Title: From Here to Construction
1From Here to Construction
- Michael Hebert
- UC Irvine
- March 9, 2004
- NSF RSVP Review
2Outline
- The Importance of, Status of, and Plans for the
Magnet Acquisition - A Review of each Level 2 WBS task examining
readiness, resource needs, and schedule to get
from here to construction - Summary of the proposal budget, schedule of
events that carries us to a construction start
3Opening Comments
- We are proposing to continue the design phase of
the magnet system in this grant period, including
funding four months of the estimated one year
magnet engineering design. We dont believe we
can wait for MRE-FC funding for the engineering
design effort. This allows us to maintain the
momentum on the critical path system. The
alternative could mean more than a years delay
in completing the project. - We have not requested support for every task that
we could start now due to the limited
availability of funding - We will make major progress on every subsystem,
in addition to the magnets in particular we will
greatly increase the engineering effort going
into MECO
4MECO Collaboration
- Institute for Nuclear Research, Moscow
- V. M. Lobashev, V. Matushka,
- New York University
- R. M. Djilkibaev, A. Mincer,
P. Nemethy, J. Sculli, A.N. Toropin - Osaka University
- M. Aoki, Y. Kuno, A. Sato
- University of Pennsylvania
- W. Wales
- Syracuse University
- R. Holmes, P. Souder
- College of William and Mary
- M. Eckhause, J. Kane, R. Welsh
- Boston University
- J. Miller, B. L. Roberts
- Brookhaven National Laboratory
- K. Brown, M. Brennan, G. Greene,
- L. Jia, W. Marciano, W. Morse,
Y. Semertzidis, P. Yamin - University of California, Irvine
- M. Hebert, T. J. Liu, W. Molzon, J.
Popp, V. Tumakov - University of Houston
- Y. Cui, E. V. Hungerford,
N. Klantarians, K. A. Lan - University of Massachusetts, Amherst
- K. Kumar
5Features of MECO
- 1000fold increase in m beam intensity over
existing facilities - High Z target for improved pion production
- Axially-graded 5 T solenoidal field to maximize
pion capture
Superconducting Solenoids
Muon Beam
1 T
1 T
Calorimeter
2 T
Straw Tracker
Stopping Target Foils
Proton Beam
- Curved transport selects low momentum m-
- Muon stopping target in a 2 T axially-graded
field to improve
conversion e- acceptance - High rate capability e- detectors in a constant 1
T field
2.5 T
5 T
Pion Production Target
6MECO MREFC Critical Path
The magnets directly determine when we finish
construction (stop spending MRE money) and start
full-scale data taking
7Magnet Progress
- As a reminder
- Conceptual Design completed on FY01 funds, very
favorably reviewed - Commercial procurement endorsed by Magnet
Acquisition Panel - Three Industrialization Studies completed using
FY02 funds - Insulation system for the coils and joints
recommended epoxy and other material choices for
radiation hard fabrication - Winding, impregnation logistics, fabrication cost
and schedule concluded that the magnets can be
built commercially within the nominal 41 month
schedule for a price consistent with our
expectations - Refrigerator/liquefier refurbish or buy new
recommendation - Procurement activities (more details in a moment)
- Magnet Acquisition Plan drafted
- Magnet Statement of Work and Technical
Specification-incorporating BNL and LLNL comments - RFP being drafted
- First meeting with potential vendors held at MT18
Conference in October
8Magnet Progress
- Field error analyses and other studies also
supported by FY03 funds - Updated structural models of PS, TS and DS
magnets from CDR to evaluate effects of modulus
and coefficient of thermal contraction variations
and deadweight effects. - New PS iron return yoke and pole piece
- Revised PS coil builds
- DS includes new iron pole piece
- TS Stiffer and wider cryostat pedestals
- Relocated horizontal support in downstream TS to
accommodate DS pole - TS Cryostat shell modeling
9Magnet Progress
TS
PS
DS
- Created mandrel and mandrel assembly drawings
with tolerances and verified manufacturability
with commercial fabrication shops - Preliminary conclusions
- Field errors due to manufacturing tolerances and
material property variations appear manageable in
PS and DS TS analysis underway - DS field errors are driven by the mandrel and
assembly tolerances. Field analysis is underway
by UCI. - PS field errors are driven by the mandrel and
assembly tolerances but the field spec in the PS
region is forgiving. - TS structural model is most complicated. Awaiting
updated results. - Final results will be reflected in the final RFP
documents
10Draft Magnet Acquisition Plan
- Draft exists and will be submitted for NSF
approval shortly - Establishes roles of all major players
- MIT Subsystem Manager and COTR, chairs bid
review panel - LLNL provides Contracting Officer backed by the
experience of the whole NIF contracting team - UCI provides source selection official, funds
vendor contract - NYU provides MREFC funds to UCI for all MECO
effort concurs with UCI source selection - BNL provide site access and interface
information, operational requirements via MDMG,
participates in bid review panel - Summarizes estimated design, construction, and
life cycle costs - Discusses commercial, technical, manufacturing,
and ESH risks - Lays out the procurement plan (next slide)
11Magnet Procurement Plan
- Assumes the final design, fabrication,
installation and acceptance testing will be
performed by a commercial vendor or a team of
vendors. - Identifies method as Best Value Source Selection
- Identifies firms have required capabilities or
known to have an interest - ACCEL
- Alahlam Ltd.
