Title: Dzero Run IIb PMG
1Dzero Run IIb PMG
- Agenda
- Upgrade/Project Status V. ODell
- outline of Response to Directors review report
- Trigger Status D. Wood
- Silicon Layer 0 Status R. Lipton
2Directors Milestones (31/07/2004)
3Directors Milestones (31/07/2004)
4Cost Performance Report(31/07/2004)
SPI BCWP/BCWS 0.88, CPI BCWP/ACWP
2.43 SPI Trigger 0.74, SPI Silicon 0.92, SPI
Online 1.11
5Management Highlights July/August
- MOUs/SOWs for life of project finished for
- Columbia
- Boston University (with CTT change request)
- University of Arizona (with CTM change request)
- University of Virginia MOU/SOWs in signature
phase - Change requests
- New change request for Silicon Pitch Adaptors, as
recommended by Directors review - Small cost/no schedule impact
- Production Readiness Reviews
- Production readiness review for STT this Friday
(9/10) - Will be organizing PRR for TAB/GAB soon
- Installation/Commissioning
- Many meetings with project personnel to review
and fine tune the installation/commissioning
schedule and plans
6Directors Review L0
- Recommendations
- (About the delayed hybrid delivery) my only
recommendation would be to follow up on the
promised delivery, understand now if vendor is
experiencing any problems, and have a team in
place to wipe, probe, stuff, bond, and thoroughly
test completed hybrids in late August/early
September. The project leaders are all too aware
that hybrid deliveries and hybrid quality issues
are invariably the pacing items on silicon
detector projects. - Done. Hybrids have now arrived and are being
wiped. See talk by Ron Lipton. - (About keeping key personnel on project at SiDet)
My recommendation would be for the project
leaders to meet at SiDet with the PPD management,
perhaps after the change in Division head, and to
provide some introduction to the project and
indicate what resources, including any key
personnel, are needed for the construction
effort. The project should take care to also
include technician effort needed for support
activities, such as modifying fixtures and
building and assembling mock-ups. - We have made specific requests for key personnel
for module production. This went through both D0
department and SiDet and was requested to John
Cooper. With the new management in place, we will
set up such a meeting. - (About H-Disk refurbishment/L0 aperture
measurements) From the presentations and
follow-up discussions it is not clear to me how
confident the project is in the aperture
clearance for Layer 0 even with the proposed
changes to reduce the profile of the detector. My
personal instinct would be to remove and
refurbish the H-disk detectors during the
upcoming shutdown period and to inspect the
aperture, perhaps with a boroscope, during the
H-disk work. I would do this even in the absence
of key personnel from Moscow State University.
This would have the advantage of getting the
H-disk work out of the way and, more importantly,
assuring the project that there are no unknown
restrictions within the 2.4 meter installation
region. There is some risk to rest of the vertex
detector with any of this work, and the D0
collaboration would need to approve the
operation. Also, I would not make this
recommendation if the project leaders felt that
it would sap resources that are needed for the
module construction effort. - We have investigated H-Disk refurbishment/L0
aperture measurements and other 04 shutdown
activities and we will do the survey. The H-Disk
refurbishment was dropped for lack of time during
this shutdown. The inner H-Disks are better than
we thought they were - 90 operational so will
likely not be refurbished during the 05 shutdown
either. See talk by Ron Lipton.
7Directors Review L0
- With the assistance of Marvin Johnson and others
the project has done a good job in reducing
pick-up noise effects of the type that plagued,
and continue to plague, the CDF Layer 00
detector. Still, in order to understand and
mitigate any remaining operational or coherent
noise issues it is important that the completed
detector be operated at SiDet for a period of at
least 6-8 weeks. I would hope that there would be
enough flexibility in the Labs schedule that the
start of the shutdown could even be delayed if
necessary to accommodate this integration study. - Agreed. This was already in the schedule (6
weeks). Any schedule gain that is made allows us
a longer integration study. We will ensure at
least 6 weeks even if the schedule is delayed. - The one week allotted between L0 Silicon
Cable-up Complete and Silicon Ready for
Resumption of Tevatron Operation seems to me to
be a bit on the short side. However, it is
difficult to scale from experiences on much
larger silicon detector installation efforts to a
single layer, 48 module system. I would recommend
that as the time of the L0 installation shut-down
draws near, the Project refines its timeline for
the installation and technical commissioning
based upon a firmer understanding of what the
work will actually entail. The timeline should
ideally be independent of any pre-conception as
to the length of the shutdown. - We are continuously reviewing the installation
schedule. What we learn during 2004 shutdown will
be fed bak into the schedule. We will certainly
revisit the installation timeline as installation
dates get closer. Note that Silicon Ready for
Resumption of Tevatron Operation does not mean
the L0 is ready to take data we plan to leave
the detector open for 6 weeks for debugging. - One last suggestion, and one that is outside the
scope of this review For oversight and
accounting purposes the upgrade project ends with
the completed detector ready for delivery to DAB.
