Dzero Run IIb PMG - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Dzero Run IIb PMG

Description:

SPI = BCWP/BCWS = 0.88, CPI = BCWP/ACWP = 2.43 ... should ideally be independent of any pre-conception as to the length of the shutdown. ... – PowerPoint PPT presentation

Number of Views:78
Avg rating:3.0/5.0
Slides: 15
Provided by: Jonathan5
Category:
Tags: pmg | dzero | iib | preconception | run

less

Transcript and Presenter's Notes

Title: Dzero Run IIb PMG


1
Dzero Run IIb PMG
  • Agenda
  • Upgrade/Project Status V. ODell
  • outline of Response to Directors review report
  • Trigger Status D. Wood
  • Silicon Layer 0 Status R. Lipton

2
Directors Milestones (31/07/2004)
3
Directors Milestones (31/07/2004)
4
Cost Performance Report(31/07/2004)
SPI BCWP/BCWS 0.88, CPI BCWP/ACWP
2.43 SPI Trigger 0.74, SPI Silicon 0.92, SPI
Online 1.11
5
Management Highlights July/August
  • MOUs/SOWs for life of project finished for
  • Columbia
  • Boston University (with CTT change request)
  • University of Arizona (with CTM change request)
  • University of Virginia MOU/SOWs in signature
    phase
  • Change requests
  • New change request for Silicon Pitch Adaptors, as
    recommended by Directors review
  • Small cost/no schedule impact
  • Production Readiness Reviews
  • Production readiness review for STT this Friday
    (9/10)
  • Will be organizing PRR for TAB/GAB soon
  • Installation/Commissioning
  • Many meetings with project personnel to review
    and fine tune the installation/commissioning
    schedule and plans

6
Directors Review L0
  • Recommendations
  • (About the delayed hybrid delivery) my only
    recommendation would be to follow up on the
    promised delivery, understand now if vendor is
    experiencing any problems, and have a team in
    place to wipe, probe, stuff, bond, and thoroughly
    test completed hybrids in late August/early
    September. The project leaders are all too aware
    that hybrid deliveries and hybrid quality issues
    are invariably the pacing items on silicon
    detector projects.
  • Done. Hybrids have now arrived and are being
    wiped. See talk by Ron Lipton.
  • (About keeping key personnel on project at SiDet)
    My recommendation would be for the project
    leaders to meet at SiDet with the PPD management,
    perhaps after the change in Division head, and to
    provide some introduction to the project and
    indicate what resources, including any key
    personnel, are needed for the construction
    effort. The project should take care to also
    include technician effort needed for support
    activities, such as modifying fixtures and
    building and assembling mock-ups.
  • We have made specific requests for key personnel
    for module production. This went through both D0
    department and SiDet and was requested to John
    Cooper. With the new management in place, we will
    set up such a meeting.
  • (About H-Disk refurbishment/L0 aperture
    measurements) From the presentations and
    follow-up discussions it is not clear to me how
    confident the project is in the aperture
    clearance for Layer 0 even with the proposed
    changes to reduce the profile of the detector. My
    personal instinct would be to remove and
    refurbish the H-disk detectors during the
    upcoming shutdown period and to inspect the
    aperture, perhaps with a boroscope, during the
    H-disk work. I would do this even in the absence
    of key personnel from Moscow State University.
    This would have the advantage of getting the
    H-disk work out of the way and, more importantly,
    assuring the project that there are no unknown
    restrictions within the 2.4 meter installation
    region. There is some risk to rest of the vertex
    detector with any of this work, and the D0
    collaboration would need to approve the
    operation. Also, I would not make this
    recommendation if the project leaders felt that
    it would sap resources that are needed for the
    module construction effort.
  • We have investigated H-Disk refurbishment/L0
    aperture measurements and other 04 shutdown
    activities and we will do the survey. The H-Disk
    refurbishment was dropped for lack of time during
    this shutdown. The inner H-Disks are better than
    we thought they were - 90 operational so will
    likely not be refurbished during the 05 shutdown
    either. See talk by Ron Lipton.

