Title: Roads
1Roads Transportation Programme 2006
- General
- Sources Of Funding
- Programmed Schedule of Works
2Roads Transportation Programme 2006
General
- Total Road Network 238Km (149
Miles) - National Primary Secondary 19 Km
- Major Urban ( Regional Routes) 36 Km
- Minor Urban Roads 183Km
3Roads TransportationProgramme 2006
Sources of Funding
- National Roads Authority
- Dept. of Environment , Heritage Local Govt.
- Dept. of Transport
- Revenue (City Council) Funding
4National Routes
- National Primary Routes
- N 6 Dublin
Road - N 17 Tuam
Road - National Secondary Routes
- N59 Moycullen
Road - N 84 Headford
Road
5National Routes Contd
- Maintenance Allocations
- National Primary Secondary 505,000
- Includes contributions for Public Lighting,
Bridge Maintenance and Winter Maintenance.
6National Routes Contd
- National Primary Pavement and Minor Improvements
- N 6 Facilities for pedestrians at selected
Roundabouts 200,000 - (Kirwin Morris Roundabouts initially)
- Works programmed March Sept 06
- N 84 Pavement overlay scheme 300,000
- Continuation of 2004/05 schemes
- Works Programmed May-June 06
7National Routes Contd
- National Secondary Pavement and Minor
Improvements - N84 Headford Road
- Traffic Calming Scheme 300,000
- Works programmed April / May 2006
- N 59 Thomas Hynes Road,
Pedestrian Crossing At Schools
30,000 - Works in progress March 06
8National Routes Contd
- Total National Roads Authority Improvements
Allocation for 2006 830,000 -
- All works on National Roads , Maintenance and
Improvements are 100 funded by the N.R.A.
9Non - National Roads
- Funding Sources D.O.E.H.L.G.
- Dept of Transport
City Council- Revenue - Categories of Work Maintenance
- Improvements
10Non - National Roads Contd
- D.O.E.H.L.G. Funding
- Block Grant 529,000
- Special Block Grant 669,000
- Low Cost Safety Improvements 30,000
- Strategic Non National Road Grant Grant 500,000
- Regional Traffic Mgt. Grant 450,000
- Training Grant (Outdoor Staff ) 25,000
- Total Allocation 2,203,000
11Non - National Roads Contd
D.O.E.H.L.G. Funding
- Block Grant funding of 529,000 allocated to
- (1) Major Minor Urban Road Mtce.
414,000 - (2) Ballymoneen Rd. /Barna Rd. Junction
75,000 - (3) Traffic Mgt. Mtce.(Traffic lights, Lighted
Bollards) 40,000
12Non - National Roads Contd
D.O.E.H.L.G. Funding
- Special Block Grant funding of 669,000
allocated between - (1)Newcastle Road/St Marys Road Surfacing
200,000 Between UCHG and Nile Lodge
Junction Works
Scheduled April-May 2006 - (2) Monivea Rd. Surfacing
200,000 - Monivea Road from Ballybane Rd to Joyces
Rd. - Works Scheduled May - June 2006
- (3) Headford Rd. Surfacing 100,000
- Along by Galway Shopping Centre Works
Scheduled April -May 2006 - (4) Bohermore Rd. Surfacing
169,000 - Between Br. Ui Eithir and Cemetry Cross
R/a Works Scheduled April -May 2006
13Non - National Roads Contd
D.O.E.H.L.G. Funding
- Training Grant 25,000
- The Non - National Roads Allocations includes a
dedicated sum each year for training for
Outdoor Staff engaged in Road Works. - Training is provided in the Regional Training
Centre in Castlebar - Such Training is provided on an on - going Basis
throughout the year
14Non - National Roads Contd
D.O.E.H.L.G. Funding
- Low Cost Safety Improvement Grant 30,000
-
- This allocation is used to provide
- (a) Anti - skid surfacing On the approaches to
Pedestrian Crossings and Traffic
Signals - (b) School Warning Lights at Boleybeg National
Scool - Works Scheduled April - July 2006
15Non - National Roads Contd
D.O.E.H.L.G. Funding
- Strategic Non National Road Grant 500,000
- This allocation , which will be added to
further funding from the Dept. of Transport, is
to further progress design work on the widening
of the Seamus Quirke Road. - This will bring the scheme to tender document
stage from which stage it will be ready to
proceed to tender when funding for construction
is provided. - Works Scheduled Feb. - Oct. 2006
16Non - National Roads Contd
D.O.E.H.L.G. Funding
- Regional Traffic Management Grant
- Allocation of 450,000 allocated as follows
- NewTraffic Lights at Taylors Hill
- Pedestrian Lights at Merchants Rd.