However, I think that the D0 should view
installation, commissioning both technical and
physics, and maintenance as an interconnected
process. In some ways it would be better if the
installation of the Layer 0 detector was viewed
as the beginning of a process. I would further
hope that there be some continuity between the
construction and commissioning efforts and that
the commissioning team is as richly layered as is
the current construction team. Finally, it is
important for the D0 collaboration to give both
support and prominence to the commissioning
effort. These comments are made in light of a
previous experience where the process did not go
as smoothly as one would have wanted. - We agree with this and this is part of our
motivation for impaneling the SC-IPC committee
which is very actively reviewing the installation
to physics commissioning schedule and effort
using the experience of the full collaboration
and with full support and participation of the
construction and operations groups.
8Directors Review - Trigger
- Recommendations
- Secure the manpower for all installation needed
in the 2004 shutdown to allow testing during the
data taking of FY05. - Agreed. This has been addressed see talk by
Darien. - Establish a forum (presumably through the
Director for Research) for ongoing dialog with
CDF and the Accelerator Division on the timing of
the FY05 shutdown (maybe this exists already). - Agreed. The director is aware of this.
- It would be helpful to have a presentation on the
trigger simulation and validation efforts some
time in early 2005. - OK. Trigger simulation workshops are ongoing. We
would be prepared to give such a presentation on
this timescale. - It would be useful to have a presentation of the
SC-IPC task list around the same time. - OK. SC-IPC gives regular updates to the
collaboration.
9Directors Review - AFEII
- Recommendations
- The committee feels that the collaboration should
carefully consider their strategy, including when
to make the decision whether or not to proceed
with an AFE replacement. - We have done this. By combing through the
schedule and performing some tasks in parallel we
have gained 1 month. Our current schedule is - D0 internal review 12/04 (was 1/05)
- Laboratory review 1/05 (was 2/05)
- (final project approval)
- Production begins 2/05 (was 3/05)
- This means installation would begin 1/06
(according to current schedule).
10Directors Review - AFEII
- Where we are
- AFE II schedule has been revisited with an aim to
speeding things along - Parallel layout of AFEII-t (instead of the
original serial layout). - We would like Wessons group (PPD) to work on
this. - This request has been transmitted to Jim Strait.
- Current status
- AFE II board close to being submitted (end of
this week) - Expect an 3 week turnaround between submission
and stuffed prototype board ready for testing - This implies prototype board will be ready for
testing by October - Plan is for John Anderson to test the board
- Mosis submission of TripT is in.
- Prototype TripT chips due back 3rd week of
October - We have had discussions with Jim Strait about
manpower for AFE RD - Need to secure engineering/technical support from
PPD for this aggressive schedule. We have
requested - Paul Rubinov, lead engineer (Full Time)
- ½ time programmer, additional full time engineer,
full time technician for all testing, timely
testing of TripT(Abder!) when it is delivered. - We have requested these people (by name). For the
RD to lead to a successful project execution, we
need these people ASAP. - We will follow up on the requests with Jim over
the coming weeks - Plan ongoing dialog with DZero operations and PPD
11Directors Review Installation and Commissioning
- Recommendations
- Include in the 04 shutdown the activities of L0
surveying (unless risks exceed paybacks). Perform
a risk analysis for the L0 05 installation and
preliminary engineering assessment by January
05. - The first point (survey activities) has been
addressed. See talk by Ron Lipton. - We will work on the risk analysis once we get the
survey results - Proactively approach the PPD Division Management
and the Directorate to coordinate usage of
manpower resources during the 04 and 05
shutdowns. - This dialog is beginning. We have approached PPD
for 04 shutdown activities. We are revising our
estimates for the 05 shutdown. Once we have this
in hand, we will approach PPD about this. - Reevaluate the MS Installation Cost estimate
after the survey performed during shutdown 04.
