Project Sceduling - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Project Sceduling

Description:

By how much can a non-critical activity be delayed without affecting completion ... A critical path for the network is a path consisting of activities with ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 20
Provided by: professo1
Category:

less

Transcript and Presenter's Notes

Title: Project Sceduling


1
Project Management CPM/PERT
Professor Ahmadi

2
Learning Objectives
  • Understand how to plan, monitor, and control
    projects using PERT/CPM.
  • Determine earliest start, earliest finish, latest
    start, latest finish, and slack times for each
    activity.
  • Understand the impact of variability in activity
    times.
  • Understand important role of software such as
    Microsoft Project in project management.

3
Project Planning
  • Specific questions that are considered
  • What is goal or objective of project?
  • What are various activities (or tasks) that
    constitute project?
  • How are these activities linked?
  • What are precedence relationships between
    activities?
  • What is time required for each activity?
  • What other resources (such as labor, raw
    materials, and machinery) are required for each
    activity?

4
Project Scheduling
  • Questions to be answered
  • When will project be completed?
  • What is schedule for each activity?
  • What are critical activities in project?
  • What are non-critical activities in project?
  • By how much can a non-critical activity be
    delayed without affecting completion time of
    entire project?
  • If variability in activity times is considered,
    what is probability project will be completed by
    a specific deadline?

5
Project Controlling
  • Control of large projects involves close
    monitoring of schedules, resources, and budgets.
  • Questions to be answered
  • At any particular date or time, is project on
    schedule, behind schedule, or ahead of schedule?
  • At any particular date or time, is money spent on
    project equal to, less than, or greater than
    budgeted amount?
  • Are there enough resources available to finish
    project on time?
  • If project is to be finished in shorter amount of
    time, what is best way to accomplish this at
    least cost?

6
Gantt Chart for a New Voice Recognition System
Apr.
May
June
July
Aug.
Project Activities
  • a. Design System
  • b. Build Prototype
  • c. Test Prototype
  • d. Estimate Material Costs
  • e. Estimate Labor Costs
  • f. Refine Design
  • g. Build the final Product
  • h. Demonstrate the product
  • i. Market the Product

7
Drawing Project Network
  • There are two major approaches for drawing a
    project network -- Activity on Node (AON), and
    Activity on Arc (AOA).
  • Although both approaches are popular in practice,
    many project management software packages,
    including Microsoft Project 2000, use AON
    networks.
  • Focus is on AON networks.

8
CPM and PERT
  • Network techniques
  • Developed in 1950s
  • CPM by DuPont for chemical plants (1957)
  • PERT by Booz, Allen Hamilton with the U.S.
    Navy, for Polaris missile (1958)
  • Consider precedence relationships and
    interdependencies
  • Each uses a different estimate of activity times

9
CPM/PERT
  • CPM stands for Critical Path Method. It is
    Project Scheduling with Known Activity Times
    (CPM)
  • PERT stands for Program Evaluation Review
    Technique. It is Project Scheduling with
    Uncertain Activity Times (PERT)
  • PERT/CPM is used to plan the scheduling of
    individual activities that make up a project.
  • PERT/CPM can be used to determine the
    earliest/latest start and finish times for each
    activity, the entire project completion time and
    the slack time for each activity.

10
Project Network
  • A project network can be constructed to model the
    precedence of the activities.
  • The nodes of the network represent the
    activities.
  • The arcs of the network reflect the precedence
    relationships of the activities.
  • A critical path for the network is a path
    consisting of activities with zero slack.

11
Determining the Critical Path
  • Step 1 Make a forward pass through the network
    as follows For each activity i beginning at the
    Start node, compute
  • Earliest Start Time the maximum of the earliest
    finish times of all activities immediately
    preceding activity i. (This is 0 for an activity
    with no predecessors.)
  • Earliest Finish Time (Earliest Start Time)
    (Time to complete activity i.
  • The project completion time is the maximum of
    the Earliest Finish Times at the Finish node.

12
Determining the Critical Path
  • Step 2 Make a backwards pass through the
    network as follows Move sequentially backwards
    from the Finish node to the Start node. At a
    given node, j, consider all activities ending at
    node j. For each of these activities, (i,j),
    compute
  • Latest Finish Time the minimum of the latest
    start times beginning at node j. (For node N,
    this is the project completion time.)
  • Latest Start Time (Latest Finish Time) - (Time
    to complete activity (i,j)).

13
Determining the Critical Path
  • Step 3 Calculate the slack time for each
    activity by
  • Slack (Latest Start) - (Earliest Start),
    or
  • (Latest Finish) - (Earliest
    Finish).
  • A critical path is a path of activities, from
    the Start node to the Finish node, with 0 slack
    times.

14
Uncertain Activity Times
  • In the three-time estimate approach, the time to
    complete an activity is assumed to follow a Beta
    distribution.
  • An activitys mean completion time is
  • t (a 4m b)/6
  • Each activitys completion time variance is
  • S2 ((b-a)/6)2
  • a the optimistic completion time estimate
  • b the pessimistic completion time estimate
  • m the most likely completion time estimate
  • The variance of the critical path is ?2 ? S2

15
Uncertain Activity Times
  • In the three-time estimate approach, the critical
    path is determined as if the mean times for the
    activities were fixed times.
  • The overall project completion time is assumed to
    have a normal distribution with mean equal to the
    sum of the means along the critical path and
    variance equal to the sum of the variances along
    the critical path.

16
Network for construction of a new
buildingExample 1
  • A project comprises of the following activities
    and their predecessors.
  • Activity Description Predecessor
  • A Survey site --
  • B Initial design --
  • C Obtain approval A,B
  • D Select architect C
  • E Establish budget C
  • F Finalize design D,E
  • G Obtain financing E
  • H Hire contractor F,G
  • Draw a network for this project.

17
Critical Path Method (CPM) Example 2
  • A project comprises of the following activities
    and their predecessors.
  • Immediate Expected
  • Activity Predecessor time (days)
  • A - 2
  • B - 6
  • C A 4
  • D B 3
  • E C, D 1
  • a. Draw a network and determine the critical
    path. How long will it take to complete the
    project? 
  • b. Provide a detailed activity schedule for the
    project.

18
Program Evaluation and Review Technique (PERT)
Example 3
  • For the following activities and their
    predecessors and the three time estimates (days)
  • Activity Predecessor Optimistic (a) Most
    Probable (m) Pessimistic (b)
  • A - 4 7.5 8
  • B - 1 2 3
  • C A 4 5 6
  • D B 7 8 9
  • E C, D 6 7 14 
  • a. Compute the expected completion time for each
    activity. 
  • b. Draw a network and determine the critical path
    based on the expected completion times.
  • c. What is the probability of finishing the
    project in less than 19 days?
  • d. What is the probability of finishing the
    project in less than 23 days?

19
Network for construction of a new buildingRefer
to Example 1-Your turn
  • A project comprises of the following activities
    and their predecessors.
  • Activity Description Predecessor Time (Days)
  • A Survey site -- 12
  • B Initial design -- 16
  • C Obtain approval A,B 24
  • D Select architect C 8
  • E Establish budget C 12
  • F Finalize design D,E 30
  • G Obtain financing E 24
  • H Hire contractor F,G 16
  • Draw a network for this project and determine the
    critical path. How long would it take to finish
    this project?
Write a Comment
User Comments (0)
About PowerShow.com