Title: Network Planning Task Force


1
Network Planning Task Force
Setting the Stage
2
Active Task Force Members http//www.upenn.edu/co
mputing/group/nptf/
  • Mary Alice Annecharico / Rod MacNeil, SOM
  • Robin Beck, ISC
  • Doug Berger / Manuel Pena, Housing Conference
    Services
  • Chris Bradie, Business Services
  • Chris Field, GPSA (student)
  • Cathy DiBonaventura, School of Design
  • Geoff Filinuk, ISC
  • Bonnie Gibson, Office of Provost
  • Roy Heinz / John Keane, Library
  • John Irwin, GSE
  • Marilyn Jost, ISC
  • Carol Katzman, Vet School
  • Deke Kassabian / Melissa Muth, ISC
  • Mike Lazenka, ISC
  • Robert Helfman, Budget Mgmt. Analysis
  • Dan Margolis, SEAS (student)
  • Chris Massicotte, Audit Compliance
  • Gerry McCartney / David Seidell, Wharton
  • Kayann McDonnell, Law
  • Donna Milici, Nursing
  • Dave Millar, ISC
  • Michael Palladino, ISC (Chair)
  • Andrew Rappe, Chemistry Faculty
  • Dan Shapiro, Dental
  • Mary Spada, VPUL
  • Marilyn Spicer, College Houses
  • Steve Stines / Jeff Linso, Div. of Finance
  • Ira Winston / Helen Anderson, SEAS, SAS

New FY 04
3
NPTF Meetings
  • Dates
  • 9/15, 9/29 (130 330 PM), 10/6, 10/20?, 11/3,
    11/17
  • 12/1 State of the Union
  • Time
  • 130 300 PM
  • Place
  • 357A conference room at 3401 Walnut Street, 34th
    street entrance, elevator to 3rd floor (near
    Starbucks)

4
NPTF Agenda
  • Review process, principles and budget assumptions
    used in 5-year budget submission.
  • Discuss operational/baseline activities.
  • Address challenges/topics and future directions.
  • Review NT financial information.

5
NPTF Process
6
NPTF Process (Continued)
  • Summer focus groups helped
  • Reaffirm process and principles
  • Update budget assumptions
  • Identify issues and concerns
  • Provide good operational feedback
  • Craft agenda for the Fall task force
  • Focus on need for more strategic discussions

7
NPTF Process (Continued)
  • If no objections, operational feedback will be
    addressed with Six Schools as a subcommittee.
  • Over billing for ports / ghost ports
  • High-cost of small wireless installations and
    ongoing charges
  • Confusing intake process for installations
  • Prodesk/NT NOC coordination
  • Confusing web (forms, outdated files)

8
NPTF Principles
  • Customers and ISC work as partners when making
    decisions.
  • Alignment with academic, research and business
    strategies of the University.
  • Network is key to many other investments across
    Penn.
  • Be a leader, not a follower. Decisions based on
    identifying competitive advantage over our peers.
  • Model flexible enough to accommodate for changing
    technologies.
  • Model encourages retirement of legacy services
    and systems.

9
NPTF Principles (Continued)
  • Use continuous process improvement approach to
    seek maximum cost-effectiveness and high degree
    of customer satisfaction.
  • Model should be rational from both a client and
    ISC perspective and be measurable in terms
    meaningful to client.
  • Model must be structured so that increasing
    demands that are fueled by rising service
    delivery requirements and expectations can be
    met. (Demand-based)
  • Keep funding model simple. (Currently, IP
    addresses are used as billing metric for Central
    Service Fee.)

10
NPTF Principles (Continued)
  • All operating expenses (business continuity,
    redundancy, planning, support, security) must be
    included in model.
  • Make costs visible for Network,
    Telecommunications and Video Services.
  • Identify tradeoffs.
  • Clarify expectations (SLAs).
  • Encourage standards and best practices (NPC).
  • Eliminate, reduce, or at least be aware of
    cross-subsidies.

11
Budget Assumptions
  • Security concerns are a top priority as various
    viruses, worms, etc. have reduced Penns
    productivity levels. These concerns will
    constitute a significant portion of the Fall NPTF
    discussions.
  • 5 year phase-out of allocated monies (2.317M) to
    occur from FY2003-07.
  • Telecommunications surplus, operating
    efficiencies and increased costs to offset
    allocated cost phase out.
  • Aggregate PennNet, Telecommunications and Video
    service rate increases projected at 1-2 maximum
    yearly, determined in conjunction with NPTF.

12
Budget Assumptions (Continued)
  • Excellent bandwidth management techniques
    combined with a good Internet strategy have eased
    the pressure on developing tiered network
    connectivity options. However, this will
    continue to be explored and evaluated as the
    need/opportunity arises.
  • Separate SLAs for College Houses and Greeknet for
    maintenance and bandwidth.
  • FY2004-09 budget assumes Next Generation PennNet
    project averages 700k, down from original
    837k/year.
  • NGP sources of funding include the
    Telecommunications surplus and the CSF as the
    allocated monies are phased out.

