CIAP,Surplus, and non-constructed CWPPRA - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

CIAP,Surplus, and non-constructed CWPPRA

Description:

Involve CPRA Interagency Planning Team and Corps of Engineers in screening of ... Barataria Barrier Island Complex Project: Pelican Island and Pass Chaland to ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 11
Provided by: bil71
Learn more at: https://lacpra.org
Category:

less

Transcript and Presenter's Notes

Title: CIAP,Surplus, and non-constructed CWPPRA


1
Coastal Restoration Updates September 10, 2007

Louisiana Department of Natural Resources
2
CIAP Current Timeline
  • Governor submitted Plan to DOI Secretary and
    Minerals Management Service (MMS)
  • June 1, 2007
  • State began implementing several restoration
    projects included in Plan, using State funds
  • June 2007
  • MMS determined Plan to be complete initiated
    approval review
  • July 30, 2007
  • MMS approval of Plan anticipated State begins
    submitting CIAP grant applications to MMS
  • Late October 2007
  • Involve CPRA Interagency Planning Team and Corps
    of Engineers in screening of CIAP proposals

3
State Early Action Projects
  • ENGINEERING AND DESIGN
  • Violet Diversion
  • Freshwater Bayou Bank Stabilization
  • Mississippi River Sediment Delivery Pipeline
  • Bayou Lamoque Diversion
  • Orleans Land Bridge Shoreline Protection
  • Blind River Freshwater Siphon
  • CONSTRUCTION
  • East Grand Terre Island
  • Barataria Land Bridge Dedicated Dredging
  • Grand Lake Shoreline Protection
  • Beneficial Use of Dredged Material
  • GIWW Bank Restoration -Terrebonne Parish
  • Rockefeller Shoreline Demo
  • Lake Salvador, Phase III
  • Coastal Forest Conservation Initiative
    (Acquisition)

4
Surplus-Funded Restoration Projects
  • Biloxi Marsh (22M)
  • Caminada Headlands OR HNC Complex (40M)
  • Marsh Creation near Freshwater Bayou (4M)
  • Cameron Parish Shoreline (31M)
  • Beneficial Use Calcasieu Ship Channel (5M)
  • Pipeline Conveyance in Plaquemines Parish (22M)

5
State Restoration Projects
  • 44 projects completed 49.71M
  • Dedicated Dredging Program 2 currently under
    construction, Grand Bayou Blue (1.8M) and the
    Point Au Fer (2.5M) project
  • Mississippi River Reintroduction Into Bayou
    Lafourche (BA-25b) currently in design (184M)
  • Barrier Island Maintenance Program (BIMP)
    Engineering and design has been initiated on the
    first project funded through BIMP, the Bay
    Champagne Marsh Creation project (3.5M)

6
CWPPRA Projects
  • 143 active projects since 1991
  • 74 projects completed 625M 71,000 ac
    protected/restored 391,000 total acres benefited
  • 14 projects under construction, 7 designed, 48 in
    ED
  • 7 projects (183M) ready to construct but
    unfunded
  • 1991-2019 LA CWPPRA Funding 2.4B

7
Oyster lease Acquisition and Compensation Program
  • Leases Acquired
  • Bush Canal Bank Stabilization and Seabreeze
    Embankment Reconstruction Project Terrebonne
    Parish Consolidated Government (CIAP)
  • Shoreline Protection in Lake Borgne at Shell
    Beach and Bayou Dupre Project (PO-30) (CWPPRA)
  • Pending Leases Acquisition
  • North Lake Mechant Landbridge Restoration Project
    (TE-44) (CWPPRA)
  • Pass Chaland to Grand Bayou Pass Barrier
    Shoreline Protection Project (BA-35) (CWPPRA)
  • Barataria Barrier Island Complex Project Pelican
    Island and Pass Chaland to Pass La Mer Barrier
    Island Restoration project (BA-38) (CWPPRA)
  • Biological Survey Conducted
  • Morganza to the Gulf Hurricane Protection Project
    Terrebonne Levee and Conservation District (Other
    Agency Request)
  • Total Surveyed Acreage 27,633.4
  • Number of Leases Acquired 9
  • Pending Lease Acquisitions 49

8
Beneficial Use of Dredged Material
  • Large opportunity along Corps-maintained channels
  • State contributed 1.4M for Wine Island
    restoration near HNC
  • CIAP (20M), State surplus funds (5M) and LCA
    funds (100M) to be available
  • State, Port of Lake Charles, Calcasieu Parish,


    Corps, and landowner working to restore
    marsh near Calcasieu Ship Channel using CIAP and
    State surplus funds

9
SCIENCE
  • LCA ST Program
  • Support the science and technology necessary to
    effectively address coastal ecosystem restoration
    needs and provide analytical tools, programmatic
    and project-specific reviews, and recommendations
    for studies to investigate scientific and
    technological uncertainties
  • FY 06 7M FY 07 5M
  • Coastwide Reference Monitoring System- Wetlands
    (CRMS-Wetlands)
  • To date, 371 sites have been visited and
    characterized and approximately 176 sites are
    fully operational and collecting all data
    parameters
  • 20.3M in funding authorized through FY 2010
  • Barrier Island Comprehensive Monitoring (BICM)
  • Completed Coastal post-storm assessment video and
    photography
  • Complete Coast-wide Shoreline Erosion Rates for
    Historic, Long-term, Short-term, and Near-term
    Time Periods (1880s, 1920s, 1980s, 2004, 2005)
  • Completed Bathymetric Surveys for sandy
    shorelines (Sabine to Mermentau, Raccoon Island
    to Sandy Point, and Chandeleur Islands)
  • Completed LiDAR Surveys for sandy shorelines
  • 0.5M yearly

10
Coastal Use Permit Streamlining
Processing time for all permits reduced by 51
(59.9 days to 30.6 days) between 2002 and 2006.