The Tata Mundra Project - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

The Tata Mundra Project

Description:

4,000 MW greenfield coal-fired plant located near Mundra Port, Gujarat ... spots; impacted coastal area devoid of mangrove vegetation and coral reefs ... – PowerPoint PPT presentation

Number of Views:622
Avg rating:3.0/5.0
Slides: 12
Provided by: ifc
Category:
Tags: coral | mundra | project | tata

less

Transcript and Presenter's Notes

Title: The Tata Mundra Project


1
The Tata Mundra Project
2
Tata Mundra Project, India
3
Tata Mundra Project, India
  • 4,000 MW greenfield coal-fired plant located near
    Mundra Port, Gujarat
  • Indias first private sector power project using
    supercritical technology most energy efficient
    plant in the country
  • Awarded by Ministry of Power through tariff-based
    competitive bidding in December 2006
  • Levelized tariff of US 5.65 cents per kWh
  • Project cost of US4.2 billion to be financed by
    equity (US1 billion) and debt from IFC (US450
    million), ADB (US450 million), Korean ECAs
    (US800 million), local banks (US1.5 billion)
  • Will sell electricity to state-owned utilities in
    5 states Gujarat, Maharashtra, Haryana,
    Rajasthan and Punjab
  • First unit of 800 MW to be commissioned in July
    2011
  • Will import coal from Indonesia and other
    countries through the Mundra Port
  • Main equipment from Korea and Japan
  • Sponsor is Tata Power, Indias largest private
    sector power company with operating capacity of
    2,355 MW (1,838 MW in thermal, 457 MW in hydro
    and 62 MW in wind)

4
Electricity Demand and Supply in India
  • India is facing energy shortages of 11 of demand
    and even higher peak shortages of 14
  • Demand-supply gap is more acute in Western region
    (where 70 of the Projects power will be
    supplied) with energy deficit at 16 and peak
    deficit at 21
  • Capacity additions of 160,000 MW required in the
    next 10 years to satisfy Indias power needs
  • New capacity will need to come from a combination
    of coal, hydro, gas, nuclear and wind projects

Indias Installed Capacity (132,329 MW)
5
Indias generation alternatives
  • Natural Gas
  • Limited availability of indigenous gas high
    price of LNG
  • Gas shortages expected to persist despite new
    domestic production
  • Hydro
  • India has substantial hydro potential mainly in
    the North and Northeast
  • High capital costs, long gestation periods and
    ES issues
  • Run-of-river hydros affected by seasonality of
    rainfall
  • Wind
  • Intermittent nature makes wind unsuitable for
    large scale base load demand
  • India has a moderate wind regime with low load
    factors of 20-25
  • Nuclear
  • India has ambitious plans for nuclear power but
    faces many challenges
  • Coal
  • Domestic coal resources are abundant in Eastern
    India
  • Imported coal is reasonably accessible for
    coastal locations
  • Coal is a viable alternative for meeting base
    load demand

6
The Ultra Mega Power Plant (UMPP) Initiative
  • GoI made a comprehensive assessment of Indias
    future energy needs and alternatives for energy
    supply
  • Detailed consultation process with various
    stakeholders
  • Large scale capacity additions needed to address
    the countrys poverty alleviation agenda
  • Launched a program in 2005-06 to bid out 9 UMPPs
    of 4,000 MW each
  • Economies of scale and competitive bidding
    expected to benefit consumers through lower
    tariffs
  • GoI stipulated use of supercritical technology
    because it results in lower carbon emissions
  • Coastal Gujarat Power Limited is the first UMPP
    to be awarded in December 2006 financial closure
    required by April 22, 2008
  • Since then, two more UMPPs awarded to Reliance
    Power

7
Development Impact
  • Access to electricity is essential for reduction
    in poverty and improved health, education and
    economic development
  • Project will increase Indias generation capacity
    by 3 likely to impact about 16 million domestic
    consumers in the country and, hence, in line
    with our inclusive growth strategy for
    infrastructure
  • Creation of 5,000 construction jobs and 700 jobs
    during operations
  • Project will sell competitively-priced power at
    US 5.65 cents per kWh and provide affordable
    energy to consumers
  • First private sector project in India using
    supercritical technology most energy-efficient
    plant in India (40.5) compared to existing
    assets (about 27) therefore lower GHG
    emissions
  • Projects tax transfers of about US790 million
    to GoI
  • Growth in port and power transmission capacity
    will further create infrastructure and employment
    for the country

