Providing Reactive Power from - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Providing Reactive Power from

Description:

The Reactive Power envisioned by FERC in Order 888 as one of six 'ancillary ... for Reactive Power are paid by Transmission Customers to the utilities today. ... – PowerPoint PPT presentation

Number of Views:130
Avg rating:3.0/5.0
Slides: 22
Provided by: Cun58
Category:
Tags: by | power | providing | reactive

less

Transcript and Presenter's Notes

Title: Providing Reactive Power from


1
Providing Reactive Power from Generating
Resources Schedule 2 of the MISO OATT by the OMS
Resource Adequacy Working Group OMS Board Meeting
at MARC June 16, 2004
2
INTRODUCTION
  • This presentation will cover the following
  • FERC Order 888 requirements for unbundling costs
    of ancillary services,
  • Reactive Power Rates in MISO paid by transmission
    customers but not collected by MISO,
  • A discussion of the importance of Reactive Power,
  • FERCs PJM Order regarding allowing
    non-transmission-owning independent power
    producers to seek compensation for supplying
    Reactive Power,
  • Recent events that have focused on need for more
    sources of Reactive Power,
  • FERC ALJs Decision in the Troy case,
  • MISOs response with a Schedule 21 companion to
    Schedule 2,
  • Will the new Schedule 21 end the controversy over
    Reactive Power compensation?
  • MISOs responses during the frequent debates in
    the Tariff Working Group,

1
3
FERC ORDER 888 REQUIREMENTS Starting in
1996, Transmission Providers across the country
began filing Open Access Transmission Tariffs at
the FERC to unbundle the costs for Wholesale
Transmission Services. FERC, Promoting
Wholesale Competition Through Open Access
Non-discriminatory Transmission Service by Public
Utilities Recovery of Stranded Costs by Public
Utilities and Transmitting Utilities, Order 888,
FERC Stats . Regs. Regs. Preambles 1991-1996
31.036 at 31,705 (1996), on rehg, Order No.
888-A, FERC Stats. Regs. Regs. Preambles
1996-2000 31.048 (1997), on rehg, Order No.
888-B, 81 FERC, 61,248 (1997), on rehg, Order
No. 888-C, 82 FERC, 61,046 (1998) (hereinafter
Order 888).
2
4
SEPARATING OPEN ACCESS TRANSMISSION FROM
GENERATION SERVICES
  • Companies had to identify assets that were booked
    in Generation Production (G) accounts that
    perform primarily a Transmission (T) Ancillary
    Service function.
  • 2) They had to add the incremental rate to
    recover the cost of these assets to the
    Transmission tariff.

3
5
  • Separating T from G (contd)
  • 3) Companies also had to identify assets booked
    in Transmission (T) accounts that primarily serve
    a generation production Generation (G) function
    and subtract the incremental rate for these
    assets from the transmission tariff.
  • In essence The unbundled transmission tariff
    should avoid cross-subsidization among Generation
    Production (G) and Transmission (T) Customers.

4
6
THE REVENUE REQUIREMENTS FOR UNBUNDLED
TRANSMISSION SERVICES MUST BE FILED AT FERC
UNRESOLVED ISSUES MAY BE SET FOR HEARING.The
Reactive Power envisioned by FERC in Order 888 as
one of six ancillary services addresses only
reactive power from generation resources.

5
7
REACTIVE POWER RATES IN MISOREACTIVE POWER
RATES FOR UTILITIES IN THE MISO FOOTPRINT--
RESULTING FROM CALCULATIONS OF UNBUNDLED COSTS AS
FILED IN EACH UTILITYS INDIVIDUAL OATT AT FERC,
CAN BE FOUND ON THE MISO OASIS AS Ancillary
Service Schedule 2. These rates for Reactive
Power are paid by Transmission Customers to the
utilities today. They are not collected by MISO.

6
8
ANCILLARY SERVICES - SCHEDULE 2 Reactive Supply
Voltage Control - Existing Customer Charges under
Current OATTs
Estimates based on On-Peak rate billed for an
average 800 kWh/month MISO Rate charged for
Sinks external to MISO (non-MISO members)
ITC (DECO) charges apply for ITC Schedule 2
7
9
THE IMPORTANCE OF REACTIVE POWERIn order 888,
FERC noted-- Electric power consists of two
components. The first, Real Power (watts) is
the active force that causes electrical
equipments to work. -- The second
component Reactive Power (Volt-amperes
reactive or VARs) Is necessary to maintain
adequate voltages so that Real Power can be
transmitted. Order 888 at 31,707.
8
10
TRANSMISSION LINES NEED TO BE ENERGIZED BEFORE
THEY WILL CARRY REAL POWER. REACTIVE POWER
PROVIDES THE ENERGIZATION TO MOVE REAL POWER.
ACCORDING TO NERC, HEAVY POWER TRANSFERS ACROSS
A TRANSMISSION INTERFACE AND HEAVY LOADING ON
TRANSMISSION LINES CAN CAUSE VOLTAGE IN AN AREA
TO BECOME DEPRESSED IF SUFFICIENT REACTIVE
SUPPLIES ARE NOT AVAILABLE TO THE
SYSTEM.UNLIKE REAL POWER, REACTIVE POWER
CANNOT BE TRANSMITTED EASILY OVER LONG DISTANCES
AND IS BEST SUPPLIED LOCALLY.Michael J.
Zimmer, Reactive Power Capability-A Challenge to
Grid Reliability atMichael.J.Zimmer_at_bakernet.com
(Washington, D.C. at 1
9
11
FERC ALLOWS NON-TRANSMISSION-OWNING INDEPENDENT
POWER PRODUCERS TO SEEK COMPENSATION AT FERC
UNDER SEC. 205 OF THE FPA FOR REACTIVE POWER
PROVIDED BY THEIR GENERATORS UNRESOLVED ISSUES
MAY BE SUBJECT TO HEARING.
  • In a 2000 PJM case, FERC allowed
    non-transmission-owning independent power
    producers to unbundle their costs of providing
    Reactive Power as an ancillary service from their
    generating resources for inclusion in a
    Transmission Providers OATT.
  • PJM Interconnection L.L.C., Docket No.
    ER00-3327 (September 25, 2000) (unpublished
    letter order), as cited in 105 FERC 61,250.

