Title: Customised PowerPoint Presentation
1Free State Public Works, Roads and Transport NCOP
Meeting
28 NOVEMBER 2006
2CONTENTS
- Bridging the first and the second economy
- Extended Public Works Program
- Integrated Sustainable Rural Development
- Contribution to poverty alleviation and job
creation - Empowerment through Procurement Procedures
- Projects currently undertaken
- Challenges
- Way forward
3Bridging the first and the second economy
- State of the Nation Address
- State of the Province address
- Our Budget Speech
- 2014 Millennium Goals
- 2010 Intervention
- EPWP
4State of the Nation Address
- We cannot allow. that government departments
become an obstacle to the achievement of the goal
of a better life for all because of insufficient
attention to the critical issue of effective and
speedy delivery of services. - Integration of planning and implementation
across the government spheres is therefore one of
the prime areas of focus in our programme .. - President Thabo Mbeki State of the Nation
Address 2006
5State of the Province address
- Creation of 50 000 jobs through EPWP
- Halving poverty and un-employment
- Transfer of skills
- Targeted procurement processes
6Our Budget Speech
- Accelerated infrastructure delivery
- Targeted procurement
- Transformation of the construction and property
industry - Nurturing of the incubator strategy
- Empowerment of youth, women, disabled, etc.
7ISRDP and Contribution to poverty alleviation and
job creation
- Makwane access road 27 learnerships and 1800
jobs created R64 million - Road infrastructure
- Selosesha R15 million project
- Trompsburg Jagersfontein R78 million
- Fezile Dabi Projects
- Sasolburg Interchange
- N1 Parys 20 km
- N1 Sasolburg Currently out on tender 24 km
- Vredefort Dome road 30 km out on tender
- Koppies Dam access road 8 km out on tender
- Heilbron Petrus Steyn Reitz Tender Closed 3
Nov 06 First Phase R149 million
8Rationale for roads upgrading and construction
- Access to Bio-Fuel plants (Economic corridor) and
linking Free State and Vereniging / Gauteng - Promotion of Tourism
- Promotion of Freight Corridors
- Linkage of North-West and the Eastern Free State
- Promote mobility, accessibility and future growth
- Access to the Heritage site
9Key Highlights in Sep 06 Mid-term Report
102006/07 Departmental BudgetR1 066 323.00
Roads
Admin, Works, Transport, EPWP
Traffic
112006/07 Budget IssuesState of the Budget
12Actual Monthly Departmental Expenditure and
Projected for 2006/07 TOTAL OVER EXPENDITURE R
261 million
Till 20 Nov 06
13MAIN INDICATORS Economic Classification
14Spending Outcomes and budget 06/07
15Actual Monthly Roads Expenditure till 31 October
2006 and Projected for 2006/07
16Empowerment through Procurement Procedures
- Unbundling of contracts to ensure that all
participate despite the CIDB grading limitation. - Maintenance and upgrading contracts targeted for
small contractors. - Learnership contracts Makwane road, Monontsa
Pass in Qwaqwa, Heuweltop in Tsetseng and Route 4
in Tsetseng. The last 3 projects are yet to
commence (Total cost for these 3 is R147 million)
17Promotion and nurturing of BEEs
- Shortened payment cycle Pay in 7 days on correct
invoice. - Appointment of mentors for SMME projects
Engineers or project managers. - Approval of sessions and reduction of guarantees.
- Monthly project meetings and continuous
monitoring. - Contractors in the incubator programme.
- Sustainable and continuous projects
- Targeted procurement
18Massification of EPWP
- Various projects have been identified for
massification and youth development - Palisade fencing projects.
- Grass cutting and road maintenance
- Possible waste management projects
- Property maintenance projects
19Challenges
- Ownership and re-determination of roads between
provincial and local e.g. through Parys is
designated as a street instead of a provincial
road. Proclamation to be made. - Nature reserves and resorts Jim Fouche in
Oranjeville and Koppies dam nature reserve leased
to private sector at not market related price.
Department is currently revisiting the processes. - CIDB 845 of the contractors are at the entry
level and at grade 9 are only 2
20Challenges (Continue)
- Planning Co-ordination and monitoring not
adequate - Project Management still lacking
- Consultants not playing ball.
