Title: Chapter 03 Project Management
1Operations Management
Chapter 3 Project Management
2Outline
- Global Company Profile Bechtel
- The Importance of Project Management
- Project Planning
- Project Organization
- Project Manager
- Work Breakdown Structure (WBS)
- Project Scheduling
3Outline - Continued
- Project Controlling
- Project Management Techniques Gantt Chart, PERT
And CPM - The Framework of PERT and CPM
- Network Diagrams and Approaches
- Activity-on-Node Example
4Outline - Continued
- Determining the Project Schedule
- Forward Pass
- Backward Pass
- Calculating Slack Time and Identifying the
Critical Path(s) - Variability in Activity Times
- Three Time Estimates in PERT
- Probability of Project Completion
5Outline - Continued
- Cost-time Trade-offs and Project Crashing
- A Critique of PERT and CPM
- Using Microsoft Project To Manage Projects
- Creating A Project Schedule Using MS Project
- Tracking Progress And Managing Costs Using MS
Project
6Learning Objectives
- Work breakdown structure (WBS)
- Gantt Chart, CPM and PERT
- AON Networks
- Forward and backward passes
- Critical path
- Variability in activity times
- Project crash
7Bechtel Projects
- Restoring over 650 oil wells in Kuwait left
ablaze or uncapped after Desert Storm - Building 26 massive distribution centers in just
two years for the internet company Webvan Group - Constructing 30 high-security data centers
worldwide for Equinix, Inc. - Building and running a rail line between London
and the Channel Tunnel (4.6 billion) - Developing an oil pipeline from the Caspian Sea
region to Russia (850 million)
8Bechtel Projects
- Expanding the Dubai Airport in the UAE (600
million), and the Miami Airport in Florida (2
billion) - Building liquid natural gas plants in Yemen 2
billion) and in Trinidad, West Indies (1
billion) - Building a new subway for Athens, Greece (2.6
billion) - Constructing a natural gas pipeline in Thailand
(700 million) - Building a highway to link the north and south of
Croatia (303 million)
9Strategic Importance of Project Management
- Bechtel Kuwait Project
- 8,000 workers
- 1,000 construction professionals
- 100 medical personnel
- 2 helicopter evacuation teams
- 6 full-service dining halls
- 27,000 meals per day
- 40 bed field hospital
10Strategic Importance of Project Management
- Microsoft Windows Longhorn Project
- hundreds of programmers
- millions of lines of code
- millions of dollars cost
- Ford Redesign of Mustang Project
- 450 member project team
- Cost 700-million
- 25 faster and 30 cheaper than comparable
project at Ford
11Project Characteristics
- Common, widely defined
- Single unit Uniqueness
- Team Work Well Organized
- Time / cost based
- Related activities in sequence(s)
- Difficult at planning
- Creativity Initiative, high labor skills
- Feedback Experience
12Management of Projects
- Planning - goal setting, defining the project,
team organization - Scheduling - relates people, money, and supplies
to specific activities and activities to each
other - Controlling - monitors resources, costs, quality,
and budgets revises plans and shifts resources
to meet time and cost demands
13Management of Projects
Figure 3.1
14Management of Projects
Figure 3.1
15Management of Projects
Figure 3.1
16Management of Projects
Figure 3.1
17Management of Projects
Figure 3.1
18Project Planning
- Establishing objectives
- Defining project
- Creating work breakdown structure
- Determining resources
- Forming organization
19Project Organization
- Often temporary structure
- Uses specialists from entire company
- Headed by project manager
- Coordinates activities
- Monitors schedule and costs
- Permanent structure called matrix organization
20A Sample Project Organization
Figure 3.2
21Matrix Organization
22The Role of the Project Manager
Receive highly visible, Responsible for making
sure that
- All necessary activities are finished in order
and on time - The project comes in within budget
- The project meets quality goals
- The people assigned to the project receive
motivation, direction, and information
23Work Breakdown Structure (WBS)
- Project
- Major tasks in the project
- Subtasks in the major tasks
- Activities (or work packages) to be completed
24Work Breakdown Structure
Figure 3.3
25Project Scheduling
- Identifying precedence relationships
- Sequencing activities
- Determining activity times costs
- Estimating material and worker requirements
- Determining critical activities
26Project Management Techniques
- Gantt Chart
- Critical Path Method (CPM)
- Program Evaluation and Review Technique (PERT)
27A Simple Gantt Chart
28Service for A Delta Jet during layover
Figure 3.4
29CPM and PERT
- Network techniques
- Developed in 1950s
- CPM by DuPont and Rand (1957)
- PERT by U.S. Navy (Polaris missile, 1958)
- Consider precedence relationships and
interdependencies - Each uses a different estimate of activity times
30Activity-on-Node (AON) Network Conventions
Activity on Activity Node (AON)
Meaning
A comes before B, which comes before C
A
C
(a)
B
A
A and B must both be completed before C can start
(b)
C
B
B
B and C cannot begin until A is completed
A
(c)
C
Figure 3.5
31Activity-on-Node (AON) Network Conventions
Activity on Activity Node (AON)
Meaning
C and D cannot begin until A and B have both been
completed
(d)
C cannot begin until both A and B are completed
D cannot begin until B is completed.
(e)
B and C cannot begin until A is completed. D
cannot begin until both B and C are completed.