60,000 - Works Scheduled May - Sept. 2006
- Dished Kerbs tactile paving at Crossing
locations 50,000 - Works Scheduled May - Sept. 2006
- Provision of Taxi Ranks
30,000 - Works Scheduled August - Sept. 2006
-
17Non - National Roads Contd
D.O.E.H.L.G. Funding
- Regional Traffic Management Grant Contd
- Traffic Calming Schemes 60,000
- (a) Claddagh ( 1st phase)
- (b) Shantalla ( 1st phase)
- Works Scheduled May - Sept 2006
- Doughiska Road / Dublin Road Junction
improvements 250,000 - This allocation which is for the provision of
junction improvements is being carried out in
conjunction with the provision of the new
in-bound bus lane on the Dublin road from the
Martin Roundabout at Doughiska towards the
Skerritt Roundabout at The Ballybane Road
junction. - Works in progress, March - October 2006
18Non - National Roads Contd
Revenue Funding
- Revenue Funding 1,547,000 allocated as
follows -
- Major Urban Road Footpath Improvements
560,000 - Works Scheduled Feb -Nov. 2006 - Details on
following Slides - Minor Urban Road Footpath Improvements
750,000 Works Scheduled Feb -Nov. 2006 - Details
on following Slides - Traffic Mgt. Facilities Maintenance 237 ,000
- Works on-going throughout the year
19Non - National Roads Contd
Revenue Funding Contd
- Major Urban Road Improvements
- Works Budget Schedule
- Surface dressing 120,000 May- Sept 06
- Sean Mulvoy Rd. Surfacing 45,000 May-June
06 - College Road Bus Bay 10,000 Feb 06
- Western Distributor Road 40,000 May 06
- Surfacing
20Non - National Roads Contd
Revenue Funding Contd
- Major Urban Footpath Improvements
- Works Budget Schedule
- Assess for Disabled 40,000 May- Oct. 06
- Newcastle Rd./Presentation
- Road. Footpaths 10,000 May-June 06
- Lower Salthill Footpaths 10,000 April 06
- Abbeygate St. Footpaths 60,000 April 06
- Seamus Quirke Rd. Paths 15,000 Sept 06
- Urgent Footpath Repairs 40,000 Feb - Oct 06
- Salthill Promenade(Ph.1) 100,000 April-May 06
- Seapoint Promenade 40,000 April-May 06
- Painting Salmon Weir Br. 30,000 May 06
21Non - National Roads Contd
Revenue Funding Contd
- Minor Urban Road Improvements
- Works Budget Schedule
- 1) Surface Dressing 75,000 May- Sept 06
- 2) Dominic Street Upr. Lr. 45,000 June
06 - 3) Sandy Road Depot 15,000 May 06
- 4) Pearse Ave .
45,000 Oct 06 - 5) Circular Road Margins 25,000 May 06
- 6) Renmore Road 45,000 Sept 06
- 7) Market Street 15,000 May 06
- 8) Rockbarton North Surfacing 30,000 June.06
- 9) Children at Play signs 50,000 April May
06 - 10) Rahylin Glebe 30,000 May 06
- 11) Thin Layer Surfacing 75,000 April -
Sept 06 - 12) Street Nameplates 10,000 June 06
- 13)Taking in Charge of Estates 65,000 June
Oct. 06
22Non - National Roads Contd
Revenue Funding Contd
- Minor Urban Footpath Improvements
- Works Budget Schedule
- 1) Renmore Park 10,000 Sept 06
- 2) Shantalla 10,000 May 06
- 3) Mervue 10,000 April 06
- 4) Claddagh 10,000 Sept 06
- 5) Castlelawn 5,000 Sept 06
- 6) Glenard 10,000 Sept - Oct 06
- 7) Dr. Mannix Road 10,000 May
06 - 8) Tirellan Heights 10,000 Nov. .06
- 9) Dr. Colohan Road 25,000 Oct. 06
- 10) College Road 5,000 April 06
- 11) Assess for Disabled 40,000 April - Oct
06 - 12) Urgent Footpath Maintenance 35,000 Feb. -
Oct 06 - 13)St. Anthonys Place 20,000 May 06
- 14)Moyola Park 10,000 Sept 06
- 15)Manor Avenue 15,000 Oct 06
23National Non - National Roads
- Traffic Management Maintenance Improvements
- Maintenance works compromise of the upkeep and
repairs of Bollards, Traffic Signals , Road
Markings , School Wardens and Special Events
Traffic Management. - A total of 477,000 is expended on Traffic
Management Maintenance and Provision of School
Wardens. - Funded by N.R.A.( 40,000) , D.O.E.H.L.G. (
40,000) ,Revenue ( 397,000 of which
145,000 is for Traffic Wardens) - Works Budget Schedule
- 1) National Primary/Secondary 40,000 Feb - Oct
06 - 2) Major Urban Mtce 60,000 Feb Dec. 06
- 3) Minor Urban Mtce 10,000 Feb Dec. 06
- 4) E.S.B. Charges 15 ,000 Jan Dec t 06
- 5) Events traffic Mgt, 22,000 March-Oct. 06
- 6) Provide New Bicycle Parking 20,000 May -
June 06 - 7) Provision of 17 School Wardens 145,000 Jan.
