Effective Updating for Construction Schedules - PowerPoint PPT Presentation

1 / 43
About This Presentation
Title:

Effective Updating for Construction Schedules

Description:

Effective Updating for Construction Schedules. Saleh Mubarak, PhD. PMI-Tampa Bay Chapter ... Bridge No. 10345, US 41 over Hillsborough River. LMN4500 ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 44
Provided by: salehm
Category:

less

Transcript and Presenter's Notes

Title: Effective Updating for Construction Schedules


1
Effective Updating for Construction Schedules
  • Saleh Mubarak, PhD
  • PMI-Tampa Bay Chapter
  • 7 October 2006

2
Seminar Outline
  • Why update projects
  • Definitions
  • Info needed for project updating
  • The interval between updates
  • Steps for updating schedules
  • Hints for Creating and Storing Updates
  • Myths about updating
  • Example for updating a schedule
  • Example discussion
  • Updating pitfalls
  • Project control
  • Baselines
  • Percent complete
  • Methods for measuring work progress

3
Why Update Schedules?
  • Schedules (like cost estimates) are always
    prepared before construction begins. However,
    updates must take place routinely for the
    following two reasons
  • Unintentional Things never happen as planned,
    and
  • Intentional Changes will likely happen during
    construction.
  • Schedules without updating, monitoring,
    controlling, and corrective action are useless.

4
Updating Schedules Definitions
  • An updated schedule is A revised schedule
    reflecting project information at a given data
    date regarding completed activities, in-progress
    activities, and changes in the logic, cost, and
    resources required and allocated at any activity
    level.
  • Data Date The date as of which all progress on a
    project is reported.
  • It is also called as-of-date or status date.
  • It is NOT current date or time now.
  • The bank statement example.

5
Updating Schedules Info Needed
  • When updating, the following information must be
    reported. This include two main categories
  • Past What has happened since last update such
    as
  • Activities that have started, their actual start
    date, percent complete and/or remaining duration.
  • Activities that are completed and their actual
    completion date.
  • Actual budget spending or resource consumption
    for each activity.

6
Updating Schedules Info Needed-2
  • Future Any changes to the schedule or to
    schedule-related items such as
  • Activities that have been added, along with their
    information (duration, logic, budget, resources,
    constraints, etc.)
  • Any activities that have been deleted (scheduler
    has to be careful in maintaining logic after the
    deletion).
  • Activities that have changed in duration, logic,
    budget, resources, constraints, codes, or any
    other change.

7
Updating Schedules Info Needed-3
  • Future (continued)
  • Any change to the imposed finish date for the
    entire schedule or the constraint date for
    certain milestones.
  • Any schedule-related, but not activity-specific
    change such as
  • cost and availability of resources,
  • change in calendar work days,
  • change in responsibility (e.g. a subcontractor
    took over a portion of the general contractors
    work or a subcontractors replacement.)

8
Future changes
  • Future changes are either
  • Pure progress A changes that happens as a result
    of logic tie between the future activity and an
    earlier delayed activity (i.e. one delay triggers
    another delay.)
  • Example Framing activity got delayed so Dry
    wall, Taping, and Painting were delayed as a
    result.

9
Future changes - 2
  • Or revisions intended changes.
  • Painting was delayed for a reason that has
    nothing to do with the logical tie with its
    predecessor.

10
Updating Schedule The Interval
  • Current Data Date
  • Anything left to this line is past.
  • Anything right to this line is future

Previous Data Date
11
Updating Schedules The Interval
  • A suitable time interval has to be chosen for
    schedule updates. It can be weekly, bi-weekly,
    monthly, or other.
  • Sometimes, this interval is shortened towards the
    end of the project.
  • In some industries, the project has to be updated
    daily.
  • Balancing between
  • A long interval Things may be forgotten by the
    time the update is due. Also, it may be too late
    to take a corrective action.
  • A short interval Too much paperwork and wasted
    time a possible distraction.

12
Updating Notes
  • Most software programs provide a space for log or
    notes, at the project and/or activity level.
  • Project managers and field crews must provide
    notes along with updates, particularly when
    things dont go as planned or simply need
    explanation or justification.
  • Why?
  • Documentation and accessibility.
  • Internal vs. external reporting
  • Show / mask notes.
  • Electronic recovery
  • Florida Sunshine Law

13
Steps for Updating a Schedule
  • The Scheduler produces a list of incomplete
    activities and submit it (on paper or electronic)
    to the project manager.
  • For an attempt to shorten the list and allow the
    focus on a certain group of activities, you can
  • Filter out completed activities
  • Filter out far-future activities
  • Possibility that PM/superintendent wants to
    change past events or make changes to far-future
    activities.
  • See sample.