7
Directors Review L0
  • With the assistance of Marvin Johnson and others
    the project has done a good job in reducing
    pick-up noise effects of the type that plagued,
    and continue to plague, the CDF Layer 00
    detector. Still, in order to understand and
    mitigate any remaining operational or coherent
    noise issues it is important that the completed
    detector be operated at SiDet for a period of at
    least 6-8 weeks. I would hope that there would be
    enough flexibility in the Labs schedule that the
    start of the shutdown could even be delayed if
    necessary to accommodate this integration study.
  • Agreed. This was already in the schedule (6
    weeks). Any schedule gain that is made allows us
    a longer integration study. We will ensure at
    least 6 weeks even if the schedule is delayed.
  • The one week allotted between L0 Silicon
    Cable-up Complete and Silicon Ready for
    Resumption of Tevatron Operation seems to me to
    be a bit on the short side. However, it is
    difficult to scale from experiences on much
    larger silicon detector installation efforts to a
    single layer, 48 module system. I would recommend
    that as the time of the L0 installation shut-down
    draws near, the Project refines its timeline for
    the installation and technical commissioning
    based upon a firmer understanding of what the
    work will actually entail. The timeline should
    ideally be independent of any pre-conception as
    to the length of the shutdown.
  • We are continuously reviewing the installation
    schedule. What we learn during 2004 shutdown will
    be fed bak into the schedule. We will certainly
    revisit the installation timeline as installation
    dates get closer. Note that Silicon Ready for
    Resumption of Tevatron Operation does not mean
    the L0 is ready to take data we plan to leave
    the detector open for 6 weeks for debugging.
  • One last suggestion, and one that is outside the
    scope of this review For oversight and
    accounting purposes the upgrade project ends with
    the completed detector ready for delivery to DAB.
    However, I think that the D0 should view
    installation, commissioning both technical and
    physics, and maintenance as an interconnected
    process. In some ways it would be better if the
    installation of the Layer 0 detector was viewed
    as the beginning of a process. I would further
    hope that there be some continuity between the
    construction and commissioning efforts and that
    the commissioning team is as richly layered as is
    the current construction team. Finally, it is
    important for the D0 collaboration to give both
    support and prominence to the commissioning
    effort. These comments are made in light of a
    previous experience where the process did not go
    as smoothly as one would have wanted.
  • We agree with this and this is part of our
    motivation for impaneling the SC-IPC committee
    which is very actively reviewing the installation
    to physics commissioning schedule and effort
    using the experience of the full collaboration
    and with full support and participation of the
    construction and operations groups.

8
Directors Review - Trigger
  • Recommendations
  • Secure the manpower for all installation needed
    in the 2004 shutdown to allow testing during the
    data taking of FY05.
  • Agreed. This has been addressed see talk by
    Darien.
  • Establish a forum (presumably through the
    Director for Research) for ongoing dialog with
    CDF and the Accelerator Division on the timing of
    the FY05 shutdown (maybe this exists already).
  • Agreed. The director is aware of this.
  • It would be helpful to have a presentation on the
    trigger simulation and validation efforts some
    time in early 2005.
  • OK. Trigger simulation workshops are ongoing. We
    would be prepared to give such a presentation on
    this timescale.
  • It would be useful to have a presentation of the
    SC-IPC task list around the same time.
  • OK. SC-IPC gives regular updates to the
    collaboration.

9
Directors Review - AFEII
  • Recommendations
  • The committee feels that the collaboration should
    carefully consider their strategy, including when
    to make the decision whether or not to proceed
    with an AFE replacement.
  • We have done this. By combing through the
    schedule and performing some tasks in parallel we
    have gained 1 month. Our current schedule is
  • D0 internal review 12/04 (was 1/05)
  • Laboratory review 1/05 (was 2/05)
  • (final project approval)
  • Production begins 2/05 (was 3/05)
  • This means installation would begin 1/06
    (according to current schedule).

10
Directors Review - AFEII
  • Where we are
  • AFE II schedule has been revisited with an aim to
    speeding things along
  • Parallel layout of AFEII-t (instead of the
    original serial layout).
  • We would like Wessons group (PPD) to work on
    this.
  • This request has been transmitted to Jim Strait.
  • Current status
  • AFE II board close to being submitted (end of
    this week)
  • Expect an 3 week turnaround between submission
    and stuffed prototype board ready for testing
  • This implies prototype board will be ready for
    testing by October
  • Plan is for John Anderson to test the board
  • Mosis submission of TripT is in.
  • Prototype TripT chips due back 3rd week of
    October
  • We have had discussions with Jim Strait about
    manpower for AFE RD
  • Need to secure engineering/technical support from
    PPD for this aggressive schedule. We have
    requested
  • Paul Rubinov, lead engineer (Full Time)
  • ½ time programmer, additional full time engineer,
    full time technician for all testing, timely
    testing of TripT(Abder!) when it is delivered.
  • We have requested these people (by name). For the
    RD to lead to a successful project execution, we
    need these people ASAP.
  • We will follow up on the requests with Jim over
    the coming weeks
  • Plan ongoing dialog with DZero operations and PPD