(To Directorate) Consider transferring the
control of MS funds for Installation from
Operations to MIE Project. - We plan to reevalute the MS costs after the
survey. We are combing through the entire
installation MS costs to fine tune our
estimates. - The second point is tricky given the lifetime of
the project. Coupling of installation to
construction project could be problematic. - Initiate communication with CDF and AD for
shutdown 05 duration. - This dialog is beginning. Consciousness has been
raised at the highest levels.
12Directors Review Cost Schedule
- Cost Recommendations
- Performance management indicators do not
consistently reflect actual costs for the work
that has been completed. The area with the
largest discrepancies is for work being done at
the universities for which invoices have not been
received. More effort should be put into getting
estimated expenditures from the universities so
the costs can be more accurately estimated and
accrued, so a more detailed analysis of the cost
variances can be performed to determine if
corrective actions are required. - We are working on this. We have focused on
getting all the MOUs/SOWs in place so that
accruals can be done in a timely manner. We will
also set up an accounting structure to make sure
the costs are more accurately measured. - Schedule Recommendations
- Pitch Adapters for Layer 0 Silicon Detector were
not part of original scope and have been added to
the work, are in the prototype state and are
being paid on MRI funds. This scope of work was
not added via a Change Request and not added to
the schedule. Currently there are issues in the
prototype phase. This additional scope could have
impact on the schedule for Layer 0. The Pitch
Adapter should be added to the project scope via
the Change Control process and then added into
the project schedule. - This has been done. See Change Request. Both
and schedule impact are minimal. - Layer 0 has Ready to Move milestone with a
baseline schedule milestone of 5/25/06 an
aggressive schedule date of 7/21/05. Layer 0
Management forecasts an approximate 2 months
earlier completion date, but they have not
modifying the aggressive/working schedule. The
aggressive/working schedule should be modified to
reflect the current forecast for work completion. - This has been done. The 7/21 date includes 6
weeks of full integration at SiDet.
13Directors Review Cost Schedule (Continued)
- Schedule Recommendations (Continued)
- The four DOE Level 1 Milestones in the PEP have
the same completion dates for the equivalent
Level II Directorate's Milestones, which does not
allow any contingency between the milestones. To
minimize the risk of the Level 1 milestone dates
being missed, a heightened level of awareness
needs to be adopted for these four milestones.
This can be addressed by emphasizing these
milestones separately in the Project's Monthly
Report. Additionally, the Directorate should
assess whether or not the dates of the equivalent
Level 2 Directorate Milestones should be modified
to allow float between the Level 1 and Level 2
milestones. - This has been addressed by adding a section to
the monthly report, highlighting the four DOE
Level 1 Milestones. We have not modified the
dates of the L2 Directors milestones for this. - There were several examples of variances between
the current working schedule and how work will be
performed. There are concerns from the project
management that the effort to update the
schedules and costing tool for the smaller
changes could be difficult with the present level
of project office support. The Project Manger
should address this concern as soon as possible. - We are updating some of these areas. We are
trying to make do with the level of support we
have.
14Directors Review - Management
- Recommendations
- Resolve the issues about DOE Headquarters/DOE
Field Office/Directorate milestones. - Done. (addressed in previous slides)
- Include all tasks (ex pitch adapter) in the
project schedule. - Done. (addressed in previous slides)
- Formalize the L0 Silicon testing plan after May
05 (end of production) and before the 05
shutdown. - We are working on this.
- Initiate communications with Division Heads and
Directorate to obtain manpower resources in an
appropriate manner. - We are beginning to address this. We have
initiated conversations with (new) PPD head. - Insure availability of key personnel at SiDet for
the L0 Assembly during the 04 shutdown. - We have addressed this.
- Present a plan for the assessment and analysis of
the risks connected with the L0 Installation. - This issue was addressed in previous slides. We
are working on this and will update it after the
04 aperture measurements are complete.