Title: Johnson Creek Artificial Propagation Enhancement JCAPE Project
1Johnson Creek Artificial Propagation Enhancement
(JCAPE) Project
Nez Perce Tribe Department of Fisheries
Resources Management
2Acknowledgements
- Nez Perce Tribe
- Bonneville Power Administration
- Idaho Fish and Game
- McCall Fish Hatchery
- Eagle Fish Health Lab
- Fish Marking Staff
- USFWS Lower Snake River Compensation Program
- NOAA Fisheries
- Bryant Ranch
- Community of Yellowpine, Idaho
3JCAPE Project Overview
4Johnson Creek Watershed
5Background
- Declining population trends indicated that
Johnson Creek summer Chinook salmon were at risk
of extirpation. - In 1995, only 5 redds were observed in Johnson
Creek spawning ground index area. - Management Action
- Implement a supplementation program to increase
the number of returning adult salmon using a
conventional fish rearing techniques. - Use only natural origin adults as broodstock and
release all supplementation adults for natural
spawning.
6Program Purpose
- Prevent extirpation of the spawning aggregate in
Johnson Creek - Preserve genetic, ecological, and behavioral
attributes of Johnson Creek summer Chinook, while
minimizing the potential impacts to other stocks - Build a naturally-sustaining summer Chinook
salmon population once factors contributing to
the initial population decline are addressed - Re-establish Tribal and Sport fishing
opportunities
7Supplementation Approach
- Release target of 100,000 smolts annually
- Direct stream release, no acclimation
- Collect only natural adults for broodstock
- 40 pairs of NOR adults for broodstock, collected
over spectrum of run - Pass all returning supplementation adults above
the weir to spawn naturally - Remove all known hatchery strays captured at weir
8Adult Return Goals
- Short-Term Goal Reduce risk of extinction.
This equates to an annual escapement of 350
adults. - Long-term Goal Establish a self sustaining
natural spawning population. At a minimum, this
equates to an annual escapement of 785 adults.
9JCAPE Project History
- JCAPE Project was initiated 1996
- Project received Partial Step 2 Review through
the NWPCC in 1998 to begin supplementation
activities - Supplementation Program has collected broodstock
in 1998, 2000 to present - Monitoring and Evaluation Program initiated 1998
- First smolt release occurred in 2000
- First adult supplementation returns in 2001
10JCAPE ESA Permitting
- Section 10 Permitting
- Prepared Benefit Risk Assessment and HGMP as
requirements of permitting process. - Submitted permit application for 300,000 annual
smolt release in March 2000. - August 2002, NOAA Fisheries determined project
should only be permitted for 100,000 annual smolt
release and could be accomplished in existing
facilities. - Section 10 Permit was approved and signed by NOAA
Fisheries in June 2005 for 100,000 smolt release.
11(No Transcript)
12Juvenile Trapping and Marking
13Spawning Ground and Carcass Surveys
14(No Transcript)
15(No Transcript)
16Juvenile Rearing
17Smolt Release
Juvenile Rearing
Adult Holding and Spawning
18JCAPE Facilities
- Broodstock is collected from Johnson Creek and
transported 35 miles (1.5 hours) to the adult
facility on SF Salmon River. - Broodstock is held and spawned at SF Salmon River
adult facility and eggs are transported 55 miles
to the McCall Fish Hatchery. - Egg incubation and juvenile fish are reared at
McCall Fish Hatchery until release. - Smolts are transported 110 miles (4 hours) to
release site on Johnson Creek.
19Program Status
Adult trap was not operated in 1999 do to low run
prediction, high and extended spring stream
flows, and no ESA permitting
20JCAPE Project Implementation
21Annual Adult Escapement to Johnson Creek
22NaturalHatchery Composition in Johnson Creek
23Broodstock Management
- Broodstock collection is managed with a sliding
scale - Broodstock Target up to 40 pairs of NOR adults
- All supplementation adults are released for
spawning
24Broodstock Composition
HOR fish are not intentionally collected as
broodstock. However, there have been a few
instances when HOR fish have been collected.
These fish were primarily identified after
spawning as an HOR based on tag recoveries not
detected when selected as brood.
25Broodstock Collection
2003 marks beginning of Sliding Scale
implementation for broodstock collection. Up to
40 pair of NOR adults may be collected as brood.
Broodstock target of 80 adults was not always
achieved. Either there were too few fish
returning (2004, 2006, 2007) or we experienced
higher than expected Pre-Spawn Mortality (2000,
2001, 2003, 2008). 2001 had low water flows and
high stream temperatures that likely contributed
to the high pre-spawn mortality.
26Green Egg to Eyed Egg Abundance
In 1998 and 2001, differences in Green Egg to
Eyed Egg survival was compounded by culling eggs
from high BKD positive females.
27Percent Egg Eye-Up
Average Egg Eye-Up Percent 81.7
Lower than expected Egg Eye-Up Percentage was
experienced in 1998, 2001, and 2008.
28Rearing Density Index
Outdoor Rearing Period
Indoor Rearing Period
29Fish Marking
- All supplementation fish are marked with CWT and
Visual Implant Elastomer (VIE) tags. - At time of release, 97.65 had both CWT and VIE
tags and 99.95 had either a CWT or VIE tag. - A portion of the supplementation fish are also
PIT tagged. - None of the supplementation fish receive any fin
clips.
30Smolt Release Dates
31Smolt Size at Release
32JCAPE Smolt Release Totals
Average Smolt Release 90,663
33Supplementation Adult Returns
34Summary
- Operated project as an integrated supplementation
program - Broodstock collected 1998, 2000-present
- Primarily collecting only natural fish as
broodstock - All returning supplementation adults are released
to spawn naturally - Supplementation smolt release numbers range from
57,000 to 120,000, average 90,000 - Supplementation adult returns have ranged from
100 to 700 adults
35Any Questions?