Title: Entergy Gulf States, Inc' Texas Proposed Transmission Reliability Projects
1Entergy Gulf States, Inc.(Texas)Proposed
Transmission Reliability Projects
- Entergy Transmission Planning Summit
- New Orleans, LA
- July 10, 2003
2Texas
32004 EGSI-TX Proposed Transmission Reliability
Projects
Possible additional D-SMES or other devices
EGSI-TX Capacitor Bank Reliability
Improvements (Multi-year)
230 kV Line 422 (Helbig-Amelia) Line
Upgrade CARRYOVER
230 kV Line 821 (Jacinto-Porter) CCN
69 kV Beaumont Reliability Improvements (Multi-yea
r)
Porter 230/138 kV Substation (Multi-year)
69 kV Neches Reliability Improvements (Multi-year)
230 kV Line 822 (China-Porter) New
Construction (Multi-year)
230 kV Line 599 (Amelia-China) Line
Upgrade (Multi-year)
69 kV Line 6 (Amelia-Raywood) Reliability
Improvements (Multi-year)
469 kV Line 6 (Amelia-Raywood)Reliability
Improvement Plan
2004-08
- Goals
- Increase Sectionalizing Capability to reduce
restoration time - Enhance Voltage Support
- Increase Line Capacity
- Completed/In Progress Projects
- Install 69 kV circuit breakers at Batson, Sour
Lake, Daisetta substations - Install additional sectionalizing equipment
(i.e., motor-operated switches, motor mechanisms,
RTUs) - Upgrade line capacity from Raywood Substation to
Hull Tap - Estimated Cost 1.2M
- Additional Improvements for 2004 and beyond
- Install 14 MVAR capacitor bank at Batson 69 kV
substation - Upgrade capacity from Amelia Substation to Hull
Tap - Estimated Cost 8M
52004-08
V
6230kV Line 821 (Jacinto-Firetower-Porter)Certifi
cate of Convenience and Necessity (CCN)
2004
- Additional load growth (industrial, commercial,
residential) in the eastern part of Montgomery
County located in Entergy's Western Region has
exacerbated the single contingency overload of
several 138 kV transmission lines. These 138 kV
transmission lines are some of the key east-west
tie lines within the EGSI-TX service territory. - Overloading on 138 kV Line 571 (Jacinto-Tamina)
have the potential to occur under the single
contingency loss of 138 kV Line 86 (Dayton
Bulk-New Caney) In addition, overloading may
occur on 138 kV Line 50 (Dayton-New Long John)
and 138 kV Line 150 (New Long John-Cleveland)
upon the single contingency loss of Line 568
(China-Jacinto) 230 kV in 2004.
7230kV Line 821 (Jacinto-Firetower-Porter)CCN
(contd)
2004
- A proposed 2005 project to build a 230 kV
transmission line from China to Porter/Tamina 230
kV substations along with the construction of a
new 230/138 kV substation at Porter/Tamina will
relieve these single contingency line overloads.
However, this project does not meet the need of
the local distribution customers in the immediate
Firetower area (Eastern Montgomery County). - To serve the immediate needs in the Firetower
area, a customer-owned radial transmission line
is proposed as a temporary solution for 2004.
The long term needs of the area will be met by
the proposed Line 821 (Jacinto-Porter) 230 kV. - Estimated Cost 400k
8Proposed Transmission Service for Firetower
Substation
Jacinto
- 2003-04
- 400 k
- Utilize existing customer-owned 138 kV
transmission line
Firetower
Splendora
Apollo
Tamina/Porter
Customer-owned line sub
Temporary Firetower Service
Jacinto
- 2005
- 3.6 M
- construct 6-mile radial at 230 kV and energized
from Porter 138 kV 2005 to Firetower 138 kV - 2007-08
- 11.2 M
- construct 18-mile to complete line from Firetower
to Jacinto 230 kV substation
Firetower
Splendora
Apollo
Tamina/Porter
Customer-owned line sub
Long Term Firetower Service
92004-05 EGSI-TX Transmission Western Region
Improvement Plan Phase II
Phase II of the Western Region Improvement Plan
addresses the projected load growth in 2005. In
2003, several planning studies have indicated the
Western Region has the potential to encounter
dynamic voltage stability problems and thermal
overloading under the double contingencies listed
below. Load at risk in 2005 is 158 MW under
any of the following double contingencies Loss
of Lewis Creek Unit 345 kV Line 119
(Crockett-Grimes) Loss of Lewis Creek Unit 230
kV Line 568 (China-Jacinto) Loss of both Lewis
Creek Units
1
5
3
2
4
63M
10EGSI-TX Capacitor BankReliability Improvement
Plan
2003
- Due to the limited supply of reactive power from
generation sources in the EGSI-TX service
territory, capacitor banks provide critical
additional reactive power support. - In recent years, several different factors have
contributed to violent failures of EGSI-TX
capacitor banks - Size of pre-insertion devices
- Relaying on capacitor banks
- To prevent such failures, some capacitor banks
will be targeted for reliability improvements in
2003 and beyond that may include - Installation of new pre-insertion devices
- Installation of new switches equipped with
pre-insertion devices - Installation of new relaying equipment
- Relocation of some capacitor banks to
electrically distance the banks - Replace obsolescent equipment associated with
capacitor banks
112003
EGSI-TX Capacitor BankReliability Improvement
Plan(contd)
- As an interim solution, Entergys transmission
planning, operations, and maintenance departments
are in the process of evaluating operating
procedures and work practices to develop a set of
operational guidelines to reduce the frequency of
capacitor bank switching until long-term
solutions can be implemented. - Safety Concern
- Estimated Cost To be determined per each
capacitor bank repair
12Neches Station Reliability Improvement Plan
2004
- Neches substation was constructed in conjunction
with Neches Power Plant in 1926-27. Most of the
stations existing equipment operating today
pre-dates the 1960's. There are 12 breakers over
47 years old still in service. Many of the
switches , potential transformers, all of the
insulators and other related equipment are also
all over 40 years old. There is also
environmental concern over old PTs and bushings
that have never been tested for PCB content. - At this time, Neches substation serves primarily
industrial and residential load. The control
house for Neches is inside the Neches station
generation station. Demolition of the retired
generating facility has already begun.
