Contractors Outreach Meeting August 31, 2005
2
Introductions
  • Janet Adams
  • SFOBB East Span Project Manager, Caltrans

3
Welcome
  • Bijan Sartipi
  • District 4 Director, Caltrans

4
Welcome
  • Olivia Fonseca
  • Deputy Director
  • Civil Rights Program and Small Business Advocate

5
SFOBB Self-Anchored Suspension Span Contract
  • Janet Adams
  • SFOBB East Span Project Manager, Caltrans

6
San Francisco - Oakland Bay Bridge
7
Contract 04-0120F4
  • This contract constructs the self-anchored
    suspension portion of the new East Span
  • Advertised on 8/1/05
  • Bids open on 2/1/06
  • Estimated cost is 1,450,000,000
  • Project funded by Toll revenues and State funds,
    therefore Buy America is not required
  • Contract duration is 2130 working days (7
    days/week)

8
Contract 04-0120F4
  • Contract consists of the following components
  • Two steel orthotropic box girders and decks
  • Steel tower consisting of 4 tower shafts with
    elevator
  • Concrete cap beam at Piers W2 and E2
  • Steel bike path
  • Steel prefabricated parallel wire strand cable
    system
  • All steel fabrication will be off-site

9
Self-Anchored Suspension Span
10
SAS and Skyway
11
View from Yerba Buena Island
12
District Contracts
  • Bob Finney
  • Deputy District Director - Construction

13
Fiscal Year 2005 - 2006 Construction Workload
(1000s)
14
North Counties
Upcoming Projects
Napa 29 - St Helena Roadway Rehabilitation
Napa 121 Replace Tulucay Bridge
SON 101 Steele Ln IC
Son 101 HOV SR 12 Steele Ln
Mrn 101 Blithedale Off-Ramp
Mrn 580 RSR - Polyester Deck Overlay
Mrn 101 HOV Central San Rafael
15
Richmond San Rafael Bridge Polyester
Deck Overlay
041521 Complete Bridge
Deck Overlay, Deck joint
Cost 18.6 M Adv Dec. 2005
16
Marin 101 HOV Gap Closure Central San Rafael
226151 Mrn 101 HOV
Widening Central San Rafael Cost 42.5
M Adv Oct. 2005
17
East Blithedale
Off Ramp
2937U1 Mrn 101
E. Blithedale Off Ramp Cost 5.8 M
Adv Feb. 2006
18
Napa 29 St. Helena Roadway
Rehabilitation
Project Limit Bale Lane
  • Rehabilitate Roadway
  • Curve Improvements
  • Super elevation Correction
  • Shoulder Widening
  • Drainage Modification
  • Digout and AC Overlay

128471 Napa 29 Pavement
Rehabilitation Cost 4.7 M
Adv Sept. 2005
St Helena
Project Limit York Creek Bridge
19
Sonoma 101 HOV Widening Route 12 -
Steele Lane
Auxiliary Lane - Steele Lane - College Avenue
Route 101 Widening Bicentennial Way - Earle
Street OC
College Ave. Bridge Replacement and I/C
Modification
Santa Rosa
6th Street New Undercrossing
4th Street Bridge Widening
Santa Rosa Creek Replace Bridge
Soundwall
Route 12 / 101 I/C Ramp Modification
245411 Son 101 HOV Route
12 to Steele Lane Cost 52.1 M
Adv Sept. 2005
20
Sonoma 101 HOV Widening Steele Lane IC
N
Route 101 Widening Cleveland - Edwards Avenue
Soundwall
Steele Lane Off Ramp Relocation
Steele Lane NB On Ramp Metering
Santa Rosa
Steele Lane Bridge Widening
263901 Son 101 HOV
Steele Lane I/C Cost 12.4 M
Adv Sept. 2005
21
San Francisco, San Mateo and Santa Clara Counties
Projects
SF 101 Presidio Viaduct
SF 80 SFOBB Resurface Upper Lower Deck
SM 101 Auxiliary Lane
Devils Slide Tunnels
SCl 680 Median Barrier
SCl 101 Grind PCC Pavement
22
0105U1 Overlay SFOBB Upper/Lower Deck
  • Resurface SFOBB
  • ¾ Polyester Deck Overlay
  • Grind ¾ Existing Epoxy Asphalt
  • Lower Deck - Replace 9 Expansion Joints

Project Limits YBI
Project Limits SFO SFOBB Anchorage
0105U4 SFOBB Resurface Upper
and Lower Deck Cost 25.0 Million
Adv 8/29/05
23
SF 101 - Presidio Viaduct Rehabilitation and
Repaint
449404 Rehab and Paint Presidio
Viaduct Cost 19.6 Million Adv Dec. 2005
24
SM 101 Auxiliary Lanes
Project Limits Millbrae Avenue
  • Auxiliary Lanes
  • NB and SB Auxiliary Lanes
  • Reconstruct Peninsula OC
  • Monte Diablo Ped. Bike OC
  • Soundwall and Retaining Wall
  • Drainage Improvements