14
Example 1 No Cost
15
Example 2 With Cost
16
Steps for Updating a Schedule-2
  • The PM (or superintendent) fills up the form in
    red ink, signs and dates it and submit it to the
    scheduler.
  • It is a good idea for the PM to keep a copy for
    himself.
  • Electronic (Excel) sheet?
  • The scheduler enters the info in the computer and
    updates the project (see hints), signs and dates
    the forms preferably using green or blue ink.
  • Should the PM do his own update?

17
Steps for Updating a Schedule-3
  • The scheduler prints a preliminary report and
    discusses it with the PM.
  • It is a good idea to produce a summary report
    (what happened between last update and this
    update).
  • Based on this discussion, the scheduler makes any
    necessary adjustments to the schedule or reports.
  • Any changes to the schedule requested by the PM
    have to be documented by the scheduler.

18
Steps for Updating a Schedule - 4
  • The scheduler produces new reports
  • Different reports for different parties
  • Reports have to be identified (title, date, etc.)
  • If the scheduler receives info on changes in
    between two updates, he (along with the PM) has
    to make a decision
  • To wait till the next update, or
  • Make a special update.

19
Multi-projects The Checklist Report
20
The Schedule Update Form
21
The Cost Update Form
22
Hints for Creating and Storing Updates
  • Always make a copy of the schedule before you
    make any changes.
  • Establish a policy (for the company) for naming
    the updates and storage location. Be consistent
    with this policy.
  • P3e/P3ec Baselines.
  • If you are making schedule for a what if
    scenario, make sure you label it differently and
    rename (or move / delete) it after a decision has
    been made to accept the changes.
  • For completed projects, archive them in a secure
    and retrievable manner.

23
Myths/Misconceptions About Schedule Updating
  • We always produce a complete schedule before the
    commencement of construction. We just dont
    update it, We trust our field staff and
    subcontractors to follow it.
  • We update projects only when there is a need
    for the update.
  • Everything is going well. There is no need for an
    update.

24
Updating Schedule An Example
25
Updating Example10 Days Later
  • Ten days after the project has started, you
    received the following report
  • Activities A and D are complete. Actual dates
  • A (0, 2), D (5, 9),
  • Activity B started on day 5. Remaining duration
    2.
  • Activity C started on day 2. Some problems
    encountered. Remaining duration 4.
  • Activity Fs duration was adjusted to 8 days.
  • Activity J was canceled.
  • New activity P, duration 4. IPA E and F. ISA
    K.

26
Updating the Network
27
The Updated Network
10, 12
12, 18
22, 26
26, 31
B 2
E 6
P 4
K 5
29, 34
25, 29
19, 25
17, 19
14, 22
10
10, 14
34, 37
F 8
PC
N 3
C 4
22, 34
14, 22
I 12
34, 37
10, 14
10
22, 26
14, 22
22, 34
M 4
G 8
22, 28
10, 19
30, 34
14, 22
L 6
H 9
28, 34
19, 28
28
Example Quiz
  • The projects calculated finish date has been
    delayed by two days for the following reason
  • The addition of new activity P.
  • The change of the duration of activity F from 5
    to 8 days.
  • Activity C took two more days than planned.
  • Combination of the above.
  • Blame it on someone else.

29
Updating Schedules Example Discussion
  • Project finish date may change
  • Good news or bad news?
  • Justification Data versus information
  • Critical path may change
  • Another path got extended
  • An existing activity took more days than planned.
  • A new activity was added.
  • The critical path was shortened
  • An existing activity took less days than planned.
  • A new activity was deleted.
  • A combination of the above.

30
Example Discussion - 2
  • Any changes in imposed finish date?
  • Change orders.
  • Approved additional rain days / unused rain days.
  • Unforeseen site conditions.
  • Other.
  • Note that adding or deleting activities has an
    impact on the predecessors and/or successors.
  • Dissolve versus delete.
  • Redundancies.
  • Possible change in the critical path and float
    amount to other activities.

