iMICE Status of Selected Activities - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

iMICE Status of Selected Activities

Description:

... VLPC Cassettes in each ... Cassette Gas system. Lid Heater and temp control circuitry. Vacuum pump. 4 ... Heaters in cassette (1 per module) control to ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 19
Provided by: AlanB154
Category:

less

Transcript and Presenter's Notes

Title: iMICE Status of Selected Activities


1
iMICE Status of Selected Activities
  • MICEUK Meeting
  • 2nd May 2006
  • Malcolm Ellis

2
Introduction
  • Review of a few of the non-UK MICE activities.
  • Almost all material is stolen from other talks at
    various meetings (MICE CM, VC, PCs and NFMCC CM).
  • Areas touched on are
  • Tracker cryostat system (Fermilab)
  • Tracker electronics (Fermilab, IIT RAL)
  • Muon Test Area (Fermilab)
  • 201 MHz cavity at MTA (LBNL)
  • CKOV I (UCL Mississippi)
  • DAQ (Geneva)
  • Frascati Test Beam plans (Geneva)

3
Tracker Cryo
  • MICE VLPC Cryo
  • 2 1024 Ch VLPC Cassettes in each system
  • Two systems per tracker- 4 Total for MICE 1
    Test Stand
  • Sumitomo GM Cryocooler
  • Cold-end operating point at approximately 7K
  • Cassette Gas system
  • Lid Heater and temp control circuitry
  • Vacuum pump

4
Prototype Cryostat
5
Cryostat Performance
  • Typical Cooldown

6
Temperature Control
  • Two stage Control
  • Heat applied to 2nd stage of cryo-cooler (7K)
  • Commercial Oxford temperature controller
  • Heaters in cassette (1 per module) control to
    final set point (9K)
  • System controls to better than 10 mK
  • Spec 50 mK
  • However running with 50Hz power (KEK), left
    cassette heaters were barely on almost no
    control from cassette
  • Thermal link

1 Count1 mK
7
Cryo Status Plans
  • The Prototype MICE VLPC cryo-system has been
    operated successfully for many months both at
    Fermilab and KEK
  • All design specs have been met except for a
    left-right temperature asymmetry
  • Thermal link design has been modified
  • This will be tested as soon as the Fermilab
    shutdown is over (June 06)
  • Cryo-coolers have been delivered
  • Cryostat parts are on order expected delivery
    is mid-June 06.
  • All systems will be assembled, tested, and
    commissioned by the end of the calendar year

8
AFEIIt Status
  • The AFE IIt pre-production boards (15) have been
    tested to D0 spec
  • The first boards came up very quickly
  • In about 1 hour
  • No green wires!
  • TriPt testing is done
  • Yield is about 80
  • More than enough chips for D0 MICE Spares for
    both experiments
  • Plus second pass could yield more
  • Production Order released April 18th
  • About 14 week lead for delivery of all boards
  • But many will arrive earlier
  • The critical issue for MICE is MICE-specific
    firmware development for AFE IIt
  • NOT a Trivial amount of work

9
AFEIIt Test Stands
  • The MICE IIT group has assembled an AFE test
    stand and will be responsible for testing left
    hand production boards
  • Part of Negotiated agreement that led to D0s
    donation of AFE IIt boards to MICE
  • In Addition an AFE IIt test stand has been
    assembled at RAL
  • Board maintenance
  • Firmware development

10
Muon Test Area Complex
11
201 MHZ Cavity at the MTA
12
Results from Preliminary Test
  • Conditioning started in late February 2006 with
  • Flat copper windows (plates) with Ti-N coatings
  • RF diagnostics
  • Good vacuum high 10-9 Torr
  • Without an external magnetic field, the cavity
    conditioned very quietly and quickly to reach
    16 MV/m
  • Limited by available RF power.
  • Test plan being developed
  • External magnetic fields
  • Achievable gradients vs magnetic field
  • Curved Be windows.

13
CKOVI
14
Sr90 b Source
15
CKOVI Road Map
Summer 06? 1 _at_ FNAL1x1x1 modulewhite
reflectorMeasure pe yields
ModelRayleigh Scattering Scattering vs
?Absorption 0Transmission vs ?Aperture 3x3 or
4x4
Fall- 06Mechanical fabrication Reflectors/Cones
Spring 07Aerogel purchaseBegin Assembly
CKV01 Summer 07
16
DAQ Frascati Test Beam
  • Preparation for the test of PID detector
    components and potential front end electronics at
    a test beam at Frascati in the summer.
  • Stand alone DAQ is being built for this (not
    reusing UniDAQ system developed for KEK tests).
  • Work being done at University of Geneva.
  • Stand alone, local DAQ
  • DAQ Reduced to minimum
  • Local Start/Stop of Runs (no remote Run Control
    -gt no DAQ framework, no event building)
  • Write data on local Disk
  • Readout particle per particle
  • No interrupts
  • VME-PCI interface CAEN V2718 only
  • Limited number of FEE modules supported
  • TDC V1290
  • QDC V972
  • Only 2 Event types
  • Particle Event
  • Calibration Event

17
Status (19th April 2006)
  • Manpower J.S. Graulich and 1 undergraduate
    student
  • Software for V2718 80 done
  • All fundamentals are done
  • Read and Write in A32/D32,D16
  • Read in BLT32, BLT64
  • Basic I/O Register (2 Inputs, 5 Outputs)
  • Software for V1290 80 done
  • Only tested with V1190, should be easily
    transported to V1290
  • Not fully commissioned yet
  • Software for V792 40 done
  • Work in progress
  • Software for run control 25 done
  • Working on User interface

18
First Results TBD
  • Readout rate of V1190
  • 27 Mbytes/sec in BLT64
  • -gt 5 ms to read the full V1190 buffer memory
  • (Readout of the tracker would require at least 40
    Mbytes/sec already obtained with BIT3 interface
    -gt we might have to deal with 2 different
    interface. No impact for BTF)
  • I need some inputs
  • Define needs for calibration
  • Define needs for online monitoring
  • Define needs for other FEE modules
  • Tests of QDC FEE options will start in background
  • Organize transport of my PC
  • When is the test beam ?
Write a Comment
User Comments (0)
About PowerShow.com