- Dec. 06 - 8) Road Lining Signage 100,000 April Oct
06 - 9)Traffic Light Renewals 50,000 Apr. May
06 - 10)Promotions 15,000 Jan Dec t 06
-
24National Non - National Roads
- Traffic Management Maintenance Improvements
Contd - A total of 850,000 is expended on Traffic
Management Improvement Works - These works are funded by City Council Revenue.
- Works Budget Schedule
- 1) Control Barriers Car Parks 750 ,000 April-
May 06 - 2) Feasability Study at 50,000 May - Sept.06
- Salmon Weir Bridge.
- 3) Bus Bays 50,000 May Dec. 06
-
25Non - National Roads Contd
Capital Funding Projects funded by The City
Council
-
- Doughiska Road Improvements 650,000
- Continuation of 2005 Scheme. Works will be
- completed in 2006 with advance funding from
- the 2007 allocations.
- Works Programmed April - Nov 2006
-
26Non - National Roads Contd
Capital Projects funded by The Department
ofTransport
-
- Seamus Quirke Road Widening 0.5M
- Scheme to be funded with
- 500,000 from Dept of Transport
- 500,000 from D.O.E.H.L.G.
- Consultants have been engaged to process
approved - Scheme to Tender Documents stage.
- Dublin Road Bus Lane 1.5M
- Construction of an inbound Bus Lane on the
Dublin Road (R921/R 338) Between the Martin
Roundabout at Doughiska and the Skerritt
Roundabout at the Corrib Great Southern Hotel -
- Works in progress and scheduled for completion
in June 2006 -
27Non - National Roads Contd
Capital Projects funded by The Department
ofTransport
-
- Strategic Bus Study 200,000
- Consultants have been engaged to progess
- this study and work is in progress.
- Report due in Sept 2006
- The study will examine and make recommendations
on the development and growth of bus transport
within the City and from towns / villages in the
adjacent county areas - The study is to include an examination of all
traffic routes within the City ,(Bus and other
vehicles) , examine the potential for Bus
Transport along key routes, ( existing and
future) and examine measures for bus priority
along appropriate routes. -
28Non - National Roads Contd
Capital Projects funded by The Department
ofTransport
-
- Provision of Improved Cycle facilities on Dublin
Road outbound between Renmore Rd. Junction and
the Skerritt Roundabout at the Corrib Great
Southern Hotel. -
- Allocation 300,000
- Consultants appointed, Design in progress.
- Works to be carried out in 2006.
-
29Non - National Roads
Revenue Funding
- Public Lighting Maintenance Improvements
- Total Budget 1,200,000
- Budget Allocated between Maintenance and
Improvements as follows - (a) Maintenance including Electricity Costs,
Contract Maintenance, - Bulb Replacement , Routine Planned
Inspections and emergency - response 990,000
- (b)Public Lighting Upgrade which includes New
Scheme Installations, - Non - Contract Maintenance and Loan
Commitments on previous - up- grade schemes. 180,000
- (c)Inner City renewals Up-Grade Schemes
30,000
30Non - National Roads
Revenue Funding Contd
- Public Lighting ImprovementsNew Schemes
Schedule Proposed Schemes - (a)Dr. Colohan Rd from Grattan Rd. Junction to
- Seapoint Roundabout along by Toft Park
April - June 06 - (b) Kirwans Lane New decorative Lighting
Sept - Oct 2006 - (c)Briarhill Underpass Repair Damaged lights
May - June 06 - (d) Walkway along by side of Hynes Yard Apr
May 06 - Car Park
- (e) Monivea Road east of Lios Caiseal Entrance
Sept 06
31Non - National Roads
Revenue Funding Contd
- Public Lighting ImprovementsNew Schemes
- Contd
- Proposed Schemes Schedule
-
- (f) Decorative Lighting at Cathedral Sept 06
- (g)Walkway From Highfield Pk. To Rahoon Rd. Oct
06 - (h) Up-grade lighting on Siobhan Mc Kenna
Road April - June 06 - (i) High Road at Ballybrit New
Lighting Sept - Oct 06 - (j) Walkway at side of Ballymoneen Church Apr
May 06 - (k) Walkway at back of Huntsman Pub Apr May
06 -
32Roads Transportation Programme 2006
- Summary of Funding
- National Roads Authority 1,335,000
- Dept. of Env. , Heritage Local Govt.
2,203,000 - Dept of Transport 2,500,000
- City Council, Revenue 4,529,000
- Total Funding 10,567,000
- This represents an increase of 21 on the 2005
programme