
- Contribution in events produced
- This is not a complete metric, but gives a good
indication - US CMS is providing a fair share of the CMS
resources forsimulations to support trigger and
physics studies
events high lumi pile-up
events simulated
49Grid Testbeds And Production Grids
- Grid Testbeds Research, Development and
Dissemination! - LHC Grid Testbeds first real-life large Grid
installations, becoming production quality - Strong Partnership between Universities, Labs,
with Grid (iVDGL, GriPhyN, PPDG) and Middleware
Projects (Condor, Globus) - Strong dissemination component, together with
Grid Projects - E.g. U.S. CMS Testbed
- Caltech, UCSD, U.Florida, UW Madison, Fermilab,
CERN
50High Level Milestones FY03
- Integration Grid Testbed deployed, running PRS
production - October 2002, Done
- SC2002 demonstration of Grid distributed
production and WorldGrid - November 2002, Done
- review of SC2002 demo, promotion and termination
- December 2002, Done
- Farm Configuration Definition and Deployment
- February 2003., being release now
- Fully Functional Production Grid on a National
Scale - February 2003, delayed by 1 Months due to lack of
available effort (but on track) - Migration of TestBed functionality to Production
Facilities - March 2003, in progress
- Start of LCG 24x7 Production Grid,
- June 2003 -- definition from the LCG/GDB has been
received during this month - Start of CMS DC04 production preparation, PCP04
- July 2003
- Running of DC04
- Feb 2004
51Resource Expectations for Data Challenge 04
52Bare Bones Plan Top-Down
- As a response to the revised funding guidance
defined a Bare Bones project plan -
- Continue to deliver SC engineering support to
CCSkeep this effort constant over the next 2
years, instead of ramping further - However, CMS Software is about 12 months behind
due to past severe understaffing - CMS needs the US (and CERN etc) man power to work
with the LCG Applications Area, - Contingencies if any will possibly develop in
course of joining forces with ATLAS et al - Ensure the US CMS system of Regional Centers is
ready for the Data Challenges(finally!) ramp the
Tier-1 effort to the required level of 13 FTE in
FY2003 - Starting at 6 FTE now, need to ramp to 13 FTE to
fully participate in the Data Challenges - The Bare Bones plan should enable US CMSto
become part in the LCG Production Grid
milestone during 2003 - Can participate in DC04 and 10 Data Challenges,
will try to pull in as much as we can from Grid
projects - Modest hardware procurements for Tier-1 and
Tier-2 centers - Typically 500k/year in FY2003, FY2004
- Need more (700k) in 2005 (latest) for
participation in 10 challenge, RC TDR - Start the deployment phase late in 2005
- Then need to start hiring or re-assigning
facility support people at the Tier-1 - Start pilot implementation of US Tier-2
53Conclusions on US CMS SWC
- US CMS SC Project is delivering a working Grid
environment, with a strong participation of
Fermilab and U.S. Universities - We need to do a lot more RD to build the system
for physics - Our customers (CCS, PRS and US CMS Users) are
happy (last time we were asking), but need and
want more support - US CMS is driving the US Grid integration and
deployment work - We have a unique opportunity to bring in our
ideas of doing science in a global and open
international and collaborative environment - Proposal to the NSF ITR solicitation to Globally
Enable Analysis Communities - That goes beyond the LHC and even HEP
- US CMS has shown that the US Tier-1/Tier-2 User
Facility system can indeed work to deliver
effort and resources to US CMS! - We definitely are on the map for LHC computing
and the LCG - With the funding advised by the funding agencies
and project oversightwe will have the manpower
and equipment at the lab and universities to
participate in strongly in the CMS data
challenges, - bringing the opportunity for U.S. leadership into
the emerging LHC physics program
54US LHC and the RP
US CMS has made a survey of intent. It appears US
CMS will grow by a factor 2 by FY07. In
addition, new groups will join before first
beam. We would like to have the flexibility to
plan for these additional physicists.
55Cost Estimates for the RP
The US CMS community has carefully estimated and
scrubbed the costs for the Research Program. The
US CMS community estimates that more support is
needed in FY07 and beyond. Present planning
within the guidance provided in the Budget
Authority delays RD for upgrades, slows the SWC
ramp up (bare bones), and reduces the contingency
fund to a level which limits management agility.
56Research Program - BA
NSF has given new guidance. Starting in FY03, the
NSF plan is to ramp to 12.5 M for US CMS in 5
steps of 2.5 M each. New DOE guidance helps 04
and 05. The scrubbed MO and bare bones SWC is
still tight in FY03. In FY04 we might be able to
increase SWC, add Tier 2 PAC support, etc.