- Ansaldo Superc
- Babcock Noell Nuclear GmbH
- Cryogenic Ltd.
- General Atomics
- Hitachi
- Establishes a fixed price, contract as the
preferred option allows for industry feedback
at draft RFP stage - Discusses possibility of splitting out high cost
risk interface items and/or installation - Establishes management information requirements
reporting, QA, etc.
- Mitsubishi Electric Corp.
- Oxford Instruments
- Sigmaphi
- Space Cryomagnetics
- Toshiba
- Wang NMR Inc.
12Draft Magnet Acquisition Schedule
- This list assumes an uninterrupted flow of funds,
i.e. an FY05 MREFC start or continuing RD
support for the engineering design in 05
13Baseline Information Today
- MECO WBS exists, but needs extensive revision.
This is job one. - Reference Design Documents listing design and
interface parameters exist for some systems.
Will need initial versions for the remaining
major systems as part of completing 1 above. - WBS Dictionary again exists, but must be
revised in conjunction with 1. - Cost Database system, including risk assessment
handling, is loaded with the preceding info as of
Jan 2003. As 1 3 above evolve, we will
incorporate the changes. - Cost Book exists, but is sparsely populated
with solid backup material. - Subsystem schedules exist in detail for the
magnets and for the proton beamline work.
Schedules for all other subsystems exist, but in
coarser grain. - Technical Design Report exists only in draft
form, but has not been updated since June 2001.
Details needed for engineering efforts have
instead been captured in the Reference Design
Documents mentioned above - Project Management Plan exists but will require
revision
14Near Term Milestones
- Preparation for a baseline review in July
Note that new hires under this proposal are not
going to be on board soon enough to contribute
much to the baselining effort
15Reviewing Each L2 WBS
- The following slides review each MECO level 2 WBS
task - Current status and recent development progress
- Specific needs for baselining
- Preparation for construction
- Near term schedule of activities
- Costs listed are those included in the pending
proposal
16WBS 1.4 Solenoids
- Resources Needed to Baseline - 558k
- Support for MIT PSFC to continue in their
oversight role and update cost information for
the baseline. This number includes the SSM and
additional FTEs to support the engineering design
effort for the four months covered under this
grant (this actually extends beyond establishing
the baseline) - Starting the Engineering Design - 1545k
- Four months of design effort by an estimated team
of 22 engineers, designers, and managers working
for the magnet construction vendor - Cost risk reduction studies at MIT and component
fabrication vendors - Contracting Officer support at LLNL
- Part-time support for magnet and cryogenics
experts at BNL to participate in Magnet Design
Management Group, providing facilities interface
and safety information to magnet contracting team
17WBS 1.4 Solenoids
Draft RFP Released This Month
Final RFP Rel. Sept. 04
Engineering Design Commences in March 05
18WBS 1.1 AGS Modifications, Studies
- Current Status
- No beam studies since 1998 nor hardware design
efforts - Hardware consists of a new AC dipole similar to
an existing magnet and new pulser and power
supply for the existing stripline kicker,
requirements based on existing studies info - New concerns about ALARA limits, available
running time, and aperture limits - Resources Needed to Baseline - 0
- Extensive beam studies will be required to
achieve MECO running conditions. Nonetheless we
have omitted this from the proposal to direct
funds elsewhere. Our plan is conduct these
studies with MREFC funds. - AGS RF experts are needed to spec the hardware,
although their time is often saturated solving
RHIC problems
19WBS 1.1 AGS Modifications, Studies
- Preparation for efficient use of MREFC funds -
151k - Design of AC dipole, new pulsers for AGS Kicker
allow for construction and installation in 06
allowing for extinction measurement in 06/7 run
This is a Final Design Review, i.e. we are ready
to cut metal on the AC Dipole and procure of
pulsers and power supplies for the Kicker in
October 04
20WBS 1.2 Proton Beamline
- Current Status
- Some off-project effort by C-AD physicists
developing beamline optics to establish aperture
limits and hardware requirements - Preliminary shielding design and AGS floor layout
in A line by C-AD engineers - RF Modulated Magnet (RFMM) stripline and cavity
geometry studies at UCI - Resources required to baseline this effort - 37k
- Beamline Optical Design a prerequisite for all