Project Limits E 3rd Avenue
264201 SM 101 Auxiliary
Lanes 3rd Ave Millbrae Ave.
Cost 74.2 M Adv
June. 2006
25
Devils Slide
Tunnels and Approach Roads
South Portal
Tunnels
New Roadway
North Portal
Bridge
Operation Maintenance Center
South Rock Cut
1123U1 Devil Slide Construct
Tunnels Cost 225.0 Million
Adv Apr. 2006
26
0C890 SCL 101 Grind PCC Pavement
Project Limits San Mateo County Line
  • Grind PCC Pavement
  • Grind PCC Pavement
  • Slab Replacement
  • AC Overlay Mainline Ramps
  • Fog Seal Shoulders

0C8901 SCl 101 Grind PCC
Pavement Cost 19.9 M
Adv 8/15/05
Project Limits Quadalupe River Bridge
27
SCl 680 Upgrade Median Barrier
Project Limits Alameda County Line
  • Upgrade Median Barrier
  • Replace MBGR w/ Concrete Barriers
  • Minor Drainage Modifications

270511 SCl 680 Upgrade
Median Barrier Cost 13.7 M
Adv Sept. 2005
Project Limits I 280 / 101 IC
28
Contra Costa County Upcoming
projects
Benicia Martinez Bridge
Carquinez Bridge
CC 80 Westbound HOV Lanes
Antioch Bridge
Richmond San Rafael Bridge
CC 680 Auxiliary Lanes
29
I 80 WB HOV Extension CC4 -
Cummings Skyway
I/C Modification
I 80 Widening
263701 CC 80 Extend WB
HOV SR4 - Cummings
Cost 19 M Adv Oct. 2005
I/C Modification
Auxiliary Lanes
I/C Modification
30
Construct Auxiliary Lanes Diablo
Road - Bollinger Canyon Road
Project Limits Diablo Road.
Project Limits Sycamore Valley Rd.
  • Construct Auxiliary Lanes
  • NB And SB Auxiliary Lanes
  • Relocate Existing Soundwalls
  • Widening Laurel Drive UC
  • Retaining Walls

Project Limits Crow Canyon Rd.
228551 CC 680 Construct
Auxiliary Lanes Cost 15.2 M
Adv Nov. 2005
Project Limits Bollinger Canyon Rd.
31
Alameda County
Upcoming Projects
Distribution Struct. Retrofit
MacArthur Blvd. On Ramp
SF Oakland Bay Bridge
5th Avenue IC Retrofit
High Street IC Retrofit
I 580 PCC Pavement Rehab.
I 238/580 Widening and Rehabilitation
SR 84 Pigeon Pass Realignment
San Mateo Hayward Bridge
Dumbarton Bridge
32
Ala I 80 / 580 / 880
Distribution Structure Retrofit - Utility Corridor
143554 Retrofit I
80/580/880 Distribution Structure Cost 13.2 M
Adv Dec. 2005
33
Alameda 880 - 5th Avenue
Interchange Retrofit
Project Limits Oak Street
  • Replace Existing Structure
  • Maintain Existing Capacity
  • Raise Profile of New Structure
  • Auxiliary Lane, from Oak St. Off Ramp
  • Standard Shoulders
  • Bike and Pedestrian Lane
  • Lake Merritt Channel

Project Limits 10th Avenue
1706U4 Ala 880 5th Avenue
Interchange Retrofit Cost102 Million Adv
Aug. 2006
34
Alameda 880 - High Street
Interchange Retrofit
Project Limits - Fruitvale Avenue
  • Replace Existing Structure
  • Maintain Existing Capacity
  • Reconfigure SR 77 / 42 Ave./880 IC- Partial
    diamond w/ at grade intersection
  • Reconstruct Frontage Road
  • - Oakport Street
  • - E. Eight Street
  • Standard Shoulders
  • Bike and Pedestrian Lane

Project Limits- .9 km S. of High Street
165424 Ala 880 High Street
Interchange Retrofit Cost60.7 Million Adv
Sept. 2006
35
I-238 Widening and Rehabilitation
I-238/580 IC to I-238/880 IC
Project Limits I-238/580 IC
Project Limits I-238/880 IC
  • Widening and Rehabilitation
  • Widen I-238 from 4 to 6 Lanes
  • Rehabilitate I-238 with LLP
  • SB I-880 Aux. Lane from I238/880 IC to A Street
    Off Ramp
  • Widen NB I-880 to I-238 to 2-Lanes
  • Widen NB I-238 to I-880 to 2 Lanes

249041 I-238 Widening
and Rehabilitation Cost 82.4 M
Adv Jan. 2006
Project Limits A Street
36
PCC Pavement Rehabilitation Hacienda Drive - I 238
  • Upgrade Existing Pavement
  • Replace Cracked Slabs
  • Grind All Lanes
  • Repair Shoulders
  • Replace Approach Slab
  • AC Overlay Ramps
  • Rehab Bridge Decks
  • Install Bridge Rails

Project Limits Hacienda Dr.
Project Limits I - 238
284311 Ala 580
PCC Pavement Rehab Cost 28 M
Adv 8/8/05
37
State Route 84 Realignment Pigeon Pass
Dublin
Pleasanton
Livermore
  • Roadway Realignment
  • Improve Horizontal / Vertical Alignment
  • Median Buffer
  • Current Design Standard
  • Standard Outside Shoulder
  • Guardrail
  • Steep Terrain
  • Environmental Sensitive Habitat

Project Location
172401 Ala 84 Roadway
Realignment Cost 21.3 M
Adv Aug. 2006
38
Networking
  • Network session