Title: EIB Status, tests and production
1EIB Status, tests and production
- - Introduction
- - QM2v1 Tests
- CSIST
- cosmic _at_ lapp
- - Planning (QM2v2 and FM/FS production)
-
SRL on behalf of the Lapp team TEM Subdetector
electronics - 01/11/06 _at_ CSIST
2EIB Functionality
- Interface between EFE-EDR ? Signal bus
- Signal Trigger on a threshold
- 9 Pmts connected to one EIB
- 36 EIBs in total of which 24 EIBs with Trigger
function - Regulation for Analog supply voltage Trigger
and EFE
3EIB on the calorimeter
ECAL 5 rows
ECAL 4 rows
B side side12 triggers 6 Non
triggers
A side side12 triggers 6 Non
triggers Mirror of B new
4Trigger schematic
Amplifier
Comparator
Flip-flop
Bus Buffer
Dynode
ETRG
100 ns
Auto reset at t 400 ns
Threshold for 100 MeV signal ? 2 mV gt Signal x 10
Tbusy-Treset 1?s
5QM2v1-EIB
- 12 Layers 6 signals layers and 6 planes
- Material Polymide Coating
- Class 5 Constraints 0.15 mm
- Size 320 mm x 60 mm
- Smaller granularity 2 sub-EIB (4 pms trigger
5pms) - Mirror A side
6QM2v1 Test bench set-up_at_CSIST (I)
4 boards tested EIB_A_T,EIB_A_NT, EIB_B_T,EIB_B_N
T
9-14 October 2005
7QM2v1 Test bench Setup
EIB
4 High gains
EFE
4 Low gains
1 dynode signal
Analog dynode Signal x10
Trigger response Yes / no
PMT
Analog dynode signal
DAC command
Intermediate board
Main trigger LV1 from Generator Or from trigger
(standalone)
BTRG
Data acquisition on PXI
EFE data used to calibrate Trigger data
8QM2v1 EIB_A/B_NT _at_CSIST
9Bus tests - Gain
Expected values found for the 4 boards
10Bus tests - Saturation
Half of the expected values .. (for the 4 boards)
11Bus tests Modified Board
After a modification on the clock distribution
(sloppy edge)
12Bus tests Saturation bis
Nominal values After a modification tested on 2
boards (A side)
13 BUS tests - Summary
- Consumption OK
- Good ordering (mirror AB) - PMT fired one by
one OK - Regulation OK
- Logical Signal shapes OK but the clock
- The 9 Pmts fired together
- Pedestals for the 9?9 channels (values and rms)
(OK) - Gains OK
- Saturations (OK)
- The EM EIB was used as reference and to check the
test bench is properly running
14QM EIB_A/B_T _at_CSIST
15 Trigger tests - Efficiency
Above the threshold
30 led amplitudes ranging from 0.1 to 2.5 Volts
same good behavior for the 2 boards , for
each pmts
16 Trigger tests - Noise
The nominal threshold 100 MeV (20 mV)
No random trigger for 1000 events
17 Trigger tests Hit pattern
20 different sequences, no failure for both
boards
18 Trigger tests- Summary
- Consumption OK
- Good ordering (mirror AB)- PMT fired one by one
OK - DAC threshold measurement OK
- EFE dynode pedestals shifts 50 mV OK
- The 9 Pmts fired together or one PMt alone
- Efficiency (effective threshold) OK
- Noise measurement for different threshold OK
(gt15 mV) - Hit pattern tests (input and output
comparison) OK - To be tested in standalone mode timing
19QM Test bench set-up_at_CSIST
20First coated QM
In total the 4 QM2v1 eibs has been coated
Side view
Top view
First look very high quality Total weight 513
gr Checked at LAPP, with mechanics OK
21Tests at LAPP
- Studies on the clock signal
- tests with the EDR
- at CERN
- At LAPP cosmic data (using 3 QM2v1 boards)
22Studies on the clock signal
CLK ADUM Input
CLK ADUM Output
(16 Mhz)
23Studies on the clock signal
Modification on the QM2v1 a buffer is added
After introducing the buffer
In addition, tests were made on synchronization
times between BDR FPGA (sequencer) and ADC
The BDR is sensitive to delay of 5-8 ns (
induced by the adum and buffer EIB_EM )
(16 Mhz)
24Tests at LAPP with EDR
- Modified QM2v1 tested
