TDA as Road Embankment Fill - PowerPoint PPT Presentation

1 / 72
About This Presentation
Title:

TDA as Road Embankment Fill

Description:

TDA as Road Embankment Fill – PowerPoint PPT presentation

Number of Views:296
Avg rating:3.0/5.0
Slides: 73
Provided by: ddw29
Category:
Tags: tda | embankment | fill | ikon | road

less

Transcript and Presenter's Notes

Title: TDA as Road Embankment Fill


1
TDA as Road Embankment Fill
NYSDOT
  • Donald Dwyer, P.E.
  • Associate Soils Engineer
  • Geotechnical Engineering Bureau
  • NYSDOT
  • June, 2009

2
Outline
  • Origins and goals of the tire shred incentive
    program
  • Background
  • Implementation
  • Design issues
  • Construction issues
  • Performance
  • Status of the program

3
Goal
  • To help solve the waste tire problem by using
    tire shreds (TDA) in the most efficient manner,
    in appropriate locations
  • It was not the goal to conduct research to
    further the state of the practice.
  • Pursue the application that uses the largest
    amount of tires with the least effort

4
Overview
  • NYSDOT Policy DOT will use tire shreds in
    appropriate applications and locations as the
    lightweight fill of first choice, or as a
    replacement for natural fill.
  • Partners included DEC, OGS, ESDC, Thruway

5
Early Work
  • Hosted a training session by Dr. Dana Shred
    Humphrey in 1996
  • Reviewed several draft legislation bills
  • First pilot project in 1999
  • Intended to establish the engineering
    requirements should TDA usage be mandated

6
Pilot Project
  • Rt 17 Five Mile Point to Occanum, Broome Co.
  • Off ramp, Rt 17 to North Road
  • 267,000 tires placed in a 10 layer

7
(No Transcript)
8
(No Transcript)
9
Placing Shreds on Geotextile
10
Compaction lines up the shreds and takes out many
of the voids that would lead to compression..
11
(No Transcript)
12
New Legislation
  • Waste Tire Management Recycling Act of 2003
    (Bill A2106)
  • 2.50 collected for each tire sold. 2 into fund.
  • Money to be used for identifying and cleaning up
    stockpiles, and using tires in civil engineering
    applications.
  • DOT, DEC, NYSTA and ESD are all named in the
    legislation.
  • Sunsets December 31, 2010. All sites were
    required to be remediated by then!

13
TDA as Fill Biggest Bang
  • DOT identified projects to use shreds as a
    substitute for ordinary fill
  • DOT set material requirements
  • DEC (through OGS) provided shreds for DOT to use
  • Open to other applications, although quantity
    used will be smaller and implementation will take
    more effort/time. (Better to keep separate from
    the initiative efforts).

14
DOTs Process (project level)
  • Identify and Select candidate projects
  • Identify the needed quantity, PSE, placement
    schedule
  • Provide design details
  • Show TDA source locations in contract documents
  • Provide specs for placement and trucking in our
    contract

15
On the supply end
  • DOT trained Inspectors of the shredding operation
    (OGS), shredding contractors, Construction
    personnel (for placement)

16
New Developments
  • Special specs for Material, Placement and
    Trucking
  • QA/QC procedures for sampling and testing GCP-19
  • Inspector training and certification course
  • Site selection and design guidelines GEM-20
  • MOU between DEC and DOT includes reimbursement
    for trucking

17
DOTs published guidelines
  • GCP-19 Sampling and Testing of Tire Shreds
  • GEM-20 Guidelines for the Selection, Design and
    Construction of Tire Shreds in Embankments

Completed in April , 2004, and subsequently
revised. See www.dot.state.ny.us/tech_serv/geo/ma
nuals.html
18
Project Selection
  • Geotechnical Engineers discuss projects with
    designers
  • Look for jobs with gt2.1 m fill, above water
    table, away from wells, water sources, NYC
    watershed
  • Select staging areas
  • Coordinate schedule with DEC, OGS

19
Quality Assurance Program
  • Inspector training course for OGS
  • GCP-19 set requirements, procedures
  • Inspectors sample and test every cone
  • Stockpiles are tracked

20
The Course
  • Consists of
  • Classroom lecture
  • Written test
  • Demonstrate proficiency in sampling and field
    testing procedures.
  • Earning certification depends on attendance and
    successful completion of all three elements.

