Title: LOUISIANA ENERGY SERVICES NATIONAL ENRICHMENT FACILITY ENVIRONMENTAL IMPACT STATEMENT
1(No Transcript)
2U.S. Nuclear Regulatory Commissions
Decommissioning Plan Review Process
- Rebecca Tadesse
- Branch Chief for Material Decommissioning
- Division of Waste Management and Environmental
ProtectionOffice of Federal and State
Materialsand Environmental Management
ProgramsU.S. Nuclear Regulatory
CommissionWashington, DC 20555
3Purpose of Todays Meeting
- Discuss the Decommissioning Plan review process
- Discuss Restricted Use decommissioning Option
- Answer questions regarding the Decommissioning
Plan review process
4Key Messages
- Protect Public Health and Safety and the
Environment - To Date No decision has been made about the site
- There will be ample opportunity for Public input
on the Decommissioning Plan
5Decommissioning Plan Review Process
- v Acceptance review (90 days)
- Technical review (1 2 years)
- Consider public comments
- Request for Additional information, if necessary
- Approval of the Decommissioning Plan via license
amendment
6Decommissioning Plan Contents
- Site radiological status (characterization)
- Planned decommissioning activities
- Plan to ensure protection of workers and the
environment - Planned final radiation survey
7Decommissioning Plan Contents
- Decommissioning cost estimate and funding
mechanism - Decommissioning Schedule
- Public input/institutional controls for
restricted use sites
8Public Awareness Activities
- Public Meetings
- Publicly-noticed meetings with the licensee
- Press Releases
- Federal Register Notices
9NRCs Restricted UseDecommissioning Option
- Public Meeting
- December 5, 2006
- Newfield, NJ
- Robert L. Johnson, Senior Project Manager
- Division of Waste Management and Environmental
Protection - Office of Federal and State Materials and
Environmental - Management Programs
- U.S. Nuclear Regulatory Commission
- Washington, DC 20555
10Outline
- What is restricted use?
- When is a site initially eligible?
- How is protection ensured?
- How is protection sustained?
- What is a long-term control license?
11What is restricted use decommissioning?
- NRCs regulations allow two options for
decommissioning - Unrestricted use
- Restricted use
- Restricted use
- Radioactive material remains onsite
- Institutional controls, engineered controls
provide protection
12When is a site initially eligible?
- Licensee required to justify
- Submit cost benefit analyses
- Compares removal costs to benefits
- Proposal must be as low as reasonably achievable
(ALARA) - ALARA is a universal concept in radiation
protection - Standard methods used
13How does restricted use ensure protection?
- Limit exposure to regulatory requirements
- Restrict adverse land uses
- Legal restrictions (institutional controls)
- Physical restrictions (fences, signs)
- Mitigate adverse natural processes (engineered
controls/cover) - Shielding cover limits radiation
- Erosion cover protects shielding
14How is protection sustained over long time
periods?
- Stringent regulatory requirements
- Defense-in-depth approach
- Institutional controls
- Legally enforceable
- Durable (State or Federal government)
- Engineered controls
- Robust designed for maximum natural events
- Reduce reliance on monitoring and maintenance
15How is protection sustained over long time
periods? (cont.)
- Defense-in-depth approach
- Licensee monitoring and maintenance
- Independent oversight and backup
- Sufficient funding (trust fund)
- Dose limit with institutional controls ¼ of
public dose limit) - Dose cap if institutional controls fail (public
dose limit)SAFETY NET
16What is an NRC long-term control license?
- An NRC legally enforceable and durable
institutional control - Last resort option for institutional controls,
independent third party - All restricted use requirements must be met
- Long term control is not a new concept
17What is a long-term control license? (cont.)
