Cockcroft-Walton Status - PowerPoint PPT Presentation

About This Presentation
Title:

Cockcroft-Walton Status

Description:

infrastructure groups Health Physics. notified need Ministry of Health ... Ministry of Health Approval. test of Safety System (Beg. April) Peter-Raymond Kettle ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 11
Provided by: ket6
Category:

less

Transcript and Presenter's Notes

Title: Cockcroft-Walton Status


1
Cockcroft-Walton Status
Carlo Bemporad Angela Papa Giovanni Signorelli
Peter-Raymond Kettle
2
Overview
  • Machine Production Status Schedule
  • C-W Area Beam Line Status Schedule
  • Integration into Beam Schedule 2007

3
Machine Status
  • original Completion Date
  • mid-May 2007
  • NEW Completion Date
  • end-February expected
  • Ready for testing mid-April 2007

MEG C-W. Status End 2006
4
Beam Line Components
Bellows Section
  • Bellows system Tested ready for shipment
  • Beam Elements available
  • Power Supplies available
  • Beam Diagnostic Elements
  • ( shutter, diaphragms, x-, y-slits, quartz
    crystalTV-camera)
  • available or almost ready

5
Machine Schedule
  • Completion of manufacture
    end-February 2007
  • Acceptance Tests in Amersfoort NL (or PSI)
  • with HVEE, INFN, PSI mid-April
    2007 ?
  • Shipment to PSI end-April ?
  • Machine Installation
  • Shipment/Guarantee Test
    mid-April to mid-May 2007

6
Cockcroft-Walton Area
  • C-W AREA
  • Area presented Nov. 2006 at
  • Coordination Committee Research
  • Area West
  • Officially in Shutdown Programme
  • area infrastructure planned be
  • installed by the end of Shutdown
  • beam-axis extension survey end 2006
  • infrastructure groups Health Physics
  • notified need Ministry of Health
  • clearance for the new area C-W
  • ?M3 shielding to be removed now to
  • check space

7
Cockcroft-Walton Area cont.
?E5 Zone
8
C-W Area Layout
Virtually all Standard Concrete Blocks
Still Problematic
9
C-W Area Shielding
  • Planned Work needed for Completion
  • (By mid-April)
  • removal of walls measure
  • layout check - freeze design
  • order special shielding start
  • standard shielding construction
  • infrastructure completion
  • water, compressed-air, power
  • Safety systems completion (Interlock)
  • Ministry of Health Approval
  • test of Safety System (Beg. April)

10
Testing Integration into Beam Schedule
  • Full test with LiF-target only possible when
  • area safety aspects completed
  • C-W beam line components magnets, vacuum
    chambers etc. at PSI
  • C-W Bellows System at PSI (will arrive soon
    storage arranged)
  • target prepared
  • CONSTRAINTS
  • cannot be tested in parallel with Beam
    Commissioning
  • bellows system cannot be placed in zone DC
    insertion system needed
  • C-W Bellows System cannot be in place during any
    DS Insertion
  • TCs or DCs or End-Cap installation/removal !!!
  • Proposed Commissioning mid-April
    mid-June
  • ? SEE Proposed Beam Schedule 2007
Write a Comment
User Comments (0)
About PowerShow.com