Title: Effective Updating for Construction Schedules
1Effective Updating for Construction Schedules
- Saleh Mubarak, PhD
- PMI-Tampa Bay Chapter
- 7 October 2006
2Seminar Outline
- Why update projects
- Definitions
- Info needed for project updating
- The interval between updates
- Steps for updating schedules
- Hints for Creating and Storing Updates
- Myths about updating
- Example for updating a schedule
- Example discussion
- Updating pitfalls
- Project control
- Baselines
- Percent complete
- Methods for measuring work progress
3Why Update Schedules?
- Schedules (like cost estimates) are always
prepared before construction begins. However,
updates must take place routinely for the
following two reasons - Unintentional Things never happen as planned,
and - Intentional Changes will likely happen during
construction. - Schedules without updating, monitoring,
controlling, and corrective action are useless.
4Updating Schedules Definitions
- An updated schedule is A revised schedule
reflecting project information at a given data
date regarding completed activities, in-progress
activities, and changes in the logic, cost, and
resources required and allocated at any activity
level. - Data Date The date as of which all progress on a
project is reported. - It is also called as-of-date or status date.
- It is NOT current date or time now.
- The bank statement example.
5Updating Schedules Info Needed
- When updating, the following information must be
reported. This include two main categories - Past What has happened since last update such
as - Activities that have started, their actual start
date, percent complete and/or remaining duration. - Activities that are completed and their actual
completion date. - Actual budget spending or resource consumption
for each activity.
6Updating Schedules Info Needed-2
- Future Any changes to the schedule or to
schedule-related items such as - Activities that have been added, along with their
information (duration, logic, budget, resources,
constraints, etc.) - Any activities that have been deleted (scheduler
has to be careful in maintaining logic after the
deletion). - Activities that have changed in duration, logic,
budget, resources, constraints, codes, or any
other change.
7Updating Schedules Info Needed-3
- Future (continued)
- Any change to the imposed finish date for the
entire schedule or the constraint date for
certain milestones. - Any schedule-related, but not activity-specific
change such as - cost and availability of resources,
- change in calendar work days,
- change in responsibility (e.g. a subcontractor
took over a portion of the general contractors
work or a subcontractors replacement.)
8Future changes
- Future changes are either
- Pure progress A changes that happens as a result
of logic tie between the future activity and an
earlier delayed activity (i.e. one delay triggers
another delay.) - Example Framing activity got delayed so Dry
wall, Taping, and Painting were delayed as a
result.
9Future changes - 2
- Or revisions intended changes.
- Painting was delayed for a reason that has
nothing to do with the logical tie with its
predecessor.
10Updating Schedule The Interval
- Current Data Date
- Anything left to this line is past.
- Anything right to this line is future
Previous Data Date
11Updating Schedules The Interval
- A suitable time interval has to be chosen for
schedule updates. It can be weekly, bi-weekly,
monthly, or other. - Sometimes, this interval is shortened towards the
end of the project. - In some industries, the project has to be updated
daily. - Balancing between
- A long interval Things may be forgotten by the
time the update is due. Also, it may be too late
to take a corrective action. - A short interval Too much paperwork and wasted
time a possible distraction.
12Updating Notes
- Most software programs provide a space for log or
notes, at the project and/or activity level. - Project managers and field crews must provide
notes along with updates, particularly when
things dont go as planned or simply need
explanation or justification. - Why?
- Documentation and accessibility.
- Internal vs. external reporting
- Show / mask notes.
- Electronic recovery
- Florida Sunshine Law
13Steps for Updating a Schedule
- The Scheduler produces a list of incomplete
activities and submit it (on paper or electronic)
to the project manager. - For an attempt to shorten the list and allow the
focus on a certain group of activities, you can - Filter out completed activities
- Filter out far-future activities
- Possibility that PM/superintendent wants to
change past events or make changes to far-future
activities. - See sample.
14Example 1 No Cost
15Example 2 With Cost
16Steps for Updating a Schedule-2
- The PM (or superintendent) fills up the form in
red ink, signs and dates it and submit it to the
scheduler. - It is a good idea for the PM to keep a copy for
himself. - Electronic (Excel) sheet?
- The scheduler enters the info in the computer and
updates the project (see hints), signs and dates
the forms preferably using green or blue ink. - Should the PM do his own update?
17Steps for Updating a Schedule-3
- The scheduler prints a preliminary report and
discusses it with the PM. - It is a good idea to produce a summary report
(what happened between last update and this
update). - Based on this discussion, the scheduler makes any
necessary adjustments to the schedule or reports.
- Any changes to the schedule requested by the PM
have to be documented by the scheduler.
18Steps for Updating a Schedule - 4
- The scheduler produces new reports
- Different reports for different parties
- Reports have to be identified (title, date, etc.)
- If the scheduler receives info on changes in
between two updates, he (along with the PM) has
to make a decision - To wait till the next update, or
- Make a special update.
19Multi-projects The Checklist Report
20The Schedule Update Form
21The Cost Update Form
22Hints for Creating and Storing Updates
- Always make a copy of the schedule before you
make any changes. - Establish a policy (for the company) for naming
the updates and storage location. Be consistent
with this policy. - P3e/P3ec Baselines.
- If you are making schedule for a what if
scenario, make sure you label it differently and
rename (or move / delete) it after a decision has
been made to accept the changes. - For completed projects, archive them in a secure
and retrievable manner.
23Myths/Misconceptions About Schedule Updating
- We always produce a complete schedule before the
commencement of construction. We just dont
update it, We trust our field staff and
subcontractors to follow it. - We update projects only when there is a need
for the update. - Everything is going well. There is no need for an
update.
