Report on the commissioning activities - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Report on the commissioning activities

Description:

WP excel sheet, PPSPS document (safety) Agree on WP outcome ... Cranes. For these we envisage a sign off procedure only. To collect the performance parameters ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 17
Provided by: JC959
Category:

less

Transcript and Presenter's Notes

Title: Report on the commissioning activities


1
Report on the commissioning activities
  • G. Mornacchi, P. Perrodo and Sub-Systems
    Collaborators

2
ATLAS components breakdown
Inner Detector
TILES
DCS
MUONS
LARG
3
View on the ATLAS work packages
MUONS
LARG
Cooling/ Ventilation WPs
DAQ
TILES

4
Concrete example Tiles calorimeter
WP1 Detector and Modules
WP4 FE Electronics on the truck
Racks,DCS
Interlocks
Active WPs
WP9 Laser system
WP8 Cesium system
WP9 HV system
BE LV system
WP2 Cables
Racks, DCS
Cooling, Sniffers
WP5 FE LVPS insertion
WP3 Rack equipment
FE electronics at IP
Racks
WP11 TILES DCS
TTC DAQ DB
WP7 BE electronics
WP6 Cosmics L1 receivers
Offline
FE-BE integration
Laser calibration
L1 receivers
WP12 min Biais events
Updated on 27/01/05
5
Process Overview
Documents stored in EDMS Under ATC/commissioning/p
hase I/
We are here
Requirements WP Schedule -gt ATLAS schedule WP
excel sheet, PPSPS document (safety) Agree on WP
outcome -gt input to sign off Document
results Preserve operational information
6
Phase 1WP next 3 months
7
Phase 1WP next 3 months
8
Sign Off
  • A number of infrastructure sub-systems have
    already been commissioned or are in the process
    of being so
  • CV
  • Cryogenics plant on surface
  • Cryogenics in USA15, Magnet equipment
  • Cranes
  • For these we envisage a sign off procedure only
  • To collect the performance parameters
  • To understand open issues and problems
  • To integrate them in a uniform documentation
    scheme, easy to trace back

9
Sign Off
  • A formal procedure to make sure that
  • Installation (if any) has been properly done
    e.g. w.r.t. TC procedures (Install. DB, etc)
  • Proper grounding safety issues have been taken
    into account
  • Documentation is available
  • Technical and maintenance documentation for H/W
    and S/W
  • User guides, operational procedures, including
    the test procedures
  • Planning for maintenance and responsibilities
    are defined
  • Performance is according to specifications
  • Or we understand where, how, possibly why, there
    is a disagreement
  • We know what are the open problems and issues
  • And what actions can be defined
  • It is clear who is authorized to use the system
    once commissioned
  • Sensitive items ID cooling, LARG high voltage,
    TILES Cesium system,
  • The sign-off procedure may occur in several
    steps
  • For a complex WP one may envisage intermediate
    milestones, hence sign offs
  • Associated to a repetitive aspect
  • E.g. ROD crates, FE electronics, muon chambers.

10
Sign Off
In the Work packages document WP
outcome (Agreed before WP activation)
Final sign-off procedure
  • Installation report
  • Inventory, grounding, safety,
  • Performance specifications
  • Expected functionality
  • Quantitative performance figures
  • Test report
  • Checklist of tests and results
  • Operational documents
  • Indicates who is responsible, who to contact for
    problems
  • Maintenance procedures/plan
  • Pointers to relevant documentation
  • Operational procedures
  • Test procedures
  • Component manuals
  • List of open issues/problems