- Identify appropriate staff, engineers, project
and financial managers - Material supplies still not transformed
- Financial Institutions not always flexible
- Transformation of the property and construction
sectors
21In Year -Budget Pressures
- Floods
- Material supplies
- Transport Infrastructure
- Law enforcement
- Maintenance
- Accommodation
- Construction material
- Accelerated infrastructure delivery
- 2010 Infrastructure
- CIDB
- Taxi recapitalization
22Interventions and corrective measures
- Planning procedures
- Project Management
- Monitoring
- Consultants
- Client departments
- Appropriate staff for infrastructure delivery
- Changed planning patterns
- Fast-track payments
- Streamline operations
- Batho Pele Testing stations and Revenue
Authorities
23Learnerships
Motheo Xhariep
24Gravel Roads
Road S 1521 Thaba Nchu
Regraveled in Xhariep
25Road repair
Extensive Blading Process
Patch work learnerships
Repair and cleaning of rest areas
Rehabilitation by milling
Cleaning of storm water drainage
26Bridges
Repair bridge approach and remove debris
Sterkspruit bridge
27Makwane access road bridge structure
28MAKWANE-S1499 before and after
29MAKWANE S1500 before
30MAKWANE S1500 Construction
31MAKWANE S1500 After
32PARYS - N1
33(No Transcript)
34SELOSHESHA
35ZASTRON BRIDGE Before and after
36BRIDGE OVER THE CALEDON RIVER AT WEPENER
37FLOOD REPAIR Bloemfontein-Zastron
38TROMPSBURG-JAGERSFONTEIN
39Conditional Grant Spending Business cases
- Infrastructure Plan
- Revisions to the maintenance budget to provide
for flood damage repair work
Road S708 near Ladybrand
Road S 1521 Thaba Nchu
40WORKS AS AN AGENT FOR CLIENT DEPARTMENTS
CLIENT DEPARTMENTS
41SEDERHOF
42Clinic Construction
43Sectoral Issues Works
- Service Level Agreements with client departments
- Payments made to contractors by PWRT or Client
departments - Budgets payment as an advance or as claimed by
PWRT - Reporting requirements of client or agent.
- Reconciliation of data with client departments
44Sectoral Issues Works
65
102
30
21
47
35
45TOTAL EXPENDITURE
DEPARTMENT BUDGET EXPENDITURE
HEALTH R84 849 000 R86 897 006 102.4
EDUCATION R117 695 000 R76 732 997 65.2
ENVIRONMENTAL AFFAIRS R10 000 000 R3 483 993 34.8
SPORT ARTS CULTURE R26 000 000 R12 257 737 47.1
SOCIAL WELFARE R24 758 000 R5 159 770 20.8
46HEALTH PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Bloemfontein Pelonomi hosp - Block E. Upgrade of ICU Â Â Â Temporary ICU to be completed before project can tender
Kroonstad Boitumelo hosp - contract 3 - pharmacy, radiology and theatres Block D R3.98m 89 87 Â Will be completed by December 2006
Kroonstad Boitumelo hosp - Contract 4 Maternity R 1,96m 44 5 Contractor has requested to complete project with cessions. Project still behind schedule
Kroonstad Boitumelo hosp - Contract 7 Mechanical infrastructure R5,44m 67 37 Will be completed during June 2007Â
47HEALTH PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Bloemfontein Pelonomi hospital - upgrade Pharmacy block I and Fence Upgrading R 0,92m 13 2 Â Busy with demolitions. Internal work 50
Kroonstad Boiutmelo hosp - contract 8 Electrical Infrastructure R 6,19m 88 78 To be completed by end November 2006
Jagersfontein Diamant Hospital Upgrading R 3,47m 33 12 Expected completion June 2008Â
Qwa-Qwa E Ross Hospital final phase of upgrading R 10.23m 22 27 Â Expected completion December 2009
48HEALTH PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Harrismith Thebe hosp final phase ofupgrading R 10,63m 27 27 Â Expected completion November 2008
Heilbron Heilbron Tokollo hosp final phase of upgrading R 9,24m 38 24 Expected completion February 2008 Â
Bloemfontein National Hospital - Paliative Care Unit R0, 75m 143 76 In process to address problems which caused delays
Bloemfontein Pelonomi Hospital Block P New Ortopedic workshop R 1,87m 129 67 Contractor was delayed by additional requests from client dept. Work is neat and progress fair.
49HEALTH PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Dealesville New Community Health Care Center  133 95 Contractor a banded site. Legal advise sought. Discussions with SARS
Odendaalsrus Thusanong First phase of upgrading - Maternity, Theatre complex and CSSD R 3,68m 66 32 Progress improved. To be completed August 2007.
Virginia Katleho Hospital - phase 1 of upgrade - new maternity ward R 0,57m 88 96 Will be completed ahead of schedule
Thaba Nchu Moroka - MDR Dining Hall R 0,17m 117 7 Work came to a standstill - cash flow problems. Alternative quotations received for completion of project.
