Title: Building Plan Submission System Review
1Building Plan Submission System Review
- German H.M Cheung
- Buildings Department
26th July 2003 JO Forum
2Buildings Ordinance (Cap123)
- Primary Objective
- To ensure minimum health and safety in and around
buildings
3- BO s.14(1) - Prior approval consent
- Save as otherwise provided, no one shall commence
or carry out any building works without prior
approval and consent from Building Authority - BO s.2 - Building Works
- Includes any kind of building construction, site
formation works, ground investigation in the
scheduled areas, foundation works, repairs,
demolition, alteration, addition and every kind
of building operation, and includes drainage works
4Exemption from BO s.14(1)
- BO s41(1) - Exempted Buildings
- BO s41(3) s41(3A) - Exempted works
- Building works (other than drainage works, ground
investigation in the scheduled areas or site
formation works) not involving the structure of
any building - Drainage works for any existing building
5- BO s.4(1) Appointment of AP RSE
- Every person for whom building works are to be
carried out shall appoint - Authorized Person
- Registered Structural Engineer (if required)
6What required for submission?
- B(A)R 29
- Prescribed Plans, Specified Form Document
- B(A)R 42(7 7A)
- Prescribed Fee
- Development Schedule
- Required by Lands Department
7Classification of submission
- First submission
- Submitted for the first time
- Re-submission
- Previously submitted for approval resubmitted
again - Major Revision
- Previously submitted for approval resubmitted
again with extensive revision
8- Major Revision (PNAP 143)
- Change in disposition / number of blocks
- Change in number of storey
- Major change in configuration of floor plans
- Fundamental reassessment of PR/SC/LV/MOE
- Change in principal use
- Substantial change in site area
- Change that seriously affect access to bldg
- Request for substantial modification/exemption/bon
us - Ground condition assumption incorrect
- Change results in OZP implication
- Fundamentally reassessment
- A repeat of the centralized processing system
necessitated
9Prescribed Plans
- B(A)R 8 for building works
- General Building Plan (Leading Plan)
- Block plan
- Size position of project bldg the nearby bldg
street - Key plan (if required)
- Position of site
- Floor plans
- Dimension, thickness, position of window etc
- Elevation plans
- Bldg elevation, level and width of street etc
- Section plans
10Prescribed Plans (cont)
- Diagrammatic plan
- Demonstrate compliance with PR SC
- Demonstrate compliance with Open space Service
lane (if required) - Plans regarding projection over street
- Showing the nature dimension of projection
- Details plan
- UFS
- No. and type of sanitary fitment
11Prescribed Plans (cont)
- Site formation plans
- Foundation plans
- Ground investigation plan (in scheduled areas)
- Structural plans
- Drainage plans
- B(A)R 29(2) May submitted separately
- B(A)R 11A Site formation Foundation Plan
12No. of sets of plans required
- PNAP 30 Centralized Processing
- At least 6 sets
- 2 sets for BD B(A)R 11
- Coloring of plans - B(A)R 14(3)
- In practice 2 sets coloring
- 2 sets for FSD
- 1 sets for DPO
- 1 sets for DLO
- Additional plans
- PNAP 30 appendix A pt. 3
13Specified Forms
- PNAP 159
- For new building development
(1st submission) - Form BA 4, 5 BA16 (if required)
- For existing building AA
(1st submission) - Form BA 4, 5, 6 B(A)R 18 BA16 (if required)
14Prescribed Fee
- B(A)R 42(7 7A)
- PNAP 143 Appendix A - for submission
- New Building (First submission / major revision)
- Industrial / Non-industrial
- GFA basis with min. charge
- Without GFA involvement (e.g. Power station)
- 11,200 per sheet (Max. A1 size)
15Prescribed Fee (cont)
- New Building (Re-submission)
- Free of charge
- AA (First submission / major revision)
- 11,200 per sheet (Max. A1 size)
- AA (Re-submission)
- Free of charge
16Prescribed Fee (cont)
- Demolition (without follow-up development)
- 11,200 per sheet (Max. A1 size)
- Demolition (with follow-up development)
- Free of charge
- Prescribed fee only for follow-up development
17Prescribed Fee (cont)
- Modification for the exemption of B(A)R 42
- Grounds
- Charity Organization
- Non-profit making organization
- School, etc
18Statutory Time for Approval
- B(A)R 30 (3)
- First submission 60 Days
- Major revision 60 Days
- Re-submission 30 Days
- Re-submission Due to B(A)R 29(3) 60 / 30 Days
- BAs decision (Not affected by Lands Dept)
- Approval SL 9/
- Approval with condition (BO s.17) SL 9 /
