Thoughts for the Day - PowerPoint PPT Presentation

1 / 53
About This Presentation
Title:

Thoughts for the Day

Description:

... Day ... Labor strikes. Who assumes the risk and how? Hard Bid. Guaranteed ... Labor, Material, Equipment. Subcontractor Quotes. Vendor Quotes. Construction ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 54
Provided by: dickpr
Category:
Tags: day | thoughts

less

Transcript and Presenter's Notes

Title: Thoughts for the Day


1
Thoughts for the Day
  • A great leader comes along about once in a
    generation and great problems come along about
    three times a week
  • Most people who succeed in the face of seemingly
    impossible conditions are people who simply dont
    know how to quit.
  • Robert Schuller

2
Con 371 Project Management and Safety
  • Contracts, Bid, and Award
  • 29 August, 2001

3
Project Execution
  • Type of Project Delivery helps determine contract
    approach
  • Amount of information
  • Type of Proposal
  • Type of Contract
  • Development of project documents
  • Design Drawings
  • Proposal
  • Contract

4
Contract Types
  • Fixed Price
  • Lump Sum
  • Bid
  • Negotiated
  • Multiple Fixed Price
  • Unit Price
  • Cost Type
  • Reimbursable
  • Cost Plus Percent
  • Cost Plus Fee
  • Guaranteed Maximum Price
  • Target Price

5
Contracting Strategy
  • Degree of Definition
  • Economic Conditions
  • Competitive Situation
  • Anticipated Changes to Scope
  • Schedule Importance
  • Total Cost Importance
  • Quality Importance

6
Contracting Approach
  • General Contractor
  • Negotiated
  • Lump Sum/Fixed Price
  • Construction Manager
  • CM as Advisor
  • CM/GC
  • CM as Agent

7
General Contractor
  • Usually self-performs work
  • Holds subcontracts
  • Assumes risk/reward of buyout
  • Performs minimal management services

8
General Contractor
  • Lump Sum - Fixed Price
  • holds subcontracts
  • assumes risk/reward of buyout
  • requires fully developed documents
  • Negotiated
  • holds subcontracts
  • owner usually assumes risk/reward of buyout
  • common for fast track
  • usually open-book

9
Construction Manager
  • Performs Extensive Management Functions
  • May/may not hold subcontracts
  • Owner Assumes Risk/Reward of Buyout
  • Usually open book
  • May/may not self-perform (CM/GC)

10
Construction Manager
  • Usually Negotiated Contract
  • Guaranteed Maximum Price
  • Cost Plus Fixed Fee
  • Cost Plus Fee with a Target Price

11
Project Fee
  • Fee is the contractors return on his/her
    investment and his/her reward for assuming risk
  • Although attractive, low fees can endanger
    project success
  • attract lower caliber firms
  • less contractor commitment to success of project
  • less experienced personnel assigned to project

12
Project Fee
  • Most effective way to reduce fee is to reduce
    risk
  • Contingency built into all estimates based upon
    adequacy of documents
  • Often performance incentives based on project
    goals are used

13
Contracting ApproachType of Contract
  • Hard Bid - Fixed Price
  • Exposes contractor to most risk
  • Fee and contingency usually high

14
Contracting ApproachType of Contracts
  • Fee Basis
  • Percent of Cost
  • Fixed Fee
  • Risk - Fee Relationship
  • G M P
  • Cost Plus Fixed Fee
  • Cost Fee Target Price
  • Incentives

15
Fee Basis
  • Percent of Cost
  • fee is expressed as simple percent of total
    construction cost
  • Disadvantage
  • fee varies directly with cost of the work
    little incentive for contractor to control cost

16
Fee basis
  • Fixed Fee
  • fee is expressed as a fixed dollar amount
  • Disadvantage
  • If final cost of work is substantially higher
    than the original it could be detrimental to the
    contractor
  • if substantially lower detrimental to the owner

17
GMP
  • Contractor prepares an estimate based on
    documents and issues a Guaranteed Maximum Price
    for the project
  • Also known as Not To Exceed price
  • Exposes contractor to risk of exceeding GMP

18
Cost Plus Fixed or Percentage Fee
  • Contract based upon final cost of work as
    determined at completion plus fee
  • Contractor does not offer cost guarantee
    reduced risk

19
Cost Fee Target Price
  • Contractor fixes cost of project as in GMP and
    makes good faith effort to meet price
  • Works well when contractor and owner have
    existing relationship
  • Reduces risk to contractor reduces fee

20
Contract are used to assign risk
  • What kinds of risks are in a project?

21
What are the project risks for the Washington
Monument refacing?
  • Safety
  • Completion
  • Material acceptance
  • Labor Productivity
  • Weather

22
Areas of Contract Risk
  • Degree of project definition
  • Design changes
  • Escalation of labor and material costs
  • Labor productivity
  • Climatic conditions
  • Labor supply
  • Bids over estimate
  • Loss not covered by insurance
  • Natural disasters
  • Labor strikes
  • Who assumes the risk and how?