50HEALTH PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Bloemfontein Pelonomi hosp - Mankovs Staff accommodation Contract A R 1,36m 25 15 Â Initial minor problems being managed by architect
Bloemfontein Pelonomi hosp - Mankovs Staff accommodation Contract B R 0,97m 25 15 Initial minor problems being managed by architect Â
51ENVIRONMENTAL AFFAIRS PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Bloemfontein Philip Sanders Resort First Phase R 0,52m   Project started. Expected completion November 2006
Bloemfontein Philip Sanders Resort 2ND Phase R0, 39m   Project unbundled in seven projects. Tenders to be called for in November 2006
Gariep Dam Gariep Dam Phase 2 R 0,16m 50 31 Expected completion September 2007
52SOCIAL WELFARE PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Bloemfontein Tshiriletsong Place of Safety R0, 16m   Documentation completed. Wait for client confirmation to proceed
Welkom One stop service center R0,004m   Mine buildings need to be purchased
Thabo Mofutsanyana One stop secure care center R 2,46m   Documentation completed. Wait for client confirmation to proceed
53SOCIAL WELFARE PROJECTS
TOWN PROJECT EXPEND TIME PROG COMMENTS
Thabo Mofutsanyana Victim Support Center    Documentation will be completed 20 Feb 2007
Bloemfontein Monument Place of Safety Secure Care R 2,39m 100 98 Contractor asked for extension of time until January 2007
54REVENUE
55REVENUE BUDGET R251mPROJECTION R245m
56Revenue Classifications
- Motor licences
- Sales of goods and services non-capital
- Fines, penalties and forfeitures
- Interest, dividends and rent on land
- Sale of capital assets
- Financial Transactions in assets and liabilities
57REVENUE 6 month target R125.7m 6 month
actual R118.3m
58REVENUE CLASSIFICATION
CLASSIFICATION ITEM BUDGET ACTUAL 30Sep 06 Collected
MOTOR VEHICLE LICENCES TAX MOTORVEHICLE LICENCES TAX -190,581,000 -84,961,300 45
SALE GOODSSERV PRODUCED BY DEPT DRIVERS LICENCE APPLICATION FEES -8,147,000 -4,430,297 54
SALE GOODSSERV PRODUCED BY DEPT LEARNER LICENCE APPLICATION FEES -4,000,000 -2,876,594 72
SALE GOODSSERV PRODUCED BY DEPT CONV DRIVERS LICENCE - CARD TYPE -4,000,000 -2,571,800 64
SALE GOODSSERV PRODUCED BY DEPT ABNORMAL LOADS LICENCES -3,473,000 -2,409,635 69
SALE GOODSSERV PRODUCED BY DEPT RENTALOFFICE BUILDINGS -8,010,000 -1,540,584 19
SALE GOODSSERV PRODUCED BY DEPT TESTING ROAD WORTHY FEES -2,000,000 -1,188,025 59
SALE GOODSSERV PRODUCED BY DEPT RENTALPARKING COVEREDOPEN -2,250,000 -1,185,764 53
SALE GOODSSERV PRODUCED BY DEPT SPECIAL LICENCES NUMBERS -2,000,000 -1,124,884 56
SALE GOODSSERV PRODUCED BY DEPT DUPLICATE DOCUMENTS LICENCES -1,500,000 -1,097,721 73
SALE GOODSSERV PRODUCED BY DEPT PUBLIC DRIVERS PERMITS -1,400,000 -879,483 63
SALE GOODSSERV PRODUCED BY DEPT TEMPORARY SPECIAL PERMIT -999,000 -842,996 84
SALE GOODSSERV PRODUCED BY DEPT LEARNERS CERTIFICATE -1,300,000 -782,135 60
SALE GOODSSERV PRODUCED BY DEPT ROAD WORTHY CERTIFICATE -1,000,000 -493,109 49
SALE GOODSSERV PRODUCED BY DEPT SERV REND COMMISSION INSURANCE -830,000 -411,373 50
SALE GOODSSERV PRODUCED BY DEPT MOTOR VEHICLE REGS PERSONAL -800,000 -400,271 50
SALE GOODSSERV PRODUCED BY DEPT ACTIVITIES ON PUBLIC ROADS FEES -400,000 -386,512 97
SALE GOODSSERV PRODUCED BY DEPT DRIVERS LICENCE CERTIFICATE -500,000 -176,460 35
SALE GOODSSERV PRODUCED BY DEPT SALESTENDER DOCUMENTS -180,000 -168,619 94
SALE GOODSSERV PRODUCED BY DEPT RENEWAL DRIVERS LICENCES -2,000,000 -155,867 8
SALE GOODSSERV PRODUCED BY DEPT MOTOR VEHICLE REGIS SPECIAL -400,000 -155,566 39
59REVENUE Classification (Continue)
CLASSIFICATION ITEM BUDGET ACTUAL 30Sep 06 Collected
FINES COURT FINES -11,746,000 -6,324,521 54
FINES IMPOUND FEES -1,000,000 -1,075,270 108
SALES OF LAND SUBSOIL ASSETS SALES OF LAND -1,500,000 -1,016,155 68
REVENUE FINANCIAL ASSETS REVFAREC OF PREV YEARS' EXP - -649,973
REVENUE FINANCIAL ASSETS REVFARECPRV SECCON DEPT DEBT - -366,267
REVENUE FINANCIAL ASSETS REVFACASH SURPLUSES - -78,355
REVENUE FINANCIAL ASSETS REVFARECPRIV STRANS-RES-WORK - -48,314
REVENUE FINANCIAL ASSETS REVFASTALE CHEQUES - -11,565
REVENUE FINANCIAL ASSETS REVFAUNALLOCATED CREDITS - -361
REVENUE FINANCIAL ASSETS RECFARECPRIV SECSTAFF DEBT - -7
60THANK YOU