Title: Victorias proposed DESALINATION plant
1Victorias proposed DESALINATION plant an
energy guzzling, climate changing, ecosystem
altering water factory catch the
water falling on Melbournes roofs - Bob Brown,
Nov 18, 2007.
Desalination should remain the last resort, and
should only be applied after cheaper alternatives
in terms of supply and demand management have
carefully been considered. - World Bank
2A long way to the power stations
A long way to Melbourne
3Strong local concern
1200 at Stand in the Sand
Y.W.Y.S. Formed
- To force government, via political pressure, to
follow due process by - Providing evidence based rationale as to why they
have chosen the most expensive and polluting
solution to securing Victorias water future. - Choosing the most economically and
environmentally responsible solution to securing
Victorias future.
4(No Transcript)
5This particular water supply option
FOR 150 billion litres...
Acceptable environmental damage ??? 5 000 000
000. 1.1 million tonnes CO2 annually.
- While 700 billion litres of stormwater and
wastewater are wasted - that CAN be collected at a FRACTION of those
costs - Recycling
- Stormwater collection
- Water tanks
- Efficient appliances . . . .
6Population increase and climate change have not
been addressed in terms of new water
infrastructure for decades. Government must now
secure water supply. The governments Water
Plan is to have 225 gigalitres of new water come
on line within two and a half years. This
represents an additional 60 more water than we
are currently using in homes, leekage and
industry. Is this Justified ?
7 But lets consider the State Governments
obligations - What is the problem and
what is the corresponding need
8So under the current level of drought and climate
change we need an additional 64 gigalitres per
year, 65 GL to stop the dam levels falling
9 64 GL to stop the dams falling under
drought,but we need to cover greater use by an
expanding population, and for river health we
cant be taking so much from our streams. 69 GL
will cover reasonable consumption of the
additional population over the next decade, even
if population continues to increase at the
current extreme rate. 32 GL returned to our
rivers and streams will give them a chance.165
GL then is a reasonable level of augmentation to
greater Melbournes water supply over the next
few years. The component for
population increase will not all be used before
the end of the decade and can be used to boost
dam levels.
10Even the State Governments own analysis, done
through DSE indicates a similar figure with 175
gigalitres of augmentation seeing dams filling in
2015/16 and then no return to restrictions until
at least 2060. The danger is that if this
augmentation comes from the most costly options,
both for our environment and the hip pockets of
consumers, then there will be no room for the
implementation of the more sustainable water
supply options for possibly decades.
11(No Transcript)
12Watershed shows there are solutions
At between 1/3 and1/2 the construction cost
At 1/4 the ongoing cost of water
And at 1/5 the carbon emissions
13Why was desalination chosen?
- Population and climate change effect on supply
- - 2006 failure of spring rains - PANIC
- - No augmentation to supply since Thomson Dam
completed in 1983. - Easy option for Government
- - Guarantee of supply
- - Hand over to PPP and wash hands of water
supply. - Lack of opposition
- - Non Labor electorate and long way from
Melbourne - - Far enough from next election if act quickly
- - Opposition parties would like water problems
solved before they come to power.
14No Electoral mandate to build a desalination
plant on the Bass Coast
- Pre election desalination was scoffed at by Labor
- They worked with Melbourne Water, water experts
and the universities to develop a Sustainable
Water Strategy - Post election this was turned on its head and
the new Water Plan was announced with
desalination and the N-S pipe as a done deal.
15Getting the message out there
- Very difficult to get traction in Melbourne
- Group considered to be NIMBYs
- Experts and academics reluctant to speak out as
their jobs and funding all comes from Government - Millions of Government dollars go into
advertising their plan as an essential - We are a small group, a long way from Melbourne,
with few funds - Government WILL NOT DEBATE THE ISSUES
16COURT ACTION
Community Group - Your Water Your Say - Crushed
- YWYS challenged the Federal Governments
- decision to exclude
- pilot plant and preliminary site works
- climate change through greenhouse emissions
- migratory species like toothed whales and birds
- from the Environmental Effects Study.
17E.E.S.
