EIB Status, tests and production - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

EIB Status, tests and production

Description:

EIB Status, tests and production – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 38
Provided by: amsC3
Category:
Tags: eib | production | status | tests

less

Transcript and Presenter's Notes

Title: EIB Status, tests and production


1
EIB Status, tests and production
  • - Introduction
  • - QM2v1 Tests
  • CSIST
  • cosmic _at_ lapp
  • - Planning (QM2v2 and FM/FS production)

SRL on behalf of the Lapp team TEM Subdetector
electronics - 01/11/06 _at_ CSIST
2
EIB Functionality
  • Interface between EFE-EDR ? Signal bus
  • Signal Trigger on a threshold
  • 9 Pmts connected to one EIB
  • 36 EIBs in total of which 24 EIBs with Trigger
    function
  • Regulation for Analog supply voltage Trigger
    and EFE

3
EIB on the calorimeter
ECAL 5 rows
ECAL 4 rows
B side side12 triggers 6 Non
triggers
A side side12 triggers 6 Non
triggers Mirror of B new
4
Trigger schematic
Amplifier
Comparator
Flip-flop
Bus Buffer
Dynode
ETRG
100 ns
Auto reset at t 400 ns
Threshold for 100 MeV signal ? 2 mV gt Signal x 10
Tbusy-Treset 1?s
5
QM2v1-EIB
  • 12 Layers 6 signals layers and 6 planes
  • Material Polymide Coating
  • Class 5 Constraints 0.15 mm
  • Size 320 mm x 60 mm
  • Smaller granularity 2 sub-EIB (4 pms trigger
    5pms)
  • Mirror A side

6
QM2v1 Test bench set-up_at_CSIST (I)
4 boards tested EIB_A_T,EIB_A_NT, EIB_B_T,EIB_B_N
T
9-14 October 2005
7
QM2v1 Test bench Setup
EIB
4 High gains
EFE
4 Low gains
1 dynode signal
Analog dynode Signal x10
Trigger response Yes / no
PMT
Analog dynode signal
DAC command
Intermediate board
Main trigger LV1 from Generator Or from trigger
(standalone)
BTRG
Data acquisition on PXI
EFE data used to calibrate Trigger data
8
QM2v1 EIB_A/B_NT _at_CSIST
9
Bus tests - Gain
Expected values found for the 4 boards
10
Bus tests - Saturation
Half of the expected values .. (for the 4 boards)
11
Bus tests Modified Board
After a modification on the clock distribution
(sloppy edge)
12
Bus tests Saturation bis
Nominal values After a modification tested on 2
boards (A side)
13
BUS tests - Summary
  • Consumption OK
  • Good ordering (mirror AB) - PMT fired one by
    one OK
  • Regulation OK
  • Logical Signal shapes OK but the clock
  • The 9 Pmts fired together
  • Pedestals for the 9?9 channels (values and rms)
    (OK)
  • Gains OK
  • Saturations (OK)
  • The EM EIB was used as reference and to check the
    test bench is properly running

14
QM EIB_A/B_T _at_CSIST
15
Trigger tests - Efficiency
Above the threshold
30 led amplitudes ranging from 0.1 to 2.5 Volts
same good behavior for the 2 boards , for
each pmts
16
Trigger tests - Noise
The nominal threshold 100 MeV (20 mV)
No random trigger for 1000 events
17
Trigger tests Hit pattern
20 different sequences, no failure for both
boards
18
Trigger tests- Summary
  • Consumption OK
  • Good ordering (mirror AB)- PMT fired one by one
    OK
  • DAC threshold measurement OK
  • EFE dynode pedestals shifts 50 mV OK
  • The 9 Pmts fired together or one PMt alone
  • Efficiency (effective threshold) OK
  • Noise measurement for different threshold OK
    (gt15 mV)
  • Hit pattern tests (input and output
    comparison) OK
  • To be tested in standalone mode timing

19
QM Test bench set-up_at_CSIST
20
First coated QM
In total the 4 QM2v1 eibs has been coated
Side view
Top view
First look very high quality Total weight 513
gr Checked at LAPP, with mechanics OK
21
Tests at LAPP
  • Studies on the clock signal
  • tests with the EDR
  • at CERN
  • At LAPP cosmic data (using 3 QM2v1 boards)