11
Directors Review Installation and Commissioning
  • Recommendations
  • Include in the 04 shutdown the activities of L0
    surveying (unless risks exceed paybacks). Perform
    a risk analysis for the L0 05 installation and
    preliminary engineering assessment by January
    05.
  • The first point (survey activities) has been
    addressed. See talk by Ron Lipton.
  • We will work on the risk analysis once we get the
    survey results
  • Proactively approach the PPD Division Management
    and the Directorate to coordinate usage of
    manpower resources during the 04 and 05
    shutdowns.
  • This dialog is beginning. We have approached PPD
    for 04 shutdown activities. We are revising our
    estimates for the 05 shutdown. Once we have this
    in hand, we will approach PPD about this.
  • Reevaluate the MS Installation Cost estimate
    after the survey performed during shutdown 04.
    (To Directorate) Consider transferring the
    control of MS funds for Installation from
    Operations to MIE Project.
  • We plan to reevalute the MS costs after the
    survey. We are combing through the entire
    installation MS costs to fine tune our
    estimates.
  • The second point is tricky given the lifetime of
    the project. Coupling of installation to
    construction project could be problematic.
  • Initiate communication with CDF and AD for
    shutdown 05 duration.
  • This dialog is beginning. Consciousness has been
    raised at the highest levels.

12
Directors Review Cost Schedule
  • Cost Recommendations
  • Performance management indicators do not
    consistently reflect actual costs for the work
    that has been completed. The area with the
    largest discrepancies is for work being done at
    the universities for which invoices have not been
    received. More effort should be put into getting
    estimated expenditures from the universities so
    the costs can be more accurately estimated and
    accrued, so a more detailed analysis of the cost
    variances can be performed to determine if
    corrective actions are required.
  • We are working on this. We have focused on
    getting all the MOUs/SOWs in place so that
    accruals can be done in a timely manner. We will
    also set up an accounting structure to make sure
    the costs are more accurately measured.
  • Schedule Recommendations
  • Pitch Adapters for Layer 0 Silicon Detector were
    not part of original scope and have been added to
    the work, are in the prototype state and are
    being paid on MRI funds. This scope of work was
    not added via a Change Request and not added to
    the schedule. Currently there are issues in the
    prototype phase. This additional scope could have
    impact on the schedule for Layer 0. The Pitch
    Adapter should be added to the project scope via
    the Change Control process and then added into
    the project schedule.
  • This has been done. See Change Request. Both
    and schedule impact are minimal.
  • Layer 0 has Ready to Move milestone with a
    baseline schedule milestone of 5/25/06 an
    aggressive schedule date of 7/21/05. Layer 0
    Management forecasts an approximate 2 months
    earlier completion date, but they have not
    modifying the aggressive/working schedule. The
    aggressive/working schedule should be modified to
    reflect the current forecast for work completion.
  • This has been done. The 7/21 date includes 6
    weeks of full integration at SiDet.

13
Directors Review Cost Schedule (Continued)
  • Schedule Recommendations (Continued)
  • The four DOE Level 1 Milestones in the PEP have
    the same completion dates for the equivalent
    Level II Directorate's Milestones, which does not
    allow any contingency between the milestones. To
    minimize the risk of the Level 1 milestone dates
    being missed, a heightened level of awareness
    needs to be adopted for these four milestones.
    This can be addressed by emphasizing these
    milestones separately in the Project's Monthly
    Report. Additionally, the Directorate should
    assess whether or not the dates of the equivalent
    Level 2 Directorate Milestones should be modified
    to allow float between the Level 1 and Level 2
    milestones.
  • This has been addressed by adding a section to
    the monthly report, highlighting the four DOE
    Level 1 Milestones. We have not modified the
    dates of the L2 Directors milestones for this.
  • There were several examples of variances between
    the current working schedule and how work will be
    performed. There are concerns from the project
    management that the effort to update the
    schedules and costing tool for the smaller
    changes could be difficult with the present level
    of project office support. The Project Manger
    should address this concern as soon as possible.
  • We are updating some of these areas. We are
    trying to make do with the level of support we
    have.

14
Directors Review - Management
  • Recommendations
  • Resolve the issues about DOE Headquarters/DOE
    Field Office/Directorate milestones.
  • Done. (addressed in previous slides)
  • Include all tasks (ex pitch adapter) in the
    project schedule.
  • Done. (addressed in previous slides)
  • Formalize the L0 Silicon testing plan after May
    05 (end of production) and before the 05
    shutdown.
  • We are working on this.
  • Initiate communications with Division Heads and
    Directorate to obtain manpower resources in an
    appropriate manner.
  • We are beginning to address this. We have
    initiated conversations with (new) PPD head.
  • Insure availability of key personnel at SiDet for
    the L0 Assembly during the 04 shutdown.
  • We have addressed this.
  • Present a plan for the assessment and analysis of
    the risks connected with the L0 Installation.
  • This issue was addressed in previous slides. We
    are working on this and will update it after the
    04 aperture measurements are complete.
Write a Comment
User Comments (0)
About PowerShow.com