- License conditions require land use restrictions
and activities - Licensee responsible for restrictions,
monitoring, maintenance - NRC responsible for inspections, enforcement, and
backup
18Conclusions
- Stringent regulatory requirements for protection
of public health and safety - Shieldalloy must demonstrate compliance
- NRCs review will determine if requirements have
been met
19Additional Information
- NRCs Decommissioning Guidance, Vol 1, Rev 2
- Section 17.7 and Appendix M
- Web site http//www.nrc.gov/reading-rm/doc-colle
ctions/nuregs/staff/sr1757/v1/ - NRC conference papers (handouts available)
- Waste Management 05
- American Nuclear Society 06
20SHIELDALLOY METALLURGICAL CORPORATION
DECOMMISSIONING
- Information Meeting
- December 5, 2006
- Newfield, New Jersey
- Ken Kalman
- Project Manager
- Materials Decommissioning Section
- Division of Waste Management and Environmental
ProtectionOffice of Federal and State
Materialsand Environmental Management
ProgramsU.S. Nuclear Regulatory
CommissionWashington, DC 20555
21OVERVIEW
- Operations
- Decommissioning Plan Submittals and Review
- Decommissioning Proposal
- Projected Timeframe
- Get Information /Submit Comments
22Location of Shieldalloy Site
23Aerial Photo of Shieldalloy Site
24OPERATIONS
- 1955-1998 - Shieldalloy used niobium ore
(pyrochlore) - Contained natural uranium and thorium in
concentrations that we regulate - Licensed to possess uranium (45,000 kg) and
thorium (303,050 kg)
25OPERATIONS
- Generated slag (18,000 m3) and baghouse dust
(15,000 m3) containing uranium and thorium - August 2001 - Shieldalloy notified NRC that it
ceased operations and intended to decomission - Within its licensed limit for uranium and thorium
- Plans to sell slag and baghouse dust for uranium
content failed
26Northwest Corner of Slag Pile
27NRC Inspector Checking Exposure Ratesof Slag Pile
28Particulate Bags
29SUBMITTALS AND REVIEW
- Acceptance Review / Detailed Technical Review
- August 2002 - Decommissioning Plan submitted
- February 2003 - Decommissioning Plan rejected
- May 2004 - NRC provided interim guidance on Long
Term Control License to Shieldalloy
30SUBMITTALS AND REVIEW
- October 2005 - Revised Decommissioning Plan
submitted. - January 2006 - Revised Decommissioning Plan
rejected - Dose Modeling
- Surface Water Hydrology and Erosion Protection
- Long term Control Approach and Institutional
Controls - Financial Assurance
31SUBMITTALS AND REVIEW
- March 2006 - Open to the public meeting held to
discuss deficiencies - June 2006 - SMC submitted supplemental
information - October 2006 - Decommissioning Plan, as
supplemented, was accepted for detailed technical
review.
32SUBMITTALS AND REVIEW
- November 16, 2006 - Federal Register Notice
Opportunity to Request a Hearing (January 16,
2007) and comment (by March 16, 2007) - December 5, 2006 - Decommissioning Information
Meeting - December 12, 2006 - Environmental Impact Scoping
Meeting
33DECOMMISSIONING PROPOSAL
- 67.7 acres for metallurgical activities and 19.8
non-contiguous acres of unaffected farmland - Process area comprised of parking lots,
administrative offices, and manufacturing
buildings - Impacted buildings remediated for unrestricted
use
34Process and Warehouse Buildings
35DECOMMISSIONING PROPOSAL
- Storage yard contains slag, baghouse dust,
excavated soils and other similar materials - Slag (18,000 m3) and baghouse dust (15,000 m3)
contain uranium, thorium and associated decay
products. - Meets NRC exposure limits
36Thermoluminescent DosimeterSouthern Boundary
Fence
37NRC Inspector Checking Exposure Rates
38Monitoring Well
39DECOMMISSIONING PROPOSAL
- Shieldalloy considered license continuation,
offsite disposal and license termination, and
onsite stabilization and long term control - Cost/Benefit analysis indicated onsite
stabilization and long term control
40DECOMMISSIONING PROPOSAL
- Release most of the site for unrestricted use
- Consolidate licensable material in storage yard
- Minimize exposure with engineered barrier
- Long term maintenance and control
- Financial assurance
41DECOMMISSIONING PROPOSAL
- Shieldalloy dose analyses are 1 mrem per year for
unrestricted areas and 1-21 mrem per year for
restricted areas - Natural background radiation is 360 millirem per
year -
- NRC staff to review Shieldalloys estimates and
conduct an independent dose analysis
42PROJECTED TIMEFRAME
- 2007 - NRC staff completes its detailed technical
review and Safety Evaluation Report - 2008 - NRC staff completes Environmental Impact
Statement and licensing decision - 2011 Shieldalloy completes its activities (if
proposal is approved) - 2012 NRC completes licensing action
43INFORMATION
- Newfield Public Library
- NRC Public Web Page - http//www.nrc.gov
- Decommissioning Web Page - http//www.nrc.gov/info
-finder/decommissioning/index.html - Shieldalloy Web Page http//www.nrc.gov/info-fin
der/decommissioning/complex/shieldalloy-metallurgi
cal-corporation-smc-.html
44COMMENTS
- Request Hearing by January 16, 2007
- Submit Comments by March 16, 2007
- By mail at
- Chief, Rules and Directives Branch
- Division of Administrative Services
- Mailstop T-6D59
- U.S. Nuclear Regulatory Commission
- Washington, DC 20555-0001
- E-mail at ShieldalloyDP_at_nrc.gov
45