Title: Performance Based Specifications
1(No Transcript)
2Ultra Thin Whitetopping (UTW)
- Thin layer (50-100mm) of PCC concrete over an
existing distressed AC pavement - Similar to mill/inlay
- Bond developed between AC and PCC forming a
composite pavement - PCC is usually high early strength and fiber
reinforced. - Joint spacing is much shorter (1-3m)
- Requires thick underlying AC
3Contents
- Study Background
- Scope of the Study
- Life-cycle Cost Methodology
- Analysis Sites - Data set
- Parametric Data
- Pavement performance models, user costs,
treatments, trigger limits, discount rate - Results
- Conclusions
4How the Study Came About
- BC Redimix Association
- Had heard of the UTW technology and wanted to
know if it could be used in the lower mainland - City of Surrey
- Was interested in knowing if UTW would be a
viable strategy in Surrey - Canadian Portland Cement Association
- Agreed to fund a study
5Scope of the UTW Study
- Identify sites thought to be suitable candidates
for UTW (intersections prone to rutting, AC
thickness greater than 120mm) - Assemble data (traffic geometry, structure,
construction and performance history) - Assemble parametric information (available
treatments, rehab strategies, user costs,
pavement performance models, discount rates - Conduct LCC analysis
- Report on effectiveness of UTW vs other strategies
6Study Methodology
- Life-cycle Benefit/Cost for infrastructure
preservation planning
7Life-cycle Cost
- Total Present Value (P.V.) of all costs over the
on-going life of the pavement -
- Life-cycle cost Initial Construction
Costs - P.V. Rehabilitation Costs
- P.V. Maintenance Costs
- P.V User Costs
- - P.V. Salvage costs
8Life-cycle costs for Preserving existing pavements
- Life cycle costspv
- P.V. Rehabilitation Costs
- P.V. Maintenance Costs
- P.V. User Costs
-
- (the analysis period is made long enough that the
salvage value is exhausted - 50 years)
9Pavement Preservation Rehabilitation and
Maintenance Treatments
- Crack Sealing
- Patching
- UTW 50mm/80mm/100mm
- Overlay
- Reclaim
- Reconstruction
10Treatment application timing is a variable
11Pavement Strategies
- Strategy is comprised of combinations of
individual treatments and treatment application
timings - Therefore, for a given site there are dozens of
potential strategies.
12Example Pavement Strategies(combinations of
treatments)
13Two methods of determining User Costs Savings
(benefits)
- Measure User Costs Directly (with Road User Cost
Models) - Vehicle Operating cost models
- Delay Cost Models
- Accident Cost Models
- Measure User Costs Indirectly (by measuring the
Area Under a Performance Curve)
14Direct Measurement of User Costs
Vehicle Repair costs Roughness Fuel
Consumption Roughness Delay Costs
Treatment application rate, Detour
Length
15RUCdo-nothing - RUCstrat 1 RUCBenefit strat 1
Calculating Strategy Benefits Using RUC
16Area-Under the-Curve Methodof measuring strategy
benefits
Calculating Strategy Benefits Using AUC
17List of Strategies (cost benefit)
18Strategy Costs are Compared with benefits to
measure cost effectiveness
195 Methods of Defining Cost Effectiveness
- Minimum LCC called Total Transport Cost (TTC)
- Minimum of (rehab Maintenance user costs)
- B/C
- (RUCdo-nothing - RUCstrategy) / (rehab maint
costs) - Min Cost (to meet Performance Specification)
- Minimum of (rehab Maint) (ie. ignore
benefit to minimize cost) - Maximum AUC Benefit
- Maximize the Area under the performance curve
(ignore cost to maximize benefit) - Maximum AUC B/C
- AUC / (rehab Maint)
20Cost Effectiveness ( using RUC)
Max Benefit/Cost
.
Min PV Cost
Min TTC
Worst First
21Cost Effectiveness (using AUC)
Max Benefit/Cost
Maximum Benefit
Min PV Cost
22Common Policies for selection of effectiveness
measurement method
- Worst First (used in the absence of preservation
planning) - Minimum total LCC (TCC) - (minimizes total cost
to the economy) - Max benefit/cost - used when funding is severely
constrained (attempts to provide best public bang
for the tax buck) - Minimum PV Cost to meet performance based
objectives (used with performance based specs
such as in Australian/New Zealand Maintenance
Contracts) - Maximum Benefit - Minimizes delay costs
(ignoring direct agency costs).