8
IFC Role Additionality
  • IFC requested by GoI to support this first
    private supercritical project in the country
  • IFC participated in pre-bid consultations to
    improve Projects bankability
  • Success is important to boost confidence of
    domestic international investors in Indias
    power sector
  • Project has significant risks due to size and
    complexity
  • First private project using supercritical coal
    technology in India
  • Significantly larger than any previous project by
    the sponsor, tripling its generation capacity
  • IFC played a key role in financial structuring on
    behalf of all lenders
  • IFCs presence contributes indirectly towards
    mitigation of political and regulatory risk
  • Project requires very long maturities (20 years)
    to achieve a low tariff for consumers
  • IFCs financing is critical to meet large debt
    financing needs
  • Local banks are providing significant debt but
    are unable to meet entire debt needs due to
    exposure limits
  • International commercial banks have limited
    appetite for long maturities because of
    refinancing risks and poor creditworthiness of
    state-owned offtakers
  • IFCs involvement requires CGPL to comply with
    more stringent ES standards than GoIs

9
Fit with IFCs Climate Change Strategy in the
Electricity Sector
  • India has few scalable alternatives to coal IFC
    encourages use of more efficient coal technology
    which results in lower carbon emissions
  • Project will have amongst the lowest GHG emission
    rates globally - lower by 40, 18 and 16
    compared to the average GHG emission rate of coal
    based plants in India, across the globe and OECD,
    respectively
  • First supercritical project sets a precedent for
    efficient coal usage consumes 1.7 million tons
    of coal less per year than traditional
    subcritical plants of comparable size
  • IFC support for this project will have a strong
    demonstration effect for other developing
    countries that need to develop coal-fired
    generation
  • Project may be eligible to sell carbon credits
    under the Clean Development Mechanism

10
Environmental and Social Issues
  • Environment Issues
  • Project site is sparsely vegetated with marginal
    cultivation remotely situated from eco-sensitive
    spots impacted coastal area devoid of mangrove
    vegetation and coral reefs
  • Robust air quality monitoring program by CGPL to
    evaluate conformity with IFCs and Indian
    National Ambient Air Quality Standards
  • Project will meet IFCs ES Performance Standards
    which are more stringent than those of GoI
  • Social Issues
  • No physical displacement resulting from Projects
    land acquisition
  • Key Livelihood Impact Loss of access to grazing
    land Company has developed a mitigation plan
    consistent with PS 5
  • IFC has confirmed Broad Community Support for the
    Project
  • Community development plan by Coastal Gujarat
    Power Limited to ensure accrual of Project
    benefits to the affected communities
  • IFC will closely monitor compliance with the
    agreed Environmental Social Action Plan

11
Risks Mitigants
  • Largest ever power plant in India with
    significant implementation risks including delays
    and cost overruns
  • Key technology supplied by reputable contractors
    at fixed price adequate contingencies and
    sponsor support for cost overruns and delays
  • Fuel supply risks from imported coal could expose
    Project to volatility in coal pricing
  • Long term coal supply contract at reasonable
    prices Coastal Gujarat Power Limited plans to
    further diversify coal sources
  • Delays in completing the requisite transmission
    lines and port infrastructure
  • Transmission port infrastructure developed by
    reputable companies with good track record
  • Off-take risks from poor creditworthiness of the
    state-owned utilities
  • Projects tariff is highly competitive ensures
    that state utilities are incentivized to pay
    power sector reforms progressing in most Indian
    states
  • Refinancing risks after 10 years of operations
    because of insufficiently long tenors from local
    banks
  • IFC and other foreign lenders providing long-term
    loans with 20 year tenor which will help mobilize
    other commercial lenders when needed
Write a Comment
User Comments (0)
About PowerShow.com