- Disapproval SL 8 BO s.16(1)
19Application for consent
- B(A)R 31 32
- Form BA 8 SSSP
- Statutory Time 28 Days
- BAs decision
- Grant consent BD103/
- Refuse by BO s.16(3)
20Notification to BA before commencement of works
- After 1st consent is granted
- B(A)R 20
- Not less than 7 Days before
- Form BA10
- (only for 1st consents commencement of work)
- Commencement of works
21Consent for Amendment
- PNAP 215
- Type I works (Normal procedure)
- 1st consent not obtained
- 1st consent obtained but amendment has major
revision - Type II works (Fast Track)
- 1st consent obtained, amendment not result in
major revision - Amendment plan approval consent at the same
time ( 28 Days)
22- BAs decision on Type II works
- SL8A (Disapproval plan refuse consent)
- SL9A (Approval plan grant consent)
- SL9B (Approval plan refuse consent)
23- Completion of works
- Submit Form BA 13/14 (Cert. on completion)
2 sets of record plans - Processing OP application
- Statutory time period is within 14 Days BO
s.21(7) - Issue BD 104
- Processing BA14 application (no statutory time
frame) - Practice time is within 28 Days
- Issue Acknowledgement letter
24Re-engineering the Building Approval Process
- PNAP 272 (Effective on 16 Aug 02)
- Replace PNAP 99
- Adopting a totally positive attitude towards
building development - Not to find fault in a building proposal
- But to facilitate building approval process
whilst ensuring safety and health
25Important Points to Note in PNAP 272
- Pre-submission Enquiry and conference
- Further simplified curtailed check system
- Minor Amendment
- Use of computer for math.calculations
- Fast track processing of minor AA works
26Pre-submission Enquiry and conference
- New structural theory, materials or systems,
sophisticated designs and unconventional
construction methods - Submission of Concept Drawings
- Demonstrated compliance with SC, PR, accountable
GFA, fire safety strategy BFA
27Further simplified curtailed check
system
- Check on fundamental issues listed out in PNAP
Appendix A only ( in case of GBP)
ltDifferent from PNAP 99gt
- Density
- Safety
- Health environment
- Major issues under allied regulation
- Audit check
- Ensuring high standard of self-regulation is
maintained - If blatantly or repeatedly contravene ordinance,
BD would take appropriate action
28Minor Amendment
- Facilitate the construction process
- Form BA16 - Modification of B(A)R 33(1)
- Prior approval consent to minor amendment would
not be required (provided that 1st consent has
already been granted ) - Only require FINAL approval consent before
certifying completion of works / OP application
(Final 28 days for approval consent in Type II
works) - PNRC 52
29Minor Amendment (cont)
- Not applicable to (in relation to GBP)
- Major revision
- Material effect on fundamental issues
- Involving geotechnical concern
- Involving application for modification
- OZP implication
- Involving work outside the lot
30Use of computer for mathematic calculations
- For calculating floor area vol. of bldg
- Provide BD with an electronic copy
- Calculation format capable of being verified by
Autocad or Microstation or software agreed by BD
31Fast track processing of Minor AA works
- Already exist PNAP 99
- Simple AA - AP confirms
- Not involve the structure of the building
- Not affect the fundamental issues (allow minor
change but need AP certify in compliance with
Ord/Reg.) - Referral to other gov. dept are not necessary
(except FSD) - 28 Days for processing both approval consent
- APs certification form PNAP 272 Appendix F
32PNAP 269
- Signboard Building Works
- Proliferation of large unauthorized signboards
- Speed up the processing of applications for the
erection of signboard in EXISTING building - Fast Track Processing of AA Plan for signboard
- Non-applicable to non-conforming submission /
unconventional signboards - Effective from 2 June 2003
33PNAP 269 (cont)
- 28 Days for both approval consent
- AP/RSE certify the provisions of the BO
requirements of the relevant government
departments for the erection of signboards are
complied with - At least 9 sets of plans
- Certificate (Appendix A)
- Checklist (Appendix B)
- Requirement (Appendix C-I) FSD, TD, HyD, etc
34Review (in terms of statutory time)
35Review (in terms of APs responsibility)
- Shorter approval time vs.
Higher responsibility for AP - Normal Processing vs.
Fast Track
Processing (PNAP 272 / PNAP 269) - Normal Processing ltType Igt vs.
Fast Track Processing
ltType IIgt (PNAP 215) vs. Minor
Amendment (PNAP 272) - Self-certification by AP