Title: Location Public Hearing


1
Location Public Hearing
  • Brief Presentation Begins at 600 pm
  • May 28, 29, 30, 2002

2
Welcome!
  • William C. Cuttler, P.E.
  • Fairfax Preliminary Engineering Manager

3
Capital Beltway Study
  • Overview
  • Purpose
  • Alternatives
  • Draft EIS
  • Public Input
  • Project Study Team
  • Federal Highway Administration
  • Virginia Department of Transportation
  • Fairfax County Department of Transportation
  • Virginia Department of Rail and Public
    Transportation
  • Metropolitan Council of Governments
  • Northern Virginia Transportation Commission
  • Washington Metropolitan Area Transit Authority
  • Metropolitan Airports Authority
  • Maryland State Highway Administration

4
Coordination with Other Studies
  • Springfield Interchange
  • Capital Beltway Rail Feasibility Study
  • I-66 Major Investment Study / EIS
  • Dulles Corridor Rapid Transit Project
  • Northern Virginia 2020 Transportation Plan
  • Marylands Capital Beltway Corridor
    Transportation Plan

5
Public Coordination
  • Public Meetings
  • Civic and Community Groups
  • Citizen Workshops
  • Fairfax County Task Force

6
Public Coordination
  • Public Meetings
  • Civic and Community Groups
  • Citizen Workshops
  • Fairfax County Task Force
  • Public Information Tools
  • Telephone Hotline
  • Internet Website
  • E-Mail Address
  • Mailing List
  • Newsletters
  • Brochures

7
Purpose Improve Safety and Mobility
8
Purpose Improve Safety and Mobility
  • Past
  • Current
  • Future

9
Major Investment Study
  • Further Evaluate Feasibility of Beltway Rail
    Transit
  • Advance Highway Improvements to National
    Environmental Policy Act (NEPA) Phase
  • Coordinate with Other Major Studies in the Region

10
Rail Feasibility Study
  • Advance the Study to the Alternative Phase
  • Perform Similar Studies for Other Rail Projects
  • Further Examine Land Use and Transit Relationship
  • Coordinate Highway and Transit Improvements in
    the Beltway Right-of-Way

11
Draft Environmental Impact Statement
  • No Build vs. Build Alternatives
  • Candidate Build Alternatives
  • Location Approval by the Commonwealth
    Transportation Board

12
Project Overview
  • Ken Wilkinson
  • Environmental Project Manager

13
Why was the Study Initiated?
  • Improvements to the Capital Beltway are needed
    to
  • Correct Safety and Design Deficiencies
  • Address Current and Future Congestion
  • Increase Capacity of Roadway
  • Connect Regional HOV Network
  • Provide Dedicated Express Bus Facilities
  • Improve Operations and Traffic Flow
  • Reduce Cut-Through Traffic

14
What Did the Study Involve?
  • Traffic Analysis
  • Development of Alternatives
  • Detailed Engineering, Traffic Operations, and
    Environmental Analysis
  • Draft Environmental Impact Statement

15
Traffic Analysis
  • Travel Demand Modeling
  • 2020 Traffic Volumes and Travel Patterns
  • Evaluation of Traffic Operations
  • Beltway
  • Interchanges
  • Intersecting Roadways

16
Traffic Volumes
17
Wide Range of Alternative Solutions
  • Rail Transit
  • Express Bus
  • Transportation System Management
  • Highway Improvements

18
Highway Improvements
  • Build Alternatives
  • 3 Mainline Alternatives
  • Improvements at 10 Interchanges
  • Direct HOV Access at Route 29

19
Concurrent HOV
  • 2002 Preliminary Cost Estimate 2.5 - 2.8
    Billion

20
Express / Local with HOV
  • 2002 Preliminary Cost Estimate 3.0 - 3.25
    Billion

21
Barrier-Separated HOV
  • 2002 Preliminary Cost Estimate 2.7 - 2.9
    Billion

22
Environmental Document
23
Impact Assessments
  • Land Use
  • Socio-Economics
  • Natural Environment
  • Parks and Recreation Areas
  • Air Quality
  • Noise
  • Cultural Resources
  • Visual and Aesthetic Conditions
  • Hazardous Materials

24
Summary of Environmental Impacts
Barrier- Separated HOV
Express/ Local with HOV
Concurrent HOV
Noise Impacts (Dwellings)
3,879
3,717
3,672
Dwellings Protected
5,123
5,199
5,129
Homes Displaced
206-217
258-294
219-258
Businesses Displaced
19-31
20-32
20-32
Parkland Required (Acres)
15.05
18.13
19.88
Historic Resources Affected
1
1
1
Wetlands Displaced (Acres)
4.62
4.74
5.06
25
Remaining Schedule
JAN 1997
JUL-NOV 1998
NOV 1998
  • Location Public Hearings
  • CTB Decision
  • Final Environmental Impact Statement
  • Record of Decision
  • Design and Construction

CITIZEN WORKSHOPS
MAJOR INVESTMENT STUDY (MIS)
DEVELOP CONCEPTS TO IMPLEMENT MIS STRATEGIES
NOV 1998-JUN1999
MARCH 2002
JUN 1999
DRAFT ENVIRONMENT IMPACT STATEMENT
CITIZEN WORKSHOPS
REFINE IMPROVEMENT ALTERNATIVES
MAY 2002
SUMMER/FALL 2002
FALL 2002
FINAL ENVIROMENTAL IMPACT STATEMENT
LOCATION PUBLIC HEARING
COMMONWEALTH TRANSPORTATION BOARD ACTION
FALL/WINTER 2002
RECORD OF DECISION
DESIGN AND CONSTRUCTION
26
Public Input
  • Comment Forms
  • Letters
  • E-Mail
  • Court Reporter
  • Comment Tonight

27
CommentsandQuestions
28
Panel
  • Bill Cuttler VDOT Fairfax Preliminary
    Engineering
  • Ken Wilkinson VDOT Environmental
  • Debra Moore VDOT Right-of-Way
  • Bob McDowell HNTB
  • Jim Curren TransCore
  • Steve Walter Parsons Transportation Group

29
Contact Us
Call the Hotline at 703-352-7185
E-mail us at beltway_study_at_parsons.com
Visit our web site at http//project1.parsons.com
/capitalbeltway
  • Send comments to
  • Capital Beltway Study
  • c/o Parsons Transportation Group of Virginia
  • 10521 Rosehaven Street, 2nd Floor
  • Fairfax, Virginia 22030

30