10
12
RECENT EVENTS HAVE FOCUSED ON A NEED FOR MORE
SOURCES OF REACTIVE POWER
  • The Bi-National Task Force Final Report found
    that August 14, 2003 Blackoutaffecting nearly
    10 of the Eastern Interconnections entire load,
    began with declining voltages during a warm
    summer afternoon of consistently increasing air
    conditioning demand and power transfers into
    FirstEnergy, a member of MISO.
  • With the loss of just one generating unit in a
    high demand load pocket, FirstEnergy had no
    additional generation to provide the needed
    Reactive Power Support.
  • U.S.-Canada Power System Outage Task Force,
    Final Report on the August 14, 2003 Blackout in
    the United States and Canada Causes and
    Recommendations (April 2004) at 31,.

11
13
More recent events have focused on a need for
more sources of Reactive Power (contd)
  • The Bi-National Task Force Final Report also
    recommended that NERC require the utility to
    confirm that all non-utility generators in its
    area enter into contracts committing them to
    producing increased or maximum reactive power
    when called upon by FirstEnergy or MISO to do
    so.
  • Id., at 151.

12
14
The FERC ALJs Decision in the Troy LLC Complaint
Case (Docket ER03-1396-000)
  • On April 21, 2004, FERC ALJ Cintron certified an
    uncontested Agreement and Settlement BETWEEN Troy
    L.L.C. (an affiliate of Dominion Power in
    Virginia) and FirstEnergy, MISO, the Midwest
    Standalone Transmission Companies and Calpine.
  • Article 2.3 of the Settlement states that MISO
    shall tender revisions to its OATT Schedule 2
    providing terms and conditions under which a
    generator is eligible for compensation for its
    reactive power capability

13
15
IN RESPONSE, MISO HAS MODIFIED ITS SCHEDULE 2 FOR
REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION RESOURCE SERVICES
  • MISO intends to preserve existing zonal rate
    design for transmission service and grandfather
    existing Schedule 2 revenue requirements of
    generators within the MISO footprint.
  • Consistent with FERCs intentions in its earlier
    PJM ruling, MISO will seek to preserve the filing
    rights of non-transmission owning independent
    generators seeking compensation for reactive
    power and voltage control from their generation
    service For this purpose, MISO introduces a
    separate schedule Schedule 21.
  • Holsclaw e-mail to Tariff_wg_at_lists.midwestiso.O
    RG (April 23, 2004)

14
16
THE NEW MISO SCHEDULE 21 WILL PROVIDE
COMPENSATION FOR FERC-FILED REVENUE REQUIREMENTS
FOR SUPPLYING REACTIVE POWER
  • The new Schedule 21 companion to the existing
    Schedule 2 is specifically designed to capture
    the terms and conditions for compensating
    non-transmission-owning generators, including
    those generating utilities separated from their
    former transmission assets by corporate
    restructuring.

15
17
Will the introduction of the new Schedule 21 end
the ongoing controversy over Reactive Power
compensation?
  • The Vertically-integrated transmission-owning
    companies insist that MISO
  • Institute a needs test to determine if and when
    reactive power is needed by non-transmission-ownin
    g companies, and
  • Institute an additional testing procedure to
    determine the VAR capability of a generator.

16
18
DURING THE FREQUENT DEBATES IN THE TARIFF WORKING
GROUP, MISO HAS RESPONDED
  • No MISO needs test will be included in the
    Schedule 2 modification (now known as companion
    Schedule 21),
  • Under Sections 205(b) and 203 of the FPA, rates,
    charges, and services of transmission and
    wholesale generation sales are to be
    nondiscriminatory.
  • Non-transmission-owning generators must file
    their revenue requirements at FERC. Parties may
    (and do) intervene in these cases to argue for
    hearing of contested issues.

17
19
During the frequent debates in the Tariff Working
Group, MISO responded (contd)
  • Additional testing will not be required.
    Interconnection of new generators, under MISOs
    compliance with FERC Order 2003, will include
    feasibility, system impact and facilities
    studies.
  • Under an Order 2003 Interconnection Agreement,
    the interconnecting generator must be willing to
    supply VAR support.

18
20
MISO can design the details of the Tariff terms
and conditions in order to avoid abuse and
misrepresentation by Reactive Power providers
  • State regulators may want to review the response
    time requirements in the new Schedule 21 to
    assure there is no unwarranted delay or lag in a
    generators response to MISOs call for reactive
    power and voltage control,
  • State regulators may want to review the terms and
    conditions of any penalties imposed by MISO for a
    non-response by a generator to MISOs call for
    reactive power and voltage control.

19
21
Any Questions?
Write a Comment
User Comments (0)
About PowerShow.com