Title: Providing Reactive Power from
1Providing Reactive Power from Generating
Resources Schedule 2 of the MISO OATT by the OMS
Resource Adequacy Working Group OMS Board Meeting
at MARC June 16, 2004
2INTRODUCTION
- This presentation will cover the following
- FERC Order 888 requirements for unbundling costs
of ancillary services, - Reactive Power Rates in MISO paid by transmission
customers but not collected by MISO, - A discussion of the importance of Reactive Power,
- FERCs PJM Order regarding allowing
non-transmission-owning independent power
producers to seek compensation for supplying
Reactive Power, - Recent events that have focused on need for more
sources of Reactive Power, - FERC ALJs Decision in the Troy case,
- MISOs response with a Schedule 21 companion to
Schedule 2, - Will the new Schedule 21 end the controversy over
Reactive Power compensation? - MISOs responses during the frequent debates in
the Tariff Working Group,
1
3 FERC ORDER 888 REQUIREMENTS Starting in
1996, Transmission Providers across the country
began filing Open Access Transmission Tariffs at
the FERC to unbundle the costs for Wholesale
Transmission Services. FERC, Promoting
Wholesale Competition Through Open Access
Non-discriminatory Transmission Service by Public
Utilities Recovery of Stranded Costs by Public
Utilities and Transmitting Utilities, Order 888,
FERC Stats . Regs. Regs. Preambles 1991-1996
31.036 at 31,705 (1996), on rehg, Order No.
888-A, FERC Stats. Regs. Regs. Preambles
1996-2000 31.048 (1997), on rehg, Order No.
888-B, 81 FERC, 61,248 (1997), on rehg, Order
No. 888-C, 82 FERC, 61,046 (1998) (hereinafter
Order 888).
2
4SEPARATING OPEN ACCESS TRANSMISSION FROM
GENERATION SERVICES
- Companies had to identify assets that were booked
in Generation Production (G) accounts that
perform primarily a Transmission (T) Ancillary
Service function. -
- 2) They had to add the incremental rate to
recover the cost of these assets to the
Transmission tariff.
3
5- Separating T from G (contd)
- 3) Companies also had to identify assets booked
in Transmission (T) accounts that primarily serve
a generation production Generation (G) function
and subtract the incremental rate for these
assets from the transmission tariff. - In essence The unbundled transmission tariff
should avoid cross-subsidization among Generation
Production (G) and Transmission (T) Customers.
4
6THE REVENUE REQUIREMENTS FOR UNBUNDLED
TRANSMISSION SERVICES MUST BE FILED AT FERC
UNRESOLVED ISSUES MAY BE SET FOR HEARING.The
Reactive Power envisioned by FERC in Order 888 as
one of six ancillary services addresses only
reactive power from generation resources.
5
7REACTIVE POWER RATES IN MISOREACTIVE POWER
RATES FOR UTILITIES IN THE MISO FOOTPRINT--
RESULTING FROM CALCULATIONS OF UNBUNDLED COSTS AS
FILED IN EACH UTILITYS INDIVIDUAL OATT AT FERC,
CAN BE FOUND ON THE MISO OASIS AS Ancillary
Service Schedule 2. These rates for Reactive
Power are paid by Transmission Customers to the
utilities today. They are not collected by MISO.
6
8ANCILLARY SERVICES - SCHEDULE 2 Reactive Supply
Voltage Control - Existing Customer Charges under
Current OATTs
Estimates based on On-Peak rate billed for an
average 800 kWh/month MISO Rate charged for
Sinks external to MISO (non-MISO members)
ITC (DECO) charges apply for ITC Schedule 2
7
9THE IMPORTANCE OF REACTIVE POWERIn order 888,
FERC noted-- Electric power consists of two
components. The first, Real Power (watts) is
the active force that causes electrical
equipments to work. -- The second
component Reactive Power (Volt-amperes
reactive or VARs) Is necessary to maintain
adequate voltages so that Real Power can be
transmitted. Order 888 at 31,707.
8
10TRANSMISSION LINES NEED TO BE ENERGIZED BEFORE
THEY WILL CARRY REAL POWER. REACTIVE POWER
PROVIDES THE ENERGIZATION TO MOVE REAL POWER.
ACCORDING TO NERC, HEAVY POWER TRANSFERS ACROSS
A TRANSMISSION INTERFACE AND HEAVY LOADING ON
TRANSMISSION LINES CAN CAUSE VOLTAGE IN AN AREA
TO BECOME DEPRESSED IF SUFFICIENT REACTIVE
SUPPLIES ARE NOT AVAILABLE TO THE
SYSTEM.UNLIKE REAL POWER, REACTIVE POWER
CANNOT BE TRANSMITTED EASILY OVER LONG DISTANCES
AND IS BEST SUPPLIED LOCALLY.Michael J.