other activity in the beamline, establishes which
magnets and instrumentation are needed note
this was previously assumed to be an off-project
research effort, now at our expense - Support for AGS Liaison Engineer is covered in
WBS 1.11 - Preparation for efficient use of MREFC funds -
447k - Shielding Design Start this long lead time task
now to begin labor (and ) intensive beamline
refurbishment in 05 - Instrumentation Controls design Allows for
procurement of instrumentation needed for beam
tests in 06/7 - RF Modulated Magnet conceptual design Allows
for prototype construction in 05, installation
in 06 shutdown, testing in 06/7
21WBS 1.2 Proton Beamline
Extracted beam parameters determined in August
RFMM design complete in January, prototype awaits
MREFC funds
22WBS 1.3 Target Heat Shield
- Current Status
- Initial version of Reference Design exists
- Extensive simulation, design, and testing of
water-cooled prototypes at UCI - Heat Shield conceptual design effort begun at
C-AD with FY03 funds - Resources required to baseline this effort - 57k
- Identify a long term subsystem manager talking
to a candidate now - Extend Heat Shield design work to full conceptual
design - Develop conceptual design of target cooling
and handling and storage systems - Preparation for efficient use of
MREFC funds - 35k - Extend target mockup tests to
realistic heat loads - Fabricate a test setup for later beam
testing
23WBS 1.3 Target Shield
Heat Shield and Target Remote Handling and
Storage System Designs complete in July
Production target design review follows prototype
beam testing on MREFC funds complete Jan 06
24WBS 1.5 Muon Beamline
- Current Status
- Vacuum, Collimator, m Beam Stop, n Absorber
Reference Designs exist - Vacuum window conceptual design completed on FY02
funds - Vacuum, m Beam Stop, and Absorber engineering
efforts ongoing at BNL - Vacuum studies, Beam Stop and Absorber
optimization at UCI - Resources required to baseline - 71k RD
- Complete BNL design work to provide detailed
magnet interface information and cost information - Preparation for efficient use of MREFC funds
- The primary motive to push these designs is to
develop the magnet interface info. With that in
hand we do not need greater detail before MREFC
start
25WBS 1.5 Muon Beamline
26WBS 1.6 Tracker
- Current Status
- Two tracker geometry options remain under
consideration - Longitudinal geometry with 3000 3m long straws
oriented nearly coaxial with the DS and 23000
capacitively coupled cathode strips for axial
coordinate measurement - Transverse geometry with 13000 1m straws,
oriented transverse to the axis of the DS,
readout at both ends - Two readout options under consideration as well
- Digitizing inside the DS cryostat or passing
analog signals out and digitizing remotely
Longitudinal Tracker
27Tracker RD
- Studies provide input to select geometry and
readout architecture - Full-length longitudinal vane prototype remains a
work in progress at Houston as mechanical
stability and straw bonding issues are resolved - Electronics design and prototype work at Houston
has progressed to testing prototype preamplifier,
digitizer, and controller boards as a system
using the current (outdated) version of BaBars
Elefant chip with very promising results - Simulations of both the longitudinal and
transverse geometries continue, indications are
that either geometry might work from a physics
standpoint
28WBS 1.6 Tracker
- Resources required to baseline this effort - 0
- We know enough about the tracker options to
reliably cost them without significantly more
engineering - Preparation for efficient use of MREFC funds -
414k - Mechanical and signal tests with full length vane
prototype - Revise the BaBar Elefant chip (from 0.8 mm to
0.25 mm technology) for MECO use a joint
venture between Houston and LBNL estimated to be
a one year design task, we are proposing to fund
six months of it under this grant - Full-time mechanical engineering support funded
under WBS 1.11 - Design and prototype a low mass manifold
29WBS 1.6 Tracker
Geometry Decision in November
30WBS 1.7 Calorimeter
- Current Status
- Bench tests of PbWO4 crystals cooled to 23 C
and large area avalanche photodiodes continue at
NYU using electronics designed and built in house - Indications are that this material will meet MECO
resolution requirements, demonstrating 20-30
photo e-/MeV (as compared with CMS 5 pe/MeV) - We need to verify the system performance via beam
tests of an 8?8 crystal array
- If true we can sharply reduce the contingency on
the Calorimeter that covered the possibility of