- - at CERN with the EDR, JINF and backplane
- with A.Kounine, V. Koutsenko
- pedestal runs worked well
- at LAPP on the calorimeter, 27 pms , HV Brick,
EPSFE, EDR,JINF backplane (cosmic data) - (S. DiFalco, Zuhao Li, SRL, Thanks to A.Kounine
- and V.Koutsenko for providing materials)
25Tests at LAPP with EDR
The third EIB(qm2v1)
2 EIBs (qm2v1) on the FM ecal
2627 HV CABLES
ECAL
EIB to EDR cables
LECROY BUS
LEMO connector
3.3
1 AMSWIRE cable adapted for ext trigger
1 AMSWIRE cable
220 V
220 V
(Only to reprogram Flash ROM in case of need)
PC Linux (Windows 2000 Or XP) ( run as root )
To be soldered on back plane
3.3
28
5
BRICK LOW VOLTAGES
27Tests at LAPP with EDR
HV 800 Volts (default values), 27 pmts
powered MIP 75-80 ADC channels
ADC channels
ADC channels
Special events selections on extreme anode
channels (top and bottom) 4 out of 6 left for
MIP measurement
28Tests at LAPP with EDR
Lecroy HV PS corresponding to 2105 gain ( 650
Volts) 9 pmts powered MIP 15 ADC channels
ADC channels
ADC channels
Special events selections extreme anode channels
(top and bottom) 4 out of 6 left for MIP
measurement
29 Cosmics tests - Summary
- 3 eibs (qm2v1) connected , 1 EPSFE, 1 EDR and 27
Pmts powered together - Consumption OK
- (-2.7 309 mA 3.8 482 mA)
- Regulation OK
- before regulator 2.44
3.49 - after regulator (-1.99 -2.00)
(2.99, 3.01) - Logical Signal shapes OK
- Pedestals for the 27?9 channels (values and rms)
(OK) - MIP seen for two HV (ie gains) (OK)
- DAC values set and measured (OK) on both eibs
30 Cosmics tests - Summary
- - It worked globally well, despite the HV values
could not be set - - Promising results. Final and complete results
to be ready by the next TIM - Need further training to use properly EBP, JINF
and the complete chain - It would be nice to have a EBPJINFEDREPSFE
- system available for future tests
- - Thanks to A.Kounine and A. Koulemszine for all
and for repairing the damages on JINF connector.
31QM2v2 Planning
Modifications (including the 2 buffers)
- As suggested by G.Ambrosi and M.Capell, the
overall FM/FS pcb production should be started as
soon as possible - PCB modified for the boards. One qm2v2 EIB_A
- Documentation ready sent to Giovanni A. ( 18
December) - Components
- Active, should arrive this week
- Passive list sent to Michael Capell together
with the one for the production (8 weeks, tbc)
32QM2v2 tests
- Functionality (as qm2v1, at CSIST BDR)
- Vibration at CSIST and (thermal stress ?)
before coating - Mechanical pieces needed, F.Cadoux proposal
(design at LAPP, production at CSIST ?) - ReFunctionality tests after coating at CSIST
- Thermal Vacuum tests at LAPP
- Tests with EDR and EPSFE, at CERN or LAPP
- (as suggested and decided on last TIM meeting,
A.Lebedev, G.Ambrosi and Doctor Ting)
33Production Planning
- After positive tests on the QM2
- PCB should identical to the QM2v2 one. Files
ready - Documentation ready sent to Giovanni A. (end of
December) - Components
- Active ordered. maximum delay 12 weeks
(beginning of April) including cables and
connectors - Passive list sent to Michael Capell together
with the one for the production (8 weeks, tbc)
34EIB_at_CSIST
Files sent to Giovanni should be reviewed before
to send to Elaine and Frank
35EIB_at_CSIST - Plans
See A.Lebedev for the complete list
36Production tests
- Functional tests (as QM2v1, at CSIST BDR)
- Vibration at CSIST
- Mechanical pieces should be ready (cf QM2v2)
- ReFunctionality tests after coating at CSIST
- VT at LAPP
- Physics tests at Cern
- Test beam scheduled mid September-October
- Tested EIBS should be mounted on the ECAL in
August
37Summary