(f)
32AON Example
Milwaukee Paper Manufacturing'sActivities and
Predecessors
Table 3.1
33AON Network for Milwaukee Paper
Figure 3.6
34AON Network for Milwaukee Paper
Figure 3.7
35AON Network for Milwaukee Paper
Figure 3.8
36Exercise
A
C
F
S
G
B
D
E
37Scheduling the ProjectCritical Path Analysis
Table 3.2
38Scheduling the ProjectCritical Path Analysis
Notation used in Critical Path Analysis
Figure 3.10
39Scheduling the ProjectCritical Path Analysis
Table 3.2
40ES EF are determined in Forward Pass
- ES Max EF of all immediate predecessors
- EF ES Activity time
41LS LF are determined in Backward Pass
- LF Min LS of all immediate following
activities - LS LF - Activity time
42Computing Slack Time
After computing the ES, EF, LS, and LF times for
all activities, compute the slack or free time
for each activity
- Slack is the length of time an activity can be
delayed without delaying the entire project
Slack LS ES or Slack LF EF
43Scheduling the ProjectCritical Path Analysis
Critical Path characteristics
- Critical path activities have no slack time
- The critical path is the longest path through the
network - The critical path is the shortest time in which
the project can be completed - Any delay in critical path activities delays the
project
44Computing Slack Time
Table 3.3
45Critical Path for Milwaukee Paper
Figure 3.13
46Exercise find the CP
A
C
F
S
G
B
D
E
47Exercise - Answer
A
C
F
S
G
B
D
E
48Variability in Activity Times
- CPM assumes one fixed time estimate for each
activity and there is no variability in activity
times - PERT uses 3 activity time estimates, by allowing
variability
49PERT Activity Times
???
- 3 time estimates
- Optimistic time (a)
- Pessimistic time (b)
- Most-likely time (m)
- Follow beta distribution
- Expected time t (a 4m b)/6
- Variance of time v (b - a) /6 2
50Computing Variance
Table 3.4
51Probability of Project Completion
Project variance is computed by summing the
variances of critical activities
s2 Project variance ?(variances of
activities on critical path)
p
52Probability of Project Completion
53Probability of Project Completion
PERT makes two more assumptions
- Activity times are statistically independent
- Total project completion times follow a normal
probability distribution
54Probability of Project Completion
Standard deviation 1.76 weeks
Figure 3.15
55Probability of Project Completion
What is the probability this project can be
completed on or before the 16 week deadline?
Where Z is the number of standard deviations the
due date lies from the mean
56Probability of Project Completion
What is the probability this project can be
completed on or before the 16 week deadline?
Where Z is the number of standard deviations the
due date lies from the mean
57Probability of Project Completion
15 16
Time (weeks)
Figure 3.16
58Probability of Project Completion
14 15
Time (weeks)
Figure 3.16
59Variability of Completion Time for Noncritical
Paths
- Variability of times for activities on
noncritical paths must be considered when finding
the probability of finishing in a specified time - Variation in noncritical activity may cause
change in critical path
60Six Steps of PERT CPM
- Define the project and prepare the work breakdown
structure (WBS) - Develop relationships among the activities -
decide which activities must precede and which
must follow others - Draw the network connecting all of the activities
- Assign time and/or cost estimates to each
activity - Compute the longest time path through the network
the critical path - Use the network to help plan, schedule and
control the project
61Questions PERT CPM Can Answer
- When will the entire project be completed?
- What are the critical activities or tasks in the
project? - the critical path - Which are the noncritical activities?
- What is the probability the project will be
completed by a specific date? - Is the project on schedule, behind schedule, or
ahead of schedule? - Is the money spent equal to, less than, or
greater than the budget? - Are there enough resources available to finish
the project on time? - If the project must be finished in a shorter
time, what is the way to accomplish this at least
cost?
62What Project Management Has Provided So Far
- The projects expected completion time is 15
weeks - There is a 71.57 chance the equipment will be in
place by the 16 week deadline - Five activities (A, C, E, G, and H) are on the
critical path, cant be delayed. - Three activities (B, D, F) have slack time and
are not on the critical path, can be delayed
(reallocate resource to crash CA) - A detailed schedule of activities with starting
and ending dates is available
63Cost-Time Trade-Offs Project Crashing
It is common to face the following situations
- The project is behind schedule
- The completion time has been moved forward
Shortening the duration of the project in the
cheapest way is called project crashing
64Factors to Consider When Crashing a Project
- Crashable activities or not?
- Critical activities or not?
- If the total crashing cost is cheapest?
65Crash and Normal Times and Costs
Figure 3.18
66Crashing The Project
Table 3.5
67Steps in Project Crashing
- Compute the crash cost per time period
- Using current activity times, find the critical
path - If there is only one critical path, then select
the activity on this critical path that (a) can
still be crashed, and (b) has the smallest crash
cost per period. (How about multi-CP?) - Update all activity times. If the desired due
date has been reached, stop. If not, return to
Step 2.
68Critical Path And Slack Times For Milwaukee Paper
Figure 3.19
69Advantages of PERT/CPM
- Especially useful when scheduling and controlling
large projects - Straightforward concept and not mathematically
complex - Graphical networks help to perceive relationships
among project activities - Critical path and slack time analyses help
pinpoint activities that need to be closely
watched - Project documentation and graphics point out who
is responsible for various activities - Applicable to a wide variety of projects
- Useful in monitoring not only schedules but costs
as well
70Limitations of PERT/CPM
- Project activities have to be clearly defined,
independent, and stable in their relationships - Precedence relationships must be specified and
networked together - Time estimates tend to be subjective and are
subject to fudging by managers - There is an inherent danger of too much emphasis
being placed on the longest, or critical, path