using BGO crystals - Further it appears that we can make use of fewer
(larger) crystals allowing reductions in APD, and
associated HV and readout channel counts (1152
crystals vs. 2000 originally)
Estimated
31WBS 1.7 Calorimeter
- Resources required to baseline this effort - 0
- We know enough to baseline this system now
- Preparation for efficient use of MREFC funds -
421k - Funds for construction of an 8 x 8 prototype
crystal array including photodetectors, cooling,
calibration, readout electronics, vacuum system
and test vessel - Funds for beam testing
- Contribution of the Chief Electrical Engineer
(funded in WBS 1.11) to the design of readout and
trigger electronics - In addition to verifying the primary approach
with an appropriate scale prototype, this
advances the design effort and should allow for
an early start to anticipated lengthy crystal and
APD procurement phases
32WBS 1.7 Calorimeter
Crystal Material Selected
Calorimeter Conceptual Design Review in June 05
33WBS 1.8 Cosmic Ray Shield
- Current Status
- Extensive testing at William Mary have
established a combination of scintillator,
wavelength shifter, and multi-anode PMT that will
meet MECOs 99.9 cosmic ray veto efficiency
requirement - Extrusion of 100 4m slats this summer at Itasca
following MINOS lead - Test slats will be assembled into a prototype
module this Fall - Resources required to baseline this effort - 53k
- Mechanical engineering support for William
Mary, either locally, or at BNL to assist in
developing a conceptual design for the counters
and particularly their installation beneath the
detector solenoid - Preparation for efficient use of MREFC funds -
90k - Materials and shop time to produce prototype
module components - Student labor for bonding WLS fibers into slats,
module assembly and testing at William Mary
34WBS 1.8 Cosmic Ray Shield
Veto Counter Conceptual Design Review in Sept 04
35WBS 1.9 Trigger DAQ
- Current Status
- No engineering has gone into the Trigger or DAQ
to date, although this has the potential to be a
long lead time item - Resources required to baseline this effort - 42k
- A fraction of the support for BUs Electronics
Design Facility (EDF) will be necessary to
develop at least a sketch level design for the
system and cost it out - Preparation for efficient use of MREFC funds -
241k - Support for the completion of EDFs design effort
- Components, prototype boards, test equipment
- Allows for testing of trigger hardware as part of
the Calorimeter and Tracker test beam studies
36WBS 1.9 Trigger DAQ
Trigger and DAQ Hardware Conceptual Design
Review in July 05
37WBS 1.10 Infrastructure
- Reminder that Infrastructure for MECO presently
refers to the counting house, electronics hut,
and compressor building for the refrigerator /
liquefier - Current Status
- Existing structures have been identified to serve
as counting house and compressor building,
although they will require some clean out and may
require refurbishment of power and other services - Electronics enclosure must be constructed, but is
small and simple - Resources required to baseline this effort - 0
- The construction cost and schedule estimation
effort on the part of the AGS liaison engineer is
supported under WBS 1.11 - Required design input information is funded under
WBS 1.4 1.7 - Preparation for efficient use of MREFC funds - 0
- This task is not on the critical path, nor are
detailed designs required to make efficient use
of MREFC funding in the first year, thus once we
have the information required for baselining, we
will be set until the project starts.
38WBS 1.11 Management
- Current Status
- Full time PM on board
- No other project office personnel
- Project documentation described earlier
- Resources required to baseline this effort -
300k - Ongoing PM support
- Support for AGS Liaison staff
- Preparation for efficient use of MREFC funds -
446k - Chief Mechanical Engineer This hire is needed
for integration as we approach construction and
to contribute to the pool of engineering talent
designing MECO - Chief Electrical Engineer the same statement
applies here - Cost and Schedule Manager The PM cannot
continue in this role as we gear up for
construction, so this individual should be on
board well before the start of MREFC funding to
setup shop and establish procedures
39WBS 1.10 1.11 Schedules
Updating the information needed for baselining is
straightforward. Detailed designs await MREFC
funds as this is not a place that we need to
spend money early.
These time estimates could prove optimistic
40Proposal MECO Budget 1
41Proposal MECO Budget 2