- There was initially no commitment to undertake an
Environmental Effects Study - After a huge number of submissions an E.E.S. was
commited to - Scope of the study restricted to exclude
alternatives, greenhouse implications or whales
and migratory species - The community is given no funding or assistance
to have quality input to the process - Your Water Your Say cannot participate
18Another Community Group forms to advocate for
better water supply options for Greater Melbourne.
To force government, via political pressure, to
follow due process by Providing evidence based
rationale as to why they have chosen the most
expensive and polluting solution to securing
Victorias water future. Choosing the most
economically and environmentally responsible
solution to securing Victorias future.
19Why we oppose this desalination project
- excessive scale that will exclude the
- better alternatives
- environmentally unsustainable
- economically prohibitive
- socially destructive
- a last resort solution that is
particularly poorly suited to Melbournes
situation.
20Alternatives to desalination.
- Stormwater capture, treatment and use either as
lowgrade or highly treated water replacement - Rainwater tanks capturing water into locally
built and installed tanks and plumbing - River peak flood diversion to storages (having
benefits to irrigators downstream) - Recycling waste water such as the Eastern
Treatment Plant to industry, agriculture, parks
and gardens - Desalination of brackish water uses less than one
third the energy and can often be done where the
water is needed avoiding pumping costs
21Desalination ALTERNATIVE OPTIONSRainwater Tanks
- Marsden Jacobs Report.
- Rainwater tanks collect and store water far more
efficiently than dams, especially in times of
drought. As the climate changes we should be
installing tanks to take advantage of the rain
that does fall on our rooftops. - Rainwater tanks are cost competitive with dams
and desalination plants. - Rainwater tanks are five times more energy
efficient than desalination plants. - in Melbourne 72 per cent of existing houses have
potential for a rainwater tank.
22Desalination ALTERNATIVE OPTIONSRainwater Tanks
Annual yield from a 5,000 litretank in Melbourne
for a 200 m2 roof collection area 86,000 litres
(235 litres / day).
End cost per 1,000 litres water Rainwater Tank
1.07 Desalination 3.00
23Desalination ALTERNATIVE OPTIONSRainwater Tanks
- Industry Benefits
- Rainwater Tank Industry
- Pump Industry
- Plumbing Industry
- IF Desalination international industry benefits
at the expense of the above local industries
24- Desalination ALTERNATIVE OPTIONS
- Regional Storm Water Collection
Professors Barry Hart and Chris Walsh Potential
for collecting over 200 Gl per year.
25Desalination ALTERNATIVE OPTIONSRecycling
- Eastern Treatment Plant
- Only 45 per household
- Protects Gunnamatta Beach
- Latrobe Valley Diversion
- Increase Yarra River Flows
- Will deliver over 100 Gl per year
26Desalination ALTERNATIVE OPTIONSRecycling
- Grey Water Systems (Home Use)
- Consumption 32 toilet, 33 shower, 23 laundry.
- Saves 350 l / household per DAY.
- For Garden Use.
27Desalination ALTERNATIVE OPTIONSConservation
- Melbournians use nearly 300 litres / person / day
c.f. SE Qld Europe (150). - Desalination PROMOTES wastage
28Desalination ALTERNATIVE OPTIONSCessation of
Catchment Logging
- 30 Gl / year can be saved by cessation of logging
in Thomson and Yarra Catchments
29Desalination ALTERNATIVE OPTIONSNew Supplies
- Dams / Connectors
- River peak flood diversion to storages
- (Rainfall PATTERNS have changed)
- Tasmanian Pipeline
30Desalination ALTERNATIVE OPTIONSAPPROPRIATE
Desalination
- EMERGENCY POINT OF USE MOBILE SUPPLY.
- SHIPS
- CONTAINERS
- NOT a 30 YEAR contract with profits flowing
overseas at the expense of OUR environment.
31The irrational justification
- We need a rainfall independent water source
- The power generation for the plant will be offset
through renewable energy credits - Despite REPEATED requests, no research or
scientific explanation for the above throwaway
lines has ever been produced.
32The Carbon Neutral HOAX
- Where there are alternatives (as there certainly
are in this case), offsetting carbon emissions
through offsite green power production or through
carbon credits is an irresponsible abuse of the
goals of such schemes that aim to reduce
necessary carbon emissions rather than being a
justification for new (but avoidable) polluting
industry.
