Title: RISK
1RISK CAPACITY INVESTMENT INCENTIVES IN
ELECTRICITY MARKETS
- Peter Jackson
- Department Of Management
- University Of Canterbury
2Outline
- My research topic/motivation
- Investment
- Optimal Plant Mix
- Hydro/Strategic concerns
- Contracts/Portfolios
- Market Structure/Solutions
3My research..
- Evaluate the impact of investor risk on
investment decisions - Explicitly deal with impact of
- Hydro risk
- Strategic behaviour
- Deterrence
- Outcomes, Solutions
- Investment/Entry
- Pricing/Efficiency
- Market structure
- Is not finished (hardly started!!!)
4Motivation - Do electricity markets deliver
appropriate security?
- Security concerns were to the fore with central
planners - Central planning proved uneconomic, and often
over-investment resulted - Electricity markets have been created in an
effort to capture economic efficiency - But private investors wont invest unless it is
economically justified - Private investors face different risks and are
investing into a spot market that is susceptible
to strategic behaviour
5Investment and Prices Why Invest?
- Generation plant can be valued (equivalently) as
a call option - Option value is dependent on pricing
- Could discount or model risk more explicitly
6Basic Screening Curve Analysis
- Optimal Plant Mix
- Risk Free
- Not Strategic
- Some energy limited plant
- With shortage costs, fixed costs are recovered in
equilibrium
7Investment Risk
- My research focus is
- Hydro risk
- Strategic risk
- But there are significant other risks for
investors - Reliability
- Regulatory/Political
- Demand growth
- Input prices
- Technological/Resource
- Transmission
- To a greater or lesser extent all plant faces
risks but peaking plant is most vulnerable.
8Energy Limited Hydro
- Energy must be/should be used
- Inflow quantities determine total energy
available - Reservoir size and plant rating determines
flexibility - Inflow sequences are also important
- Peaking plant may never operate for its true
purpose. - Being in the optimal plant mix is not the same as
being in the dispatch.
9Energy Limited Hydro
- Notional revaluation of fuel and capital cost
based on energy available - All plant is impacted but peaking plant is worst
off
10Peaking Plant Cautious Entry
- Given hydro variability, how much peaking plant
is required? - Apart from other issues the investor need to know
inflow distribution. - What is really important is the PDC, and this can
vary for a variety of reasons eg hydro inflows - But what if PDC is a result of gaming? (And
gaming and hydro inflows are probably related) - What is the true underlying PDC? It may be
impossible to estimate, especially for an entrant
11The Impact Of Risk On Adequacy
12Peaking Plant Investment
- Price and quantity risk from a variety of sources
- Natural
- Strategic
- Hydro generation makes forecasting particularly
difficult - Not suitable for many standard forms of contract
- Finance difficult to obtain given risks
- So how do we get any peaking plant built at all?
13Wider considerations.
- Standalone entry very difficult
- But firms have multiple generation plants, and
contracts in place lower risk - The impact on the portfolio of assets and
obligations is more relevant than the performance
of the individual asset - Spot market gaming may increase returns above
SRMC and incentivise investment - Strategic firms will not want to settle contract
shortfalls with competitors - Deterrence
- Market structure may (or may not) help
14NZ - Market Structure
- LP Clearance
- Market design goals
- Allocative efficiency
- Productive efficiency
- Dynamic efficiency
- NZ Market
- S.O.Es Private investors
- Energy only market
- Vertical Integration
- Hydro influence
- Few Large customers
Wolak Report, 2009
15Potential Solutions
- Tolerate gaming
- Two part markets
- Capacity ticket systems
- Current proposals from taskforce
16Contracts and Risk I
- Consider increasing risk on generators who are
unable to cover contractual obligations
17Contracts Risk II
- Increasing cost of over contracting improves
adequacy but this analysis assumes contracts are
exogenous - What if contracts are endogenous? Equilibirum
contract prices will be higher for higher risk - Customers will get more security (but pay for it)
- What is the relative performance of other
solutions? - Market power (18 - Wolak)
- Capacity payments (25 - Initial market study)
- Evaluation required
18Future Work required
- Energy limited plant
- MW limited
- Dynamic analysis
- Plant retirement
- Demand growth
- Investment
- Strategic interactions
- Spot market
- Cautious Entry
- Deterrence
- Complementarity Formulations
- Evaluate remedies