- In 2001, a new control house was proposed to be
built at a an estimated cost of 3.25 million. It
was later determined that the option to build a
new control house was not a permanent,
cost-effective solution.
13Neches Station Reliability Improvement Plan
(contd)
2004
- Recommended solution Reconfigure Neches
substation - Phase I Move load off of the 69 kV system at the
existing Neches station. IN PROGRESS - Phase II Acquire CCN for new 138 kV transmission
line Carroll St-Viway - Phase IIIMove existing Entergy load off of the
34.5 kV system at the existing Neches station. - Phase IV Construct new 138 kV Neches bus on
adjacent property and relocate 138 kV
transmission lines. - Tie 138kV Line 457 (Neches-Carroll St) with 138kV
Line 172 (Sabine-Neches) - Construct 2 miles of 138 kV transmission line to
complete Carroll St-Viway 138 kV - Phase V Construct new 69 kV bus and relocate 69
kV transmission lines. - Phase VI Relocate Vidor 69 kV load to the 230 kV
system - Estimated Cost 6.5M
Mayhaw
Vidor
Viway
Exxon-Mobil
Neches
Carroll St
Mobil2
Pennwalt
Glycol
Houston Chemical
14Beaumont 69 kV Reliability ImprovementsHelbig
230/69 kV Substation ReconfigureAmelia 230/69
kV Substation Reconfigure
2004
- The Beaumont 69 kV subsystems are separated by a
normally open circuit breaker at Crockett 69 kV
substation. The western portion of this subsystem
is served by Amelia 230/69 kV substation and
Helbig 230/69 kV substation. Both substations
have a bus-tie breaker configuration. - Contingency Loss of the Helbig 69 kV bus or
loss of the Amelia 69 kV bus due to a bus-tie
breaker failure has the potential to cause
cascading outages on the 69 kV subsystem that
serves the Beaumont commercial and residential
area. - Interim Solution In 2001, 69kV Line 466
(Goodyear-West End) was upgraded and the normally
open breaker at Crockett 69 kV substation was
closed. However, under the new operating
configuration, the loss of Helbig 69 kV source
may cause Line 98/190 (Nitro-S. Beaumont 69kV) to
overload.
15Beaumont 69 kV Reliability Improvements Helbig
230/69 kV Substation ReconfigureAmelia 230/69
kV Substation Reconfigure(contd)
2004
- Recommended Solution Reconfigure Helbig 230/69
kV substation with additional bus-tie breaker.
Reconfigure Amelia 230/69 kV substation with
additional bus-tie breaker. Close the
normally-open breaker at Crockett 69 kV
substation. - Estimated Cost 4.8M
16(No Transcript)
172005 EGSI-TX Proposed Transmission Reliability
Projects
Possible additional D-SMES or other devices
EGSI-TX Capacitor Bank Reliability
Improvements (Multi-year)
230 kV Line 821 (Jacinto-Porter) (Multi-year)
Porter 230/138 kV Substation (Multi-year)
230 kV Line 822 (China-Porter) New
Construction (Multi-year)
230 kV Line 599 (Amelia-China) Line
Upgrade (Multi-year)
69 kV Line 6 (Amelia-Raywood) Reliability
Improvements (Multi-year)
182006-2010 EGSI-TX Transmission Reliability Target
Areas (Beaumont and Port Arthur Areas)
138 kV Line 449 (Toledo-Newton) Line Overload
138 kV Line 97 (Rayburn-Doucette) Line Overload
138 kV Line 455 (Jasper-Rayburn) Line Overload
Stowell 138/69 kV Auto Overload
69 kV Line 461 (Dupont Beaumont-Kolbs) Line
Overload
69 kV Line 581 (Helbig-West End) Line Overload
69 kV Line 427 (Port Neches-Goodrich) Line
Overload
192006-2010 EGSI-TX Transmission Reliability Target
Areas (Western Region)
138 kV Line 596 (Lewis Creek-Longmire) Line
Overload
138 kV Line 93 (Doucette-Corrigan Bulk) Line
Overload
138 kV Line 430 (Cypress-Menard) Line Overload
138 kV Panorama/Longmire/ Dobbin/Navasota Low
Voltages
Cypress 500/230kV 230/138 kV Auto Overload
138 kV Line 571 (Jacinto-Tamina) Line Overload
138 kV Line 187 (Cypress-Rye) Line Overload
138 kV Line 50 (Dayton-New Long John) Line
Overload
230 kV Line 599 (Amelia-China) Line Overload
138 kV Line 86 (Dayton-New Caney) Line Overload
202006-10 EGSI-TX Tentative Solution
230/138 kV Lewis Creek Substation (2007-08)
230 kV Line 524 (Jacinto-Lewis Creek) (2007-08)
230 kV Line 821 (Porter-Lewis Creek) (2010)
New 230kV Line (Cypress-Jacinto) (multi-year
project) (2007-08)
230 kV Line 821 (Jacinto-Firetower) (2006-07)