33CLIMATE CHANGE NIGHTMARE.
- The 100 mW plant and its 25 mW pumping costs will
produce an estimated massive 1 200 000 tonnes
of carbon emissions every year, 285
000 new cars! - While there are environmentally friendlier
alternatives, this is absolutely irresponsible
and incongruous with recent federal government
commitments to reducing emissions by 60 by 2050! - New opinion is that that figure must be 90 to
avoid climate catastrophe.
34(No Transcript)
35Environmental Issues.
- Lack of detail.
- Issues relating to EES / Controlled Action.
- Because of the decision to procure the plant
through a public-private partnership arrangement,
the final location, layout, size, form and
materials of the plant will not be finalised
until after the selection of the private
provider. - Assessment of Matters of National Environmental
Significance (EPBC Act) for the Desalination
Project (Biosis Research, 12 December 2007),
Section 1.1.1
36- At present, it is not possible to specifically
address all potential impacts of the proposed
project as details of the site design are yet to
be determined. These include details of the area,
dimensions and location within the study area of
the facility footprint construction techniques
ongoing operational requirements adopted or
potential mitigation measures and possible
impacts beyond the facility itself. When these
details have been fully resolved, the
implications on flora and fauna will be able to
be addressed specifically and thoroughly for the
facility and the remainder of the study area. - Preliminary Flora and Fauna Assessment
Desalination Plant, Bass Coast, Victoria Impact
Assessment Report, Biosis Research, November 2007
(Report 4 , EES Referral)
37- At present, it is not possible to specifically
address the potential impacts of the proposed
route as details of the design are yet to be
determined. These include the precise alignment,
proposed construction techniques within each
section, adopted or potential mitigation
measures and possible impacts beyond the
pipeline route (e.g. downstream) itself. When
these details have been fully resolved, the
implications on flora and fauna will be able to
be addressed specifically and thoroughly for the
pipeline. - Preliminary Flora and Fauna Assessment
Desalination Plant Transfer Pipeline Corridor-
Wonthaggi to Cranbourne, Victoria, Biosis
Research, November 2007 (Report 5 , EES Referral)
38Heritage
- 14 identified Aboriginal heritage sites
- No Cultural Heritage Management Plan
- Archaelogical Sites
- Register of the National Estate
39(No Transcript)
40Entrainment
- The passive capture and death of organisms
- 14 000 litres water / second 350 000 per second
- Loss of Biomass base food chain organisms
- Poor Mixing / Cumulative effects
- Disposal problems / further greenhouse emissions
- ENTRAPMENT
41Effluent
- Salt
- Biocides
- Cleaning Agents
- Heavy Metals
- Dead organisms
- POOR MIXING
Local Ecosystem Alteration Pest species risk.
42Why else is this wrong?
- Public Private Partnership
- Economics
43The Public Private Partnership
- The MOST expensive way to deliver projects.
- GUARANTEES full operation even WHEN there is
cheaper available catchment water. - Ownership of infrastructure to international
companies reduces control of our essential
services
44Economic Arguments.
- How much will the end user pay?
- Up to 4 - 5 times current water costs
45Economic Arguments.
- Desalination is THE most expensive alternative
- PPP means control of our water is handed over to
largely foreign owned consortium - Short term construction jobs will be the only
bonus to area. Long term jobs numbers will be
similar to a small supermarket
- Economic Report prepared for DSE indicates the
majority of labor involved will NOT be from
Gippsland.
46Economic Arguments.
The Australian Financial Review (Mar 26, 2008) By
PETE HEININGER... According to one of
Australias leading independent water experts, Dr
Peter Coombes, taxpayers need to know how much
they can expect to pay for water once formal
carbon trading schemes and carbon taxes are in
place, and desalination plant operating costs,
including the costs of transporting water to
cities, have been properly counted. We also need
to ask what implications these carbon footprints
will have on Australia reaching its planned 60
per cent cut to greenhouse gas emissions by 2050.
47Ten year of drought continuing - Current policy
is a mix of pre election Central Region
Sustainable Water Strategy and the New Plan,
Our Water Our Future.
48Thompson Dam rainfall Runoff
49Melton rainfall
50Yarra Ranges rainfall
51Geelong Rainfall
52Glen Eira rainfall