23
Risk/Fee Relationship
  • Hard Bid
  • Guaranteed Maximum Price
  • Cost Plus Fee with a Target Price
  • Cost Plus Fixed Fee
  • Cost Plus Percent Fee
  • CM as Advisor

24
Degree of Risk inConstruction Contracts
Assumes Most
Shared
Shared
Shared
Shared
Assumes Most
25
Construction ContractsElements
  • Offer
  • Invitation for Bid
  • Bid Forms
  • Acceptance
  • Notice of Award
  • Notice to Proceed
  • Consideration
  • Money
  • Time

26
Project Phases
  • Preconstruction
  • Contract Award
  • Contract Administration

27
Preconstruction Phase
  • Determine Price and Construction Methods
  • View Site for Information
  • Pre-bid Site Visits
  • Obtain Clarifications
  • Addendums
  • Verify Labor, Material, Equipment
  • Subcontractor Quotes
  • Vendor Quotes

28
Construction ProposalsTime Contractor
Qualifications
  • Stated in Proposal
  • Calendar Days
  • Periods of Non-Work
  • Liquidated Damages
  • Administrative Costs
  • Actual Damages
  • Qualifications
  • Responsive
  • Responsible

29
Construction Contracts
  • Contract Technical Terms
  • Contract Commercial Terms

30
Construction ContractsTechnical Terms
  • The scope of work
  • Scope
  • Price
  • Conditions of Contract
  • General
  • Site safety and security
  • Special
  • Plans
  • Construction drawings by design agents
  • Shop drawings by contractors
  • Specifications
  • Performance
  • Method
  • Responsibilities of Owner and Contractor
  • Guarantees/ Warranties
  • Performance
  • Equipment
  • Schedule
  • Engineering

31
Construction ContractsCommercial Terms
  • Suspension and termination of work
  • Force majeure
  • Insurance and risk management
  • Applicable law
  • Arbitration
  • Type of contract
  • Fee structure
  • Payment terms
  • Limits of liability
  • Project change notices
  • Cost-escalation clauses
  • Subcontracts

32
Construction ContractsContract Bonds
  • During Bidding
  • Bid Bond
  • Contractor will provide Contract Bonds and do
    work
  • During Performance
  • Performance Bond
  • Completion of Project
  • Payment Bond
  • Payment of Subcontractors, Workers, Suppliers

33
Contract Administration
  • Construction - accomplished by contract
  • Understand terms
  • Ensure compliance
  • Contract requirements
  • Notice to Proceed
  • Authority of project personnel
  • Submittal requirements
  • Progress schedules/payments
  • Change order procedures
  • Disputes
  • Quality control

34
Contract AdministrationProgress Payments
  • Unit Price
  • Quantities in place
  • Retention
  • Lump sum
  • Schedule of values
  • Percentage of work accomplished
  • Difficult to estimate accurately
  • Cost plus contracts
  • Accounting system to collect costs incurred
  • Submittal of payrolls, invoices, delivery tickets

35
Contract AdministrationChanges/Claims
  • Changes
  • Formal request - owner initiated
  • Constructive changes
  • Differing site conditions
  • Claims
  • Delay
  • Acceleration
  • Performance quality
  • Contract related

36
Thoughts for the Day
  • Present choices determine future consequences
  • You manage things You lead people
  • Grace Murray Hopper
  • Admiral, U.S. Navy (retired)

37
CON 371 - Project Management and Safety
Project Organization 29 August 2001
38
Project Organization
  • The function of creating in advance of execution
    the basic conditions that are required for
    successful achievement of the project objectives.
  • Objectives - project goals

39
Project Organization Concept
  • Define Project Organization Principles
  • Establish the proper relationship among the work
    to be done, the people doing the work, and the
    workplace
  • Present the Complex Issues
  • Elements that impact the size and nature of the
    organization

40
Traditional Project Delivery
  • Life Cycle Steps in the project
  • Owner contracts with Architect
  • Architect hires Engineering Consultants
  • Construction Drawings Completed
  • Architect sends out for bid on behalf of Owner
  • Architect receives bids and assists Owner in
    selection of Contractor.
  • Contractor Contracts with Owner.
  • Construction.
  • Contractor turns over to Owner
  • Owner hires his Operations staff.

41
Project Responsibilities
  • Planning and Scheduling
  • Estimating
  • Engineering
  • Change Orders
  • Administration
  • Materials
  • Procurement
  • Cost Control
  • Safety
  • Supervision
  • Labor
  • Quality Control
  • Accounting
  • Payroll
  • Security
  • Subcontractors

42
Traditional Project Structure
Contract Strategy Major Players Scope of
Work Task Financial Timing
What types of organizational designs are used to
support the project?
43
Functional Organization
President Owner
44
Functional Organization
  • Advantages
  • Stability
  • Excellent Corporate Memory
  • Latest Technology
  • Understanding of tasks
  • Tight Control
  • Disadvantages
  • Low adaptability
  • Minimum appreciation of project objectives
  • rigid operating rules
  • resistance to change

45
Task Force Organization
46
Task Force Organization
  • Advantages
  • Team Spirit
  • Responsive to new ideas and methods
  • Self sufficient
  • High adaptability
  • Understanding of task
  • Disadvantages
  • Poor stability
  • No corporate memory
  • No functional checks and balances
  • Reinventing the wheel

47
Matrix Organization
48
Matrix Organization
  • Advantages
  • Strengths of functional team
  • Strengths of project-oriented team
  • Access to corporate memory
  • Control of project objectives
  • Disadvantages
  • Defining accountability to functional and project
    managers
  • Whos the boss?

49
Thoughts on Organizational Design
  • Vertical vs Horizontal
  • How many communication layers?
  • Span of Control
  • How many people can one supervise?
  • Line and Staff Functions
  • At what level do we want the functions to exist?
  • Corporate Organizational Structure
  • How does the Corporate Organization look?

50
The Players and their Corporate Organizations
51
Complexities to Project Organization
  • How will the complexity of the project impact the
    size and nature of the organization?

52
A List of Complexities
  • Project Work Tasks
  • Project Delivery Method
  • Contract Strategy
  • Owners Resources
  • Local Labor Market
  • Governmental Authorities
  • Scope Areas
  • Technical Level
  • Quality
  • Project cost
  • Functional Expectations
  • Project Schedule
  • Size of Project

53
Typical Field Organization
Write a Comment
User Comments (0)
About PowerShow.com