21
Purpose of the course
  • To train and certify inspectors. At the end of
    the course, inspectors will be able to
  • Determine sampling intervals
  • Provide guidance to tire shredder
  • Conduct and interpret tests
  • Document test results
  • Inspectors have the responsibility of assuring
    that the shred stockpiles they accept meet DOT
    specification requirements.

22
(No Transcript)
23
(No Transcript)
24
Material Specs
25
What Makes a Good Shred?
  • Proper size (meets gradation requirements)
  • Clean cut edges (minimizes exposed steel)
  • Minimal exposed and free steel
  • No contaminants (gas, oil, hydraulic fluid, etc.)
  • At least one sidewall cut (to minimize cupping)
  • Relatively clean (no clinging dirt or mud)

While they dont have to be perfect, this is a
construction material.
26
Size Requirements
27
Measurement of Shred
  • Measured shred lengths from 1-1/2 inch to 16
    inches using a sizing board
  • Used it for protruding steel
  • Also used a No. 4 sieve

28
Why do we measure length rather than width, like
an aggregate?
29
(No Transcript)
30
Other Requirements
  • Visual
  • All shreds shall
  • have at least one sidewall severed from each
    shred.
  • have less than 1 by weight of free steel.
  • Protruding Steel
  • Tire shreds shall conform to the following
    requirements for protruding steel
  • - Metal wires protruding more than 2 inches from
    the edge of any tire shred 0.
  • - Metal wires protruding between 1 inch and 2
    inches from the edge of any tire shred 0 25
    of the shreds by weight.
  • - All shreds with metal wires protruding less
    than 1 inch from the edge of any tire are
    acceptable.

31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
A nice pile of chips, with free steel visible
35
(No Transcript)
36
(No Transcript)
37
Rejection
  • If shreds fail a test
  • All shreds produced in that batch are rejected
    discard or reprocess (if possible)
  • Any rejected shreds that are reprocessed shall be
    sampled and tested again (sample from the cone)
  • Discuss the results with the shred processor
    immediately. Instruct him to take immediate
    measures to rectify the problem.
  • Record the failing results on the Tire Shreds
    Documentation Form.

38
Processing
39
(No Transcript)
40
(No Transcript)
41
(No Transcript)
42
(No Transcript)
43
(No Transcript)
44
(No Transcript)
45
(No Transcript)
46
(No Transcript)
47
Construction Details and Requirements
48
Embankments
  • Tire shred layers are 1 m max
  • 1 m cover on the side slopes
  • Each layer is wrapped in geotextile
  • Multiple layers are allowed, with 0.6 m compacted
    earth in between
  • No shreds within 1.5 m of the top of finished
    grade

49
Typical Section
50
Projects
51
I87 Grade Crossing Elimination 1.1 M
tires Route 240X/Cattaraugus Creek 300 K
tires Route 219 Section V 1.8 M tires I87 Bridge
Replacement 1 M tires I84-I87 Interchange 380 K
tires (140 K used by DOT)
52
(No Transcript)
53
(No Transcript)
54
(No Transcript)
55
(No Transcript)
56
(No Transcript)
57
(No Transcript)
58
(No Transcript)
59
(No Transcript)
60
(No Transcript)
61
(No Transcript)
62
(No Transcript)
63
(No Transcript)
64
Performance
  • All projects were required to have a 30 day
    waiting period under a 2 surcharge (all projects
    wintered over).
  • Post-paving settlements were negligible.
  • No problems to date

65
  • One project saw a blowout, necessitating
    installation of a weep.

66
Program Summary
  • 5.6 M PTEs used
  • 81 inspectors trained and certified
  • 6 projects in 5 Regions
  • Reviewed well over 1,000 inspection forms
  • Duration of effort was 2003 to 2008

67
Other Applications for Recycled Tires.
68
Tire Chips as Subgrade
  • Delaware County

69
Tire Bales
  • Chautauqua Co

70
(No Transcript)
71
(No Transcript)
72
Thank You!
  • Feel free to contact Don Dwyer of the
    Geotechnical Engineering Bureau
  • ddwyer_at_dot.state.ny.us
Write a Comment
User Comments (0)
About PowerShow.com