Title: HSC development in Taiwan
1 HSC development in Taiwan
- Shiang-Yu Wang (???)
- Institute of Astronomy and Astrophysics Academia
Sinica
2Background
- Instrumentation capability is one of the major
research topic in ASIAA - Development of WIRCAM in CFHT successfully
finished in 2005 - Long term relationship with Japan
- Promote collaborations in Asian region
- Discussion with Subaru began in 2006
3Hyper SuprimeCam
HSC fits IAAs interests both in the science and
technical sides
4Our Role in HSC
- Mechanical Shutter
- Filter exchanger
- CCD emulator?
- Optical and Mechanical components?
Tight space and weight limits of the HSC makes it
challenging
5Specifications for shutter
- Time Repeatability 1
- Time Accuracy 0.01 s
- Shortest exposure time 1s
- Maximum Speed 800 mm/s
- Operation Temperature -10 to 10C
- Weight 25Kg
- 15mm thickness at shutter body and 120mm diameter
of the drums
6(No Transcript)
7(No Transcript)
8Major activities in IAA
- Extract system design and specifications form
Subaru last June - HSC team formed in IAA
- ARL to be the major contractor for the two
systems - Fabric material purchased for strength test
- Regular meeting with ARL
9Aeronautical Research Lab. (ARL)
- Government funded Military research laboratory
- Major jet fighter development center in Taiwan
- Long term collaboration on the SMA project with
good partner spirit. - Main contractor carrying out the ALMA EA FEIC.
10Shutter design
11COVER
SCREEN
FRAME
DRUM
12(No Transcript)
13SHUTTER DESIGN CONCEPT
14(No Transcript)
15(No Transcript)
16Shutter weight estimation
1 FRAME SH0012 1 AL 5.772 5.772
2 MOTOR HT3005 2 2.190 4.380
3 SHAFT SH0001 2 STEEL 1.209 2.418
4 SCREEN SH0016 1 FIBER 1.800 1.800
5 COVER SH0015 1 AL 1.349 1.349
6 ROLLER-IDLE SH0013 2 TEFLON 0.256 0.512
7 DRUM-UPPER SH0004 4 AL 0.212 0.848
8 COUPLING FAMM-L40 2 AL 0.13 0.260
9 TORQUE-METER QWLC-8M 2 STEEL 0.128 0.256
10 DRUM-RIGNT SH0003 2 AL 0.100 0.200
11 OTHER 1.342
TOTAL 19.137
17Projected Milestones
- Shutter components ready in March
- Prototype of shutter system to be finished in
May. - Detailed interface defined in May.
- System fabrication starts in late 2008.
- Ready for delivery in early 2010.