Title: Rhodri Jones


1
BPM Issues in Sector 7-8
  • Asynchronous Trajectory Mode
  • Worked on 1st Shot
  • All BPMs acquired
  • BPM Problems
  • BPMIV.88104 H / V flip suspected
  • H pick-up on BI installation traveller should
    be V
  • Fibre mix-up on 8 BPMs Q1-Q7 Left of 8
  • Corrected on Saturday morning
  • BPM.34R7.B2
  • Horizontal plane inverted
  • BPM.28R7.B2
  • B1-B2 mismatch of individual button signal
  • Reflectometry team?
  • BPM.12R7.B2
  • H / V inversion fibres crossed
  • BPMWE.5L7.B2
  • H polarity error (nothing visible on photos)

2
BPM Issues in Sector 7-8
  • Other Suspects
  • BPMW.5L7.B2
  • both H V - gain/polarity? optics? ()
  • BPMSX.4L8.B2
  • both H V - gain/polarity? optics?
  • Beam is off centre in BPMSX by 10mm (in between
    D1 D2)
  • Optics
  • phase advance error
  • insufficient response data for further details

Courtesy of R. Steinhagen
3
BPM Issues in Sector 7-8
  • Successful Tests of Synchronous Capture Mode
  • BST successfully used to advance pre-pulse to 2
    turns before injection
  • Data collected from a single front-end crate
  • alternate BPMs from Q1L8 to Q32L8
  • Conclusions
  • Pre-pulse to bunch timing stable to better than
    3ns
  • limited by resolution of BPM TDC
  • Reproducible
  • Uncorrected corrected data sets taken 2 shifts
    apart
  • Will now automate this to allow quick phasing in
    of all BPMs