22
Studies on the clock signal
CLK ADUM Input
CLK ADUM Output
(16 Mhz)
23
Studies on the clock signal
Modification on the QM2v1 a buffer is added
After introducing the buffer
In addition, tests were made on synchronization
times between BDR FPGA (sequencer) and ADC
The BDR is sensitive to delay of 5-8 ns (
induced by the adum and buffer EIB_EM )
(16 Mhz)
24
Tests at LAPP with EDR
  • Modified QM2v1 tested
  • - at CERN with the EDR, JINF and backplane
  • with A.Kounine, V. Koutsenko
  • pedestal runs worked well
  • at LAPP on the calorimeter, 27 pms , HV Brick,
    EPSFE, EDR,JINF backplane (cosmic data)
  • (S. DiFalco, Zuhao Li, SRL, Thanks to A.Kounine
  • and V.Koutsenko for providing materials)

25
Tests at LAPP with EDR
The third EIB(qm2v1)
2 EIBs (qm2v1) on the FM ecal
26
27 HV CABLES
ECAL
EIB to EDR cables
LECROY BUS
LEMO connector
3.3
1 AMSWIRE cable adapted for ext trigger
1 AMSWIRE cable
220 V


220 V
(Only to reprogram Flash ROM in case of need)
PC Linux (Windows 2000 Or XP) ( run as root )
To be soldered on back plane
3.3
28
5
BRICK LOW VOLTAGES
27
Tests at LAPP with EDR
HV 800 Volts (default values), 27 pmts
powered MIP 75-80 ADC channels
ADC channels
ADC channels
Special events selections on extreme anode
channels (top and bottom) 4 out of 6 left for
MIP measurement
28
Tests at LAPP with EDR
Lecroy HV PS corresponding to 2105 gain ( 650
Volts) 9 pmts powered MIP 15 ADC channels
ADC channels
ADC channels
Special events selections extreme anode channels
(top and bottom) 4 out of 6 left for MIP
measurement
29
Cosmics tests - Summary
  • 3 eibs (qm2v1) connected , 1 EPSFE, 1 EDR and 27
    Pmts powered together
  • Consumption OK
  • (-2.7 309 mA 3.8 482 mA)
  • Regulation OK
  • before regulator 2.44
    3.49
  • after regulator (-1.99 -2.00)
    (2.99, 3.01)
  • Logical Signal shapes OK
  • Pedestals for the 27?9 channels (values and rms)
    (OK)
  • MIP seen for two HV (ie gains) (OK)
  • DAC values set and measured (OK) on both eibs

30
Cosmics tests - Summary
  • - It worked globally well, despite the HV values
    could not be set
  • - Promising results. Final and complete results
    to be ready by the next TIM
  • Need further training to use properly EBP, JINF
    and the complete chain
  • It would be nice to have a EBPJINFEDREPSFE
  • system available for future tests
  • - Thanks to A.Kounine and A. Koulemszine for all
    and for repairing the damages on JINF connector.

31
QM2v2 Planning
Modifications (including the 2 buffers)
  • As suggested by G.Ambrosi and M.Capell, the
    overall FM/FS pcb production should be started as
    soon as possible
  • PCB modified for the boards. One qm2v2 EIB_A
  • Documentation ready sent to Giovanni A. ( 18
    December)
  • Components
  • Active, should arrive this week
  • Passive list sent to Michael Capell together
    with the one for the production (8 weeks, tbc)

32
QM2v2 tests
  • Functionality (as qm2v1, at CSIST BDR)
  • Vibration at CSIST and (thermal stress ?)
    before coating
  • Mechanical pieces needed, F.Cadoux proposal
    (design at LAPP, production at CSIST ?)
  • ReFunctionality tests after coating at CSIST
  • Thermal Vacuum tests at LAPP
  • Tests with EDR and EPSFE, at CERN or LAPP
  • (as suggested and decided on last TIM meeting,
    A.Lebedev, G.Ambrosi and Doctor Ting)

33
Production Planning
  • After positive tests on the QM2
  • PCB should identical to the QM2v2 one. Files
    ready
  • Documentation ready sent to Giovanni A. (end of
    December)
  • Components
  • Active ordered. maximum delay 12 weeks
    (beginning of April) including cables and
    connectors
  • Passive list sent to Michael Capell together
    with the one for the production (8 weeks, tbc)

34
EIB_at_CSIST
Files sent to Giovanni should be reviewed before
to send to Elaine and Frank
35
EIB_at_CSIST - Plans
See A.Lebedev for the complete list
36
Production tests
  • Functional tests (as QM2v1, at CSIST BDR)
  • Vibration at CSIST
  • Mechanical pieces should be ready (cf QM2v2)
  • ReFunctionality tests after coating at CSIST
  • VT at LAPP
  • Physics tests at Cern
  • Test beam scheduled mid September-October
  • Tested EIBS should be mounted on the ECAL in
    August

37
Summary
Write a Comment
User Comments (0)
About PowerShow.com