23Analysis Data Set Requirements
- Site data affecting pavement performance
- subgrade, pavement structure, traffic volumes,
vehicle loadings, climate and construction
history - Site data affecting Road User Costs
- traffic volumes and mix, intersection
configuration, and/or detour lengths - Site data required for calibrating pavement
performance prediction models - rutting history, roughness history, cracking
history
24City of Surrey Supplied
- Existing AC thickness is the most important
consideration for UTW - Surrey has an extensive pavement thickness
database - selected 150 arterial and collector intersections
with AC thickness greater than 120mm - Historical roughness, rutting and cracking data
- Locally calibrated RUC models
- Locally calibrated pavement performance models
- 1999 Traffic AADT Volume Data, 1995
Classification data
25Parametric Data Requirements
- pavement performance models
- Asphalt
- UTW
- set of potential treatments and costs
- maintenance treatments
- rehab treatments
- treatment trigger limits
- potential strategies
- combinations of treatments required to preserve
the pavement indefinitely - road user cost models
- discount rate
26Performance Prediction Models
Crack Strength, Traffic, Age Rut
Crack, Strength, Traffic,
Age Roughness Rut, Crack, Strength,
Traffic, Age, Environment
27Example Crack Prediction Model
28Example Rut Prediction Model
29Example Roughness Prediction Model
30Pavement Quality Index (PQI)(Composite Index for
AUC Calculations)
Overall Condition of the pavement Cond. Index
Roughness, Cracking, Rut etc. This Index is used
extensively in BC
31Overall Pavement Quality
32Rehabilitation Treatments and Costs (Can)
- For intersections in Surrey (weekend work, all
inclusive) - Reconstruction 50/m2
- Mill/Inlay 50mm 18/m2
- Deep Patch (prior to inlay) 13-55/m2
- 100mm UTW 45/m2
- 80mm UTW 40/m2
- 50mm UTW 37/m2
33Maintenance Treatments and Costs
- Crack Sealing 1.50/ln-m
- Route Seal Cracks 2.50/ln-m
- Thin Overlay/Patching 8/m2
34Treatment Triggers/Limits
- Reconstruction rutting (20 - 40mm) cracking (
gt 20) - Mill/Inlay rutting (20 - 40mm) cracking ( 5 -
25) - UTW rutting (20 - 40mm) cracking ( 5 - 40 )
- Crack Seal All low severity cracks every 3
years - Route Seal All medium severity cracks every 3
years - Patching All high severity cracks every 3 years
35Predicted Cracking - Overlay in 2004
36Predicted Rut - Overlay in 2004
37Predicted Roughness - Overlay 2004
38Overall Pavement Condition - Overlay in 2004
39Reconstruct - 2008
40Reconstruct - 2009
41Reconstruct - 2010
42UTW Pavement Performance Models
- Inferred from UTW design charts
- provide design life in terms of allowable trucks
to the end of design life - PCC industry claims
- very little load related cracking or rutting
until the end of the design life - Assumed that at the end of the design life the
pavement deteriorates at the rate of the
remaining underling AC (which is now thinner)
43UTW - 2004
44UTW - 2004
45UTW - 2004
46UTW - 2004
47UTW - 2005
48UTW - 2006
49UTW - 2007
50Road User Cost Models
- Vehicle Operating Costs (models are available)
- Fuel Consumption
- Vehicle Repair and parts consumption
- Delay Costs (no readily available models)
- Freight Rates
- Value of Commercial Time
- Value of Personal Time
- Idling Fuel Consumption
- Detour Costs (more easily calculated than delay
costs) - Fuel Consumption
- Vehicle Repair and parts consumption
- Amortization, Insurance etc.
51VOC Model Used
Surrey Model
Ontario Model
58 of Ontario
52VOC models used
Ontario Model
58 of Ontario
Surrey Model
53Delay Costs (not used)
- Most Significant Cost
- at 5/car/hr and 10/truck/hr a 30 min delay over
two days at major intersection could cost as much
as 500K - Difficult to agree on
- Longer life treatments such as PCC or
reconstruction are heavily favoured - Therefore the study assumed that all traffic
would be detoured.
54Detour Costs
- Detour Length 1.6 km (Surrey Arterial grid)
- VOC
- 0.35/car/km
- 1.00/truck/km
- Off-peak Closure Period
- Reconstruction 4 days
- UTW 2 days
- Mill/inlay 1 day
554 6 Discount Rate
- 4 is the long term difference between B of
Canada prime and Inflation - 4 is used by BC Alberta Governments
- NWT uses 6
- Ontario uses 7
- Arguably should use greater than 4 to allow for
future lower costs resulting from new technology
56The Analysis
- Used Deighton Associates Limited - Total
Infrastructure Management System (dTIMS) LCC
analysis software - Tested 150 intersections
- Approximately 44 strategies/intersection
- Cost effectiveness of 6,600 strategies measured
by each of the 5 cost effectiveness methods
57The Results
- The strategy selected is heavily dependant on the
cost effectiveness method used - It is impossible to have exactly the same
strategy selected by all methods - It is possible to have a strategy comprised of
the same underlying treatment (applied in
different years perhaps) selected by all 5
methods - example at a given intersection
- 50mm UTW lowest cost
- 100mm UTW Max AUC
- 75mm UTW Max B/C
58UTW Effectiveness
59Example Effects of selection criteria on a
network of pavements
60(No Transcript)
61(No Transcript)
62The bad news
- Hard to find thick pavements
- Of the 36 sites where UTW is most effective, only
2 are warranted to be done in 2000/2001 - The AC thickness must be uniform ie. Continuously
thick (additional pavement thickness survey cost) - UTW is less compatible (than AC) with future
geometric changes
63(No Transcript)