Zimmer, Reactive Power Capability-A Challenge to
Grid Reliability atMichael.J.Zimmer_at_bakernet.com
(Washington, D.C. at 1
9
11FERC ALLOWS NON-TRANSMISSION-OWNING INDEPENDENT
POWER PRODUCERS TO SEEK COMPENSATION AT FERC
UNDER SEC. 205 OF THE FPA FOR REACTIVE POWER
PROVIDED BY THEIR GENERATORS UNRESOLVED ISSUES
MAY BE SUBJECT TO HEARING.
- In a 2000 PJM case, FERC allowed
non-transmission-owning independent power
producers to unbundle their costs of providing
Reactive Power as an ancillary service from their
generating resources for inclusion in a
Transmission Providers OATT. - PJM Interconnection L.L.C., Docket No.
ER00-3327 (September 25, 2000) (unpublished
letter order), as cited in 105 FERC 61,250.
10
12RECENT EVENTS HAVE FOCUSED ON A NEED FOR MORE
SOURCES OF REACTIVE POWER
- The Bi-National Task Force Final Report found
that August 14, 2003 Blackoutaffecting nearly
10 of the Eastern Interconnections entire load,
began with declining voltages during a warm
summer afternoon of consistently increasing air
conditioning demand and power transfers into
FirstEnergy, a member of MISO. - With the loss of just one generating unit in a
high demand load pocket, FirstEnergy had no
additional generation to provide the needed
Reactive Power Support. - U.S.-Canada Power System Outage Task Force,
Final Report on the August 14, 2003 Blackout in
the United States and Canada Causes and
Recommendations (April 2004) at 31,. -
11
13More recent events have focused on a need for
more sources of Reactive Power (contd)
- The Bi-National Task Force Final Report also
recommended that NERC require the utility to
confirm that all non-utility generators in its
area enter into contracts committing them to
producing increased or maximum reactive power
when called upon by FirstEnergy or MISO to do
so. - Id., at 151.
12
14The FERC ALJs Decision in the Troy LLC Complaint
Case (Docket ER03-1396-000)
- On April 21, 2004, FERC ALJ Cintron certified an
uncontested Agreement and Settlement BETWEEN Troy
L.L.C. (an affiliate of Dominion Power in
Virginia) and FirstEnergy, MISO, the Midwest
Standalone Transmission Companies and Calpine. - Article 2.3 of the Settlement states that MISO
shall tender revisions to its OATT Schedule 2
providing terms and conditions under which a
generator is eligible for compensation for its
reactive power capability
13
15IN RESPONSE, MISO HAS MODIFIED ITS SCHEDULE 2 FOR
REACTIVE SUPPLY AND VOLTAGE CONTROL FROM
GENERATION RESOURCE SERVICES
- MISO intends to preserve existing zonal rate
design for transmission service and grandfather
existing Schedule 2 revenue requirements of
generators within the MISO footprint. - Consistent with FERCs intentions in its earlier
PJM ruling, MISO will seek to preserve the filing
rights of non-transmission owning independent
generators seeking compensation for reactive
power and voltage control from their generation
service For this purpose, MISO introduces a
separate schedule Schedule 21. - Holsclaw e-mail to Tariff_wg_at_lists.midwestiso.O
RG (April 23, 2004)
14
16THE NEW MISO SCHEDULE 21 WILL PROVIDE
COMPENSATION FOR FERC-FILED REVENUE REQUIREMENTS
FOR SUPPLYING REACTIVE POWER
- The new Schedule 21 companion to the existing
Schedule 2 is specifically designed to capture
the terms and conditions for compensating
non-transmission-owning generators, including
those generating utilities separated from their
former transmission assets by corporate
restructuring.
15
17Will the introduction of the new Schedule 21 end
the ongoing controversy over Reactive Power
compensation?
- The Vertically-integrated transmission-owning
companies insist that MISO - Institute a needs test to determine if and when
reactive power is needed by non-transmission-ownin
g companies, and - Institute an additional testing procedure to
determine the VAR capability of a generator.
16
18DURING THE FREQUENT DEBATES IN THE TARIFF WORKING
GROUP, MISO HAS RESPONDED
- No MISO needs test will be included in the
Schedule 2 modification (now known as companion
Schedule 21), - Under Sections 205(b) and 203 of the FPA, rates,
charges, and services of transmission and
wholesale generation sales are to be
nondiscriminatory. - Non-transmission-owning generators must file
their revenue requirements at FERC. Parties may
(and do) intervene in these cases to argue for
hearing of contested issues.
17
19During the frequent debates in the Tariff Working
Group, MISO responded (contd)
- Additional testing will not be required.
Interconnection of new generators, under MISOs
compliance with FERC Order 2003, will include
feasibility, system impact and facilities
studies. - Under an Order 2003 Interconnection Agreement,
the interconnecting generator must be willing to
supply VAR support.
18
20MISO can design the details of the Tariff terms
and conditions in order to avoid abuse and
misrepresentation by Reactive Power providers
- State regulators may want to review the response
time requirements in the new Schedule 21 to
assure there is no unwarranted delay or lag in a
generators response to MISOs call for reactive
power and voltage control, - State regulators may want to review the terms and
conditions of any penalties imposed by MISO for a
non-response by a generator to MISOs call for
reactive power and voltage control.
19
21Any Questions?