Title: The Way We Work update Property Panel 23 May 2006


1
The Way We Work updateProperty Panel 23 May
2006
  • David Robinson

2
Progress achieved in 2005/06
  • Apsley One fit-out by Mace
  • Relocation of 511 staff in Jan 06
  • Release of
  • Langleybury
  • 501 St Albans Rd
  • Manor Street
  • Dacorum Civic Centre
  • Hempstead Rd
  • Cow Lane
  • Apsley Two landlord started refurbishment

3
Change management
  • Change management approach agreed
  • Changing HCC culture and working practices
  • Learning review completed
  • Stakeholder engagement
  • Apsley Strategic Group
  • Apsley Improvement Group
  • Manager's session

4
(No Transcript)
5
What is now different at Apsley?
  • Office environment open 0630 to 2130hrs and
    being used Monday to Saturday
  • Touchdown areas for visiting HCC staff being used
    on a regular basis
  • Approximately 50 of staff now using Voicemail
    effectively on a regular basis with 34
    retrieving messages when away from the office
  • The first 20 Staff from Apsley have been set up
    and are using their own Broadband to access HCC
    systems from home locations

6
Targets for 2006/07
  • Handover of Apsley Two to Mace
  • Complete fit-out of Apsley Two
  • Relocate next 500 staff to Apsley Two
  • Acquire and fit-out the A1 base
  • Relocate Hertfordshire Development Centre
  • Complete sales of vacated premises
  • Effective change management including FM
  • Electronic document storage

7
Apsley Two
  • Part of the combined acquisition of Apsley
  • 15 year full repairing lease
  • Formerly occupied by BT
  • 1980s glass cladded structure
  • 67,704 sq ft over 3 floors
  • 274 car parking spaces
  • Fit-out completion by Dec 06
  • Staff move in Jan 07

8
Apsley Two
9
(No Transcript)
10
Occupation of Apsley Two
  • CSF / ACS staff from Hertsmere and St Albans
  • Training suites from New Barnfield
  • Child / adult protection conference suites
  • Occupational health facility
  • Trading Standards met lab and evidence rooms
  • E-learning areas
  • Meeting / conference rooms

11
Properties released by Apsley Two
  • St Albans
  • Porters Wood
  • Alma Road
  • Hertfordshire House
  • Hatfield
  • New Barnfield
  • (Training block)
  • Hertford
  • Castle Street

  • Watford
  • Clarendon Road
  • Lower High Street
  • Upton Road
  • Borehamwood
  • Civic Centre
  • Abbotts Langley
  • Parsonage Close

12
Agreed staff requirements for the A1 base
  • 841 CSF staff
  • 613 ACS staff
  • 106 Vertex staff
  • 49 client services staff
  • Hertfordshire Development Centre
  • Trading Standards officer team (2010)

13
Key Properties released by A1 base
  • Hertfordshire Development Centre
  • Mount Pleasant, Hatfield
  • Old Grammar School, Letchworth
  • Porters Lodge, Ware
  • Southgate, Stevenage
  • Parkway, Welwyn Garden City
  • Warren Park Rd, Hertford
  • Eleanor Cross Rd, Waltham Cross
  • 19/21 St Albans Rd, Hatfield

14
County Hall
  • County Hall must accommodate
  • Over 200 CSF and ACS operational staff moving
    from the East locations
  • Teams identified to move out so far include
  • ACS Finance
  • Money Advice unit
  • Crime and Drugs Strategy unit

15
Properties released by moves to C/Hall
  • Warren Park Road, Hertford
  • Porters Lodge, Ware
  • 103 New Road, Ware
  • Old Fire Station, Ware
  • Eleanor Cross Road, Waltham Cross
  • 5-9 Limes Court, Hoddesdon
  • Drill Hall, Cheshunt

16
Financial position
  • Total capital budget 31.8m
  • Capital spend to date 6.6m
  • Projected Capital receipts 35.2m
  • HCC project management c.0.4m p.a.
  • Business case projected revenue savings
  • 4.3m over 7 years to 2011-12

17
Questions?