Work packages tree
Execution of the WP Follow-up during
the Commissioning meetings
EDMS
Archive documents
11
Weekly meetings at Point 1
  • Make use of sub-system installation meetings to
    follow phase 1 sub-system specific commissioning
  • Phase 1 has too many WPs to concentrate their
    follow up in a single weekly meeting
  • Avoid proliferation of meetings
  • Assume that emphasis will shift from installation
    to commissioning
  • Weekly meeting
  • The same morning as the follow-up of the
    management meetings for UX15 (EAM) counting
    rooms (CRM)
  • Use for topical discussion, sign off, follow
    sub-systems w/o an installation meeting (e.g.
    DSS, DCS, DAQ, trigger)
  • Minutes can be found at
  • Experimental Area Management (EAM)
    http//atlas.web.cern.ch/Atlas/TCOORD/Activities/L
    ogistics/G1/EAM_minutes_index.html
  • Counting Rooms Management (CRM) ATC-C-IM-0001
  • Inner Detector ATC-GE-MM-0132
  • Calorimeters ATC-GE-MM-0125
  • Muons ATC-GE-MM-0126

12
Monthly meetings
  • Start discussion of phase 2 commissioning - gt
    monthly meeting
  • Overall status and issues to be escalated TMB,
    EB

13
Potential difficulties
  • Elaborating the commissioning work to be done
    needs time and some distance with the daily work
    on site.
  • Collaborators involved in commissioning in the
    sub-systems are too often overloaded by many
    other things (e.g. production/installation
    tasks).
  • More effort needed to prepare the functional
    work packages following installation.
  • The new installation planning is very tight (no
    float anymore). This can jeopardize the tests and
    the commissioning. Determine priorities in the
    tests.
  • Test programs, software and analysis tools ready
    in advance is an important asset.
  • Centralized management of the computers and
    network at point 1 is mandatory to avoid
    confusion.
  • Need of a centralized support for the counting
    rooms.

14
Phase II commissioning
  • Define a reasonable end of Phase I for the
    sub-systems.
  • We wont go sequentially Phase 1-gt Phase 2.
  • System integration
  • Partitioning the ATLAS detector Trigger
    (CTP,LTP), DAQ (RCD), DCS, DB
  • Integration Sub-detectors DAQ DB Offline
    data
  • Integration Sub-detectors central DCS DBs
  • Operations L1calo LARG TILES (Workshop Feb..
    1st 2005, next in April)
  • Functional tests
  • Noise tests and Calibration Pulse tests on large
    scales involving sub-detectors and L1. Involves
    ROD crate DAQ.
  • Partial cosmic runs Tiles Muon Barrel sector
    13 ( alignment) LARG (later). Involves ROD
    crate DAQ.
  • Toroid tests (after completion) Sub-systems
  • Infrastructure (cooling, ventilation)
    sub-systems (detectors, electronics, TDAQ, DCS)

15
Phase II commissioning
  • More local combinations
  • LARG cryogenics
  • Magnets cryogenics
  • ID gas system
  • Muons gas system
  • Work organization
  • Many ideas are around and we already feel the
    pressure to take cosmics asap. Need a clear
    formulation (WP) to decide the priorities and
    build a planning.
  • Working groups being organized
  • L1, DAQ or DCS oriented
  • Detector performances and physics coordinators
    calibration data, cosmics
  • Elaborate WPs. Monthly meetings to discuss and
    plan them.
  • Role of commissioning coordination
  • Need a place to operate the detector being
    commissioned (proto Control Room)
  • .

can be considered not as Phase II, but as A
natural extension of Phase I
16
Conclusion
  • Continue to initiate the mechanics of WPs with
    the various ATLAS systems. Milestone of June,
    before the barrel calorimeters move to IP.
  • The success of a well commissioned ATLAS system
    is the result of the sum of many detailed
    tasks.They have to be well thought and prepared
    to be meaningful for the future.This required
    more collaborators involved in these aspects. The
    acknowledgment of this work is of importance.
  • Centralized management of the computers and
    network at point 1 will become soon mandatory to
    avoid confusion.
  • Need of a centralized support for the counting
    rooms.
  • Start thinking seriously soon to a proto control
    room.
Write a Comment
User Comments (0)
About PowerShow.com