Title: NWSBU Strategic Capabilities Process
1NWSBU Strategic Capabilities Process
2NWSBU Has Identified 22 Strategic Capabilities
- Capabilities linked to Sandia Organizations
- Capabilities identified as critical to near and
long term needs of NWSBU - Annual Strategic Capabilities Process established
to assure health of capabilities - Evaluate current State of Health
- Establish evolution/direction
- Address needs
- Establish priorities
- Deploy budgets
3Strategic Capability Process Leverages
Information Gathered Through Capability Studies
- DelCap Examined capabilities needed to meet
Defense Program Deliverables (LEPs) - SAND 2002-2429
- JelCap Examined health of NWSBU capabilities
- SAND 2001-2508
- People
- Capital Equipment
- Facilities
- StratCap Adds in information regarding work
content - Coordinated by Rick Fellerhoff
- Strategic Capability Process Leverages above to
address people, facilities, CE and work content
required to meet near and long term needs of
NWSBU - Yearly process that impacts budget for each
capability - Initiated in FY03
4Objectives of Strategic Capabilities Process
- Increased communication and leverage between
Critical Capabilities - Provide direction and focus for capabilities
- Systematic, greater attention to health of
strategic capabilities - Uniform basis for assessment and discussion
- Annual process for prioritization of support
- Provision of guidance to LDRD, Capital Equipment,
Construction processes, SEPR ? - Outcomes
- Much less effort defining work scope and funding
for strategic capabilities - Greater certainty for line organizations
- Fewer strategic capabilities at risk
5Strategic Capabilities State of Health
Assessment
- Focused on following elements
- Facilities
- Capital Equipment
- Staffing
- Work Content
- Annotated Powerpoint file addressing following
- Executive Summary (short)
- Current State Assessment
- Desired Evolution of the Capability
- Gap Analysis and Critical Issues
6Process Timelines for FY04 Program
- 9/23-25/2002 Strategic capabilities kaizen
- 10/15/2002 Structure/template of capability
document completed by Capability Working Group - 10/27/2002 Capability Document structure
validated by DDLT - 11/14/2002 Capability process rolled out to
Capability Owners - 1/6/2003 Annotated Capability Presentations
distributed to DDLT - 1/17/2003 Capability Presentations Completed
- 1/24/2003 Validation of Capability Needs
completed by DDLT - 2/27/2003 PDLT completes integrated priorities
for all capabilities - 3/31/2003 Provide guidance to facilities, CE,
LDRD, Staffing - 3/31/2003 PDLT deploys FY04 Budget
7Current Status Presentations Completed by
January 16, 2003
- Excellent participation by Capability Owners,
Surrogates and DDLT - Increased communication between capabilities
already occurring - Validating strategic capabilities and their
gaps/needs/concerns
8SEPR Supporting Many of NWSBU Critical
Capabilities
- Priorities ?
- Short and long term balance ?
9Long Term Capability Needs
- Grant Heffelfinger Overview 5 focus areas
addressing the long-term NWSBU Needs - In-depth Presentations addressing benefits that
SEPR provides to NWSBU capabilities - Justine Johannes Process Science.
- Eliot Fang Micro and Nano Sciences.
10Questions and Recommendations
- Are we addressing the critical science-based
simulation capabilities required by the NWSBU? - Short and long term ?
- Is there a process in place to integrate, on a
yearly basis, the evolving NWSBU capability
requirements? - Leverage the NWSBU Strategic Capabilities Review
Process - Will provide information/guidance in 1st quarter
of CY03
11Backup process slides
12System Studies
Duane Dimos David Myers Carol Adkins
Art Ratzel Wil Gauster
NWSBU and Capability Needs
Current State
Fearless Forecast expanded to clarify impact on
capabilities
- SOH Document
- Current State
- Capability Evolution
- Gap Analysis and Issues
Desired State
Complete by 1/17/2003
Gaps and near term activities
Validation
Complete by 1/24/2003
13StratCap Planning To-Be Process (2)
PD Closure and Concurrence
Complete by 2/27/2003
Merge Capability Inputs
14StratCap Planning To-Be Process (3)
Guidance
Complete by 3/31/2003
Deploy Budgets