PACS Status Report - WE - PowerPoint PPT Presentation

1 / 6
About This Presentation
Title:

PACS Status Report - WE

Description:

Problems in CFM identified (ringing of bus lines) and S/W work-around implemented ... change to red Ge:Ga array 16/19 Dec 06. Warm-up/cool-down for exchange ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 7
Provided by: albrechtp
Category:
Tags: pacs | report | status

less

Transcript and Presenter's Notes

Title: PACS Status Report - WE


1
PACS Status Report - WE SVR-2 MPE, 18 Jan
2007 O.H. Bauer
2
FM ILT WE Configuration
  • DPU FM
  • SPU FM (partly repaired)
  • DECMEC EQM (not redundant and only blue array)
  • BOLC FM
  • Second set-up used for SPU OBS development

3
Instrument Overview and Subsystem Responsibilities
Cryo-Harness
13
4
WE Status I
  • DPU
  • Problems in CFM identified (ringing of bus lines)
    and S/W work-around implemented
  • FM apparently does not show the same symptoms,
    but showed some erratic behaviour (MEMCOPY
    routine caused corrupted data packets)
  • SPU, DECMEC (but also LFI REBA, ...)
  • During tests at CRISA read errors from the DSP
    program memory (PRAM), only with special memory
    contents, were found.
  • Error was found on all DSP PCBs ? systematic
    design error!
  • PACS FM SPU partially repaired, can be used for
    FM ILT.
  • ? Complete repair and re-qualification after ILT
    will take four weeks.
  • BOLC OK

5
WE Status II
  • DECMEC
  • During TV test (cold phase, -25C) DECMEC FM
    stopped after one hour of operation two dead
    transistors found, temperature/design problem
  • ?Delivery of qualified FM (not EMC can be done
    after FPU delivery) later than mid Feb has
    dramatic impact on ILT schedule and delivery
  • ?Most of ILT has to be executed with EQM, which
    is not fully FM-equivalent (lacking redundancy,
    only blue DEC)
  • ?Change to red array and swap of EQM against FM
    need warm-up to 40 K

6
Schedule
  • Schedule Summary FM (refurbished CQM for FPU)
  • ILT at MPE cool down started 19 Oct
    06
  • Partial warm-up/cool-down forchange to red GeGa
    array 16/19 Dec 06
  • Warm-up/cool-down for exchange
  • of chopper, repair of illumination
  • problem and possible DECMEC
  • exchange 23 Dec 06 18 Feb 07
  • ? DECMEC FM delivery to MPE mid Feb 07
    ??
  • FM WE/FPU delivery to Project late
    April 07 !?
  • Schedule for FS FPU
  • FS FPU ready for possible
  • delivery to Project
    end Sep 07
Write a Comment
User Comments (0)
About PowerShow.com