Title: Offshore Wind Power: The European Experience
1Offshore Wind Power The European Experience
- Bill Bulpitt, Mary Hallisey Hunt, Susan Stewart
- Georgia Tech Strategic Energy Institute
- Southeast Regional Offshore Wind Power Symposium
- February 27, 2007
2Offshore Wind Deployment in Northern Europe
- Two phases
- Series of small demonstration projects built in
sheltered shallow water (1991 1999) - Larger projects of increasingly commercial nature
built in more challenging situations (between
2000 present)
3European Experience
www.offshorewindenergy.org
red (built Mm windturbines), purple(built
small windturbines), blue(under construction),
grey(planned)
4European Wind Farms
5(cont.) European Wind Farms
6Offshore Wind Development Drivers
- Europe imports 50 of energy needs
- Projected to be 70 within two decades if changes
not implemented - Looking for indigenous energy source free of
social economic disadvantages associated with oil
and gas - Kyoto
7Onshore Market Limited
- Less land available
- Greater and more consistent resource available
offshore
8European Policy Instruments
- Feed in Tariff
- Bidding
- Green Certificates
- Green Pricing
9Main Instrument Feed-in-Tariff
- Guaranteed (by law) power purchase price to be
paid by local utility - Ex. Germany
- Fixed Tariff 6-8 cent/kWh, depending on
location (offshore up to 9 cent/kWh) - Pool price 3-4.5 cent/kWh
- Wind costs 5-6 cent/kWh _at_ 6-7 m/s
- Utilities have to pay feed-in tariff and have to
connect
10Instrument Fixed Quotas Combined with Green
Certificate Trading
- Government introduces fixed quotas for power
retailers - Producers of renewable power receive certificates
- Retailers must buy certificates
- A market for renewable power is created!
- Netherlands, Sweden, UK, etc.
- (Similar to Renewable Energy Portfolio)
11Policy Drivers
- Shared agenda across governments departments
instrumental in successful policy development - Stable framework supported start-up incentives
for projects and encouraged investment
12Why Offshore Wind Advanced
- Ultimately, onshore wind will face practical and
social limits - Potential capacity factor that can be achieved is
much greater offshore - Offshore incentives and government pressure to
fulfill alternative energy targets
13Motivations Vary by Country
- Denmark
- Germany
- United Kingdom
- Ireland
- Belgium
14Policy Synthesis
- Danish experience most advanced 20 of
electricity generated from wind - Other countries proceeded in parallel, not
replicating Denmark, but meeting their own
socio-political demands - As yet, no formal attempt to benchmark
experiences in offshore wind, but some common
themes emerging
15Common Themes in Offshore Wind
- Stable policy framework
- Provides incentive and encourages investment
- Plan for identifying strategically important
locations - Strategic Environmental Assessment (SEA)
Directive was established by the European Union
in 2001 - Initial efforts need targeted support measures
from government - Absence of specific market for offshore wind has
not prevented offshore wind projects, but it has
caused delays
16Danish Offshore Wind - Key Environmental Issues
- Study based on 8 years of scientific research at
two largest offshore wind farms in worlds (Horns
Rev Nysted) - Pre and post construction studies conducted
17Overview of the Danish Monitoring Program
- Sea mammals harbor porpoises and seals
- Fish
- Birds
- Hydrography
- Coastal effects
- Artificial reef effects
- Socioeconomics
- Community acceptance
- Noise emissions
- Temp. gradients around cables
- Electromagnetic fields
- Benthic fauna
- Viewshed
18Results of Danish Study
- Attitudes in neighboring coastal communities
largely positive - Support growing as pre-construction worries of
drop in tourism have evaporated as people
realized this had not occurred after the wind
turbines were in view - Virtually no negative impacts to birds, marine
mammals or fish - Strong avoidance behavior of birds