13
Budget Assumptions (Continued)
  • There will be no rate increases for existing
    services for Telecommunications and in FY 04 and
    05.
  • For FY2005 College House students will continue
    to be billed indirectly as part of housing fees
    for baseline PennNet and Penn Video Network
    services.
  • Building entrance and router equipment are on a
    four-year replacement cycle.
  • Closet electronics and network servers are on a
    three-year replacement cycle.
  • NT will run a fiscally self-sufficient GigaPoP
    (MAGPI) and break even in FY 04 and beyond.

14
Budget Assumptions (Continued)
  • The CSF will subsidize approximately 800 wired,
    public lab connections that have computers
    attached in FY2004. TBD for FY2005.
  • The growth rate in IP addresses from the
    schools/centers is projected to increase by 1800
    per year from FY2004-09.
  • In FY2004, the IP address growth projection is
    800, as SOM and others do clean-up.
  • ISC managed wallplates projected growth at 1800
    new per year.

15
Budget Assumptions (Continued)
  • To retain and recruit appropriate NT IT staff,
    4 compensation has been budgeted to include
    annual performance increases, equity increases,
    bonuses, promotions and reclassifications from
    FY2004 - 09.
  • In FY2004 a 54.2 overhead rate was calculated to
    cover costs of benefits, rent, training,
    computers, telephones, etc. TBD for FY2005.
  • The NOC will not be physically staffed (7x24x365)
    through FY2009. It will continue to operate from
    6 AM 11 PM, M-F with the rest of the week
    covered by technical staff on beepers.
  • NT total expense budget increases from 22.5M in
    FY 04 to 24.2M in FY 09.

16
ISC NT FY 2004-09 Projected Revenue (All Sources)
17
Projected Telecommunications Revenue (FY2004)
18
Fall Challenges
  • Security
  • There are many threats to the network and data
    security from viruses, worms, etc.
  • This has resulted in a loss of productivity for
    Penn.
  • A host of services may need to be developed and
    deployed including VPNs, firewalls,
    intrusion-detection, virus protection, patch
    management, etc.
  • We must take every opportunity to educate IT and
    senior administrators in search of solutions for
    these most pressing problems.

19
Fall Challenges (Continued)
  • Telecommunications/Infrastructure
  • After the contract expires in July 2005,
    Telecommunications services costs from Verizon
    may increase.
  • Aging Telecommunications and Video
    infrastructure.
  • Aging Telecommunications equipment.
  • With the continued financial shake-up in
    Telecommunications, we may see a decrease in
    competition and therefore higher rates.
  • Moving towards VoIP may help, but a serious
    investment is necessary to upgrade Penn to new
    infrastructure and equipment.

20
Strategies
  • Examine Security Needs
  • Take realistic look at cost of productivity loss
    given current threats.
  • Create new revenue
  • Deploy new services as needed and as
    opportunities arise. (Cellular, VoIP, digital
    movies, etc.)
  • Rollout tiered network connectivity as soon as it
    is ready
  • Revisit Central Services List
  • Slow down Next Generation PennNet
  • Decrease redundancy
  • Decrease services

21
Strategies (Continued)
  • Continue to find operating efficiencies
  • Lower vendor expenses
  • Eliminate staff and contractors
  • Charge for unregistered IP addresses, private
    subnets, fiber circuits, domain names, etc.
  • Complete full audits for all services and charge
    out more accurately.

22
FY2004 Projected CSF Expenses
23
FY 02 vs. FY 03 School NT Expense Comparison
24
Operational Discussions
  • Review CSF bundle of services
  • Internet
  • Public lab subsidy
  • Internet2
  • Building/backbone upgrades
  • Voice services (cellular, VoIP, etc.)
  • Routing core upgrades
  • Next Generation PennNet (building redundancy)
  • Wireless authentication

25
Strategic NPTF Fall Challenges/Topics
  • Security (VPNs, firewalls, intrusion-detection,
    virus protection, patch management)
  • On-line directory operational funding
  • Authorization
  • Wireless authentication in CSF?
  • Wired authentication
  • More public wireless how to fund?
  • Public lab IP subsidy
  • Time to phase out and swap for wireless IP
    subsidy?
  • Tiered network connectivity options
    possible/necessary for FY 05?

26
Future Meetings
  • 9/29
  • 10/6
  • 10/20?
  • 11/3
  • 11/17
  • 12/1
  • Security Discussions (Part I)
  • Operational financial discussions
  • Security discussions (Part II)
  • Other strategic discussions
  • Voting / preliminary rate setting
  • State of the Union