57NSF MRE -gt Ops !
This is a great accomplishment and the investment
of NSF in the future shows confidence.
58P5 and the LHC Upgrades
Construction Projects
Research Program
P5
RD in support of Upgrades
e.g. Advanced Detector Research - Trigger
proposal for high L
Prepare TDR for major Upgrade of LHC and/or
detectors
59Issues
- The ramp up of the RP is crucial. FY03 and FY04
will either get us a good start on preparation
for Physics or we will drop the ball on Data
Challenges and the Physics TDR. - A firm commitment by NSF and DOE is absolutely
necessary if we are to plan rationally. The MO
Evaluation Group and SWC Reviews is a start.
60Summary
- US CMS is on schedule and on budget for the
Detector Construction. - CERN and CMS appear to be holding schedule. Beam
in 2007 with luminosity 1/10 design is quite
thinkable. - For the RP, CD4 is altered, BA is known up to
increments. The ML use the CMS schedule. Start
FY02 tracking of the RP under SOW agreements for
MO and SWC. The RP has been (over)scrubbed. - A cornucopia of Physics awaits us and we need to
be ready for the harvest.
61LHC Physics - Priority
HEPAP Subpanel on Long Range Planning Report puts
a high priority on the Physics of the LHC (all
quotes in this talk are from the Subpanel Report).
62LHC Computing Grids
The IT tools developed for LHC physics analysis
are and will be vital to the advancement of
global science. Grid computing will make a major
impact in many areas of business and commerce.
The leading role of LHC was recognized in the
HEPAP Subpanel Report.
63Results Silicon Pixel Sensors
New submission has improved average pixel
breakdown voltage by 200 V (before irradiation).
Purdue
Daniela Bortoletto Purdue University
NEW SUBMISSION
OLD SUBMISSION
D/cms\project\base request\2003\sent dg.ppt
64Brugge Winding Machine
Repaired and CMS cable completed
65US Tasks
20 cm
6,000 Tracker Outer Barrel (TOB)
modules constructed at FNALUCSB FNAL and UCSB
will have equal capabilities and capacity
66Test Setup CMS Pixel Readout
Computer Control Clock/Trigger
Generation. Early FEC Prototype
Readout Chip
VHDI
FPGA TBM
Power Distribution
Rutgers
D/cms\project\base request\2003\sent dg.ppt
67EB Bare Modules at CERN
68ECAL Transducers - APDs
65,000 APDs delivered from by Hamamatsu half-way
there. Testing, qualification and selection in
steady state. Rejection rate after delivery now
down to 3 from 7 for first 20,000.
69DA Q -EVB Demonstrator
EVB demonstrator in Lab 32 323211 PCs
(RUBUEVMRCS) Myrinet 2000 128 port Clos
switch GB Ethernet 64 port FastIron 8000
70US CMS387 Members from 38 Institutions
New groups - due to SiTrkr and ECAL scope
increases and other natural growth. FIT added.
FIU and Yale (Zeller) applying.
71NSF Summary for FY99-FY02
We have a plan of BCWS which, as yet, does not
saturate the NSF total BAC. We must work hard to
spend out the MRE in FY03.
HPD
ADC
Align
72Research Program - Upgrades
HEPAP Subpanel Report gives strong support to LHC
Upgrades. The present Budget Authority makes
strong Upgrade RD impossible in a timely
fashion. Note that an upgrade is a very cost
effective way to maximize the Physics output of
the pre-existing LHC complex
73LHC Physics and Upgrade
In general mass reach is increased by 1.5 TeV
(25 ) for Z, heavy SUSY squarks or gluinos or
extra dimension mass scales. A 20 measurement
of the HHH coupling is possible for Higgs masses
from 150 to 200 GeV. However, to realize these
improvements we need to launch the necessary
accelerator RD and maintain the capabilities of
the LHC detectors by upgrading them in a modest
fashion.
74NSF Tracking
NSF Tracking has been brought up to date. Since
the MRE ends in FY03, this is crucial progress.
This resulted in an EAC increase.
75 Extended Surface Phase
Additional costs part of C I
Objectives channel test of HV/LV burn-in of
electronics flushing gas readout test of ?10
of sub-detector (HB, HE, HO, HF,MB,ME, RB etc)
vertical slice tests with test-beam DAQ
prototype final DAQ
CMS supports the slice concept. CMS is taking
responsibility for the SX5 infrastructure. US CMS
will be doing MO in SX5 in 03
76Topics for Physics TDR?