19(No Transcript)
20European Offshore Wind Project Detail
21 Arklow Bank Arklow, Ireland
22Project Statistics
- Turbines 3.6MW x 7
- Depth of piles 35-45m
- Weight of piles 280tonne (5m diameter)
- Weight of turbines 290tonne
- Blades 50.5m, 15tonne each
- Nacelle/Hub height 73.5M
- Rotational speed 8.5 15 rpm
- Distance offshore 10km
- Onshore cable 5km
- Voltage 38kV distribution connected
- Rotor diameter 104m gt soccer pitch area
- 25MW serves 16,000 households (Irish)
- Sandbank 24 miles long 2.5 wide, depths 3 -20 m
- Largest commercially operating turbines installed
to date - Largest consented offshore site todate
Source McAdam
23Arklow Bank Site Details
- 60 km south of Dublin
- 7 - 12 km from coast
- 24 km long 2.5 km wide
Arklow
24Arklow Cable Routing
Source Airtricity
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33Arklow Sand Characteristics
Source Airtricity
34(No Transcript)
35(No Transcript)
36Arklow Turbine FoundationSource Airtricity
37Scroby Sands WindfarmNorfolk, England
38Scroby Sands
- Country United KingdomLocation East Anglian
Coast, 3km east of Great YarmouthTotal Capacity
60 MWNumber of Turbines 30Distance to Shore
2.5 kmDepth 4-8 mCapital Costs about 110
million EuroStatus BuiltConstruction Date
2003Manufacturer VestasTotal Capacity 2
MWTurbine-type V80 - 80m diameter/ 60m
hubheightMean Windspeed 7.5 m/s Windfarm
Developer E.ON UK
39(No Transcript)
40(No Transcript)
41(No Transcript)
42(No Transcript)
43 Siemens/BonusPrototype Factory
44Wind Facility Locations
Siemens Facility Locations
Hovsore
Brande
45(No Transcript)
46(No Transcript)
47(No Transcript)
48(No Transcript)
49(No Transcript)
50Horns Rev Wind FarmDenmark
51Horns Rev
- Country DenmarkLocation West CoastTotal
Capacity 160 MWNumber of Turbines 80Distance
to Shore 14-20 kmDepth 6-12 mCapital Costs
270 million EuroStatus Operational
Construction Date 2002 Manufacturer
VestasTotal Capacity 2 MWTurbine-type V80 -
80m diameter / 70m hubheightMean Windspeed 9.7
m/sAnnual Energy output 600 GWhWindfarm
Developer Elsam http//www.hornsrev.dk/Engelsk/d
efault_ie.htm
52(No Transcript)
53(No Transcript)
54(No Transcript)
55(No Transcript)
56Thank You
- bill.bulpitt_at_energy.gatech.edu
- mary.hunt_at_energy.gatech.edu
57Supporting Information
58Denmark
- Government in power from 1991-2001
(Social-Democratic) had strong environmental
agenda - A Public Service Obligation was realized by the
(then) nationalized utilities - Action Plan for offshore wind was published in
1997 after realizing onshore sites were limited - In 1999, electricity liberalization caused a
rethinking of the way utilities in a now
competitive market developed wind farms - A public tender for construction was introduced
and put forward by the new conservative coalition
in 2001
59Germany
- Under a feed-in tariff, offshore wind receives a
higher per kWh price than onshore wind - this will begin decreasing 2 per year in 2008
- Stable framework conditions and expected cost
reductions were commended by developers - Environmental and employment benefits were
highlighted to public
60United Kingdom
- Wide belief that offshore wind would be necessary
to meet government targets for limiting fossil
fuel production - Government sought to provide a national framework
via the Crown Estates Round 1 in call for
offshore wind farms December, 2000 - Industry response to Round 1 was higher than
expected - Government support of Round 2 was more pro-active
and supportive of offshore wind
61Ireland
- Similar to UK in terms of first priority was to
develop a framework for offshore wind - Government developed a consent regime based on
existing legislation - Progress slow due to grid constraints, limited
specified market, and no political preference for
offshore wind - New feed-in tariff may promote progress
62Belgium
- Utilities obligated to procure renewable energy
- Progress due primarily to superior offshore wind
resource potential -