31
Delete vs. Dissolve Activities Deleting Activity
B
A
B
C
C
A
32
Delete vs. Dissolve Activities Dissolving
Activity B
  • The dissolve works only with FS type relationship
    and does not transfer lags.

C
A
33
Updating SchedulesExample Discussion - 3
  • Check constraints
  • Late Finish lt Early Finish!
  • People in charge of future activities have to be
    informed about the impact of the changes on their
    activities.
  • Comparison may be made to 2 baselines
  • The original baseline, and
  • The previous update.
  • For example, if the current update shows a
    negative float of 30 days, it is initially
    considered bad news. However, when it is compared
    to the previous update that had a negative float
    of 42 days, it shows that the contractor is on
    the right track.
  • Claim digger.

34
Progress Override or Retained Logic?
35
Start Date Delayed Keep Durations or End Dates?
  • Construction start is delayed by 2 months
  • Keep end date (then duration will shrink to fit),
    or
  • Keep duration 6 months (then construction
    completion will be delayed too).

NTP
Construction
9/1/04
3/1/05
5/1/05
11/1/04
36
Quiz 6
  • True or False
  • Updating is needed for projects that have
    duration of at least one year or a minimum budget
    of 1 million.
  • Data date is the date all information was entered
    in the computer.
  • In updating schedules, we must not only enter
    work progress but we must also enter any changes
    to future work.
  • Switching your computer default rule from
    Retained Logic to Progress Override will
    most likely- result in an earlier completion
    date.
  • Pay requests and schedule updating are totally
    independent processes.
  • Negative float is an indication that the schedule
    is not meeting its expected completion date or an
    interim imposed date.

37
Project Control
  • Project control is the continuous practice of
  • monitoring work progress,
  • comparing it to baseline budget and schedule,
  • finding any deviations and their causes, and
  • taking a corrective action wherever and whenever
    necessary.
  • The ability to determine a project status as it
    relates to the time and schedule selected.
    (Popescu)
  • Also called project tracking.
  • Project control is done by the contractor. The
    owner may do project monitoring (steps 1 and 2,
    and possibly 3, above).

38
Why Project Control?
  • Project control is needed because projects never
    run exactly as planned.
  • Project control is a cyclical iterative task do
    small part of the work and compare to baseline,
    do corrective measure, adjust plan (if needed),
    do another part of the work, and so on.
  • Project control requires measuring work progress
    and calculating the projects percent complete.

39
Baseline Schedule
  • Baseline The original approved plan for a
    project including approved changes. It usually
    includes Baseline Budget and Baseline Schedule.
    It is used as a benchmark for comparison with
    actual performance.
  • Baseline Budget The projects original approved
    budget including any approved changes.
  • Baseline Schedule A schedule prepared by the
    contractor before the start of the project and
    usually approved by the owner- typically used for
    performance comparison.
  • Also called Target Schedule.

40
Definition of Percent Complete
  • Percent Complete (PC or PCT)
  • An estimate, expressed as a percent, of the
    amount of work which has been completed on an
    activity or group of activities (or work
    breakdown structure component). (PMBOK 2000)
  • A ratio comparison of the completion status to
    the current projection of total work. (PMBOK
    1987)
  • One measure of completion used to determine the
    remaining duration of a partially completed
    activity. (Welcom PM Glossary, Project Management
    Solutions, Internet 1998)
  • Percent complete can be for an activity, work
    package (or assembly), or the entire project.

41
Methods to Measure Work Progress
  • Units completed
  • Start/finish
  • Supervisor Opinion
  • Cost/Budget or Manhours Ratio
  • Actual
  • Baseline
  • Duration Ratio
  • Actual
  • Baseline
  • Incremental milestones
  • Weighted or Equivalent Units
  • The Work-Day Unit Method

42
So, Which One Should I Use?
  • None of the previously discussed methods is
    wrong. None of them can be considered the right
    method.
  • Most importantly
  • The project management team has to know exactly
    what each percent complete means.
  • The project manager has to pick one or two
    parameters to use.
  • The project manager has to be consistent with the
    chosen parameters throughout the project.

43
Conclusion
  • Comments
  • Keep in touch
  • salehmubarak_at_hotmail.com
  • (813) 417-5654
Write a Comment
User Comments (0)
About PowerShow.com