24Updating Schedule An Example
25Updating Example10 Days Later
- Ten days after the project has started, you
received the following report - Activities A and D are complete. Actual dates
- A (0, 2), D (5, 9),
- Activity B started on day 5. Remaining duration
2. - Activity C started on day 2. Some problems
encountered. Remaining duration 4. - Activity Fs duration was adjusted to 8 days.
- Activity J was canceled.
- New activity P, duration 4. IPA E and F. ISA
K.
26Updating the Network
27The Updated Network
10, 12
12, 18
22, 26
26, 31
B 2
E 6
P 4
K 5
29, 34
25, 29
19, 25
17, 19
14, 22
10
10, 14
34, 37
F 8
PC
N 3
C 4
22, 34
14, 22
I 12
34, 37
10, 14
10
22, 26
14, 22
22, 34
M 4
G 8
22, 28
10, 19
30, 34
14, 22
L 6
H 9
28, 34
19, 28
28Example Quiz
- The projects calculated finish date has been
delayed by two days for the following reason - The addition of new activity P.
- The change of the duration of activity F from 5
to 8 days. - Activity C took two more days than planned.
- Combination of the above.
- Blame it on someone else.
29Updating Schedules Example Discussion
- Project finish date may change
- Good news or bad news?
- Justification Data versus information
- Critical path may change
- Another path got extended
- An existing activity took more days than planned.
- A new activity was added.
- The critical path was shortened
- An existing activity took less days than planned.
- A new activity was deleted.
- A combination of the above.
30Example Discussion - 2
- Any changes in imposed finish date?
- Change orders.
- Approved additional rain days / unused rain days.
- Unforeseen site conditions.
- Other.
- Note that adding or deleting activities has an
impact on the predecessors and/or successors. - Dissolve versus delete.
- Redundancies.
- Possible change in the critical path and float
amount to other activities.
31Delete vs. Dissolve Activities Deleting Activity
B
A
B
C
C
A
32Delete vs. Dissolve Activities Dissolving
Activity B
- The dissolve works only with FS type relationship
and does not transfer lags.
C
A
33Updating SchedulesExample Discussion - 3
- Check constraints
- Late Finish lt Early Finish!
- People in charge of future activities have to be
informed about the impact of the changes on their
activities. - Comparison may be made to 2 baselines
- The original baseline, and
- The previous update.
- For example, if the current update shows a
negative float of 30 days, it is initially
considered bad news. However, when it is compared
to the previous update that had a negative float
of 42 days, it shows that the contractor is on
the right track. - Claim digger.
34Progress Override or Retained Logic?
35Start Date Delayed Keep Durations or End Dates?
- Construction start is delayed by 2 months
- Keep end date (then duration will shrink to fit),
or - Keep duration 6 months (then construction
completion will be delayed too).
NTP
Construction
9/1/04
3/1/05
5/1/05
11/1/04
36Quiz 6
- True or False
- Updating is needed for projects that have
duration of at least one year or a minimum budget
of 1 million. - Data date is the date all information was entered
in the computer. - In updating schedules, we must not only enter
work progress but we must also enter any changes
to future work. - Switching your computer default rule from
Retained Logic to Progress Override will
most likely- result in an earlier completion
date. - Pay requests and schedule updating are totally
independent processes. - Negative float is an indication that the schedule
is not meeting its expected completion date or an
interim imposed date.
37Project Control
- Project control is the continuous practice of
- monitoring work progress,
- comparing it to baseline budget and schedule,
- finding any deviations and their causes, and
- taking a corrective action wherever and whenever
necessary. - The ability to determine a project status as it
relates to the time and schedule selected.
(Popescu) - Also called project tracking.
- Project control is done by the contractor. The
owner may do project monitoring (steps 1 and 2,
and possibly 3, above).
38Why Project Control?
- Project control is needed because projects never
run exactly as planned. - Project control is a cyclical iterative task do
small part of the work and compare to baseline,
do corrective measure, adjust plan (if needed),
do another part of the work, and so on. - Project control requires measuring work progress
and calculating the projects percent complete.
39Baseline Schedule
- Baseline The original approved plan for a
project including approved changes. It usually
includes Baseline Budget and Baseline Schedule.
It is used as a benchmark for comparison with
actual performance. - Baseline Budget The projects original approved
budget including any approved changes. - Baseline Schedule A schedule prepared by the
contractor before the start of the project and
usually approved by the owner- typically used for
performance comparison. - Also called Target Schedule.
40Definition of Percent Complete
- Percent Complete (PC or PCT)
- An estimate, expressed as a percent, of the
amount of work which has been completed on an
activity or group of activities (or work
breakdown structure component). (PMBOK 2000) - A ratio comparison of the completion status to
the current projection of total work. (PMBOK
1987) - One measure of completion used to determine the
remaining duration of a partially completed
activity. (Welcom PM Glossary, Project Management
Solutions, Internet 1998) - Percent complete can be for an activity, work
package (or assembly), or the entire project.
41Methods to Measure Work Progress
- Units completed
- Start/finish
- Supervisor Opinion
- Cost/Budget or Manhours Ratio
- Actual
- Baseline
- Duration Ratio
- Actual
- Baseline
- Incremental milestones
- Weighted or Equivalent Units
- The Work-Day Unit Method
42So, Which One Should I Use?
- None of the previously discussed methods is
wrong. None of them can be considered the right
method. - Most importantly
- The project management team has to know exactly
what each percent complete means. - The project manager has to pick one or two
parameters to use. - The project manager has to be consistent with the
chosen parameters throughout the project.
43Conclusion
- Comments
- Keep in touch
- salehmubarak_at_hotmail.com
- (813) 417-5654