Title: Support chariot for ITS
1Support chariot for ITS FMD services on the
RB24 side
- Foreward
- This presentation reports the current ideas to
solve the problem of moving the ITS services out
of the PMD acceptance cone - To fit in the existing installation procedure,
the chariot supporting the ITS and FMD services
is made of two, upper and lower, halves - There are still 4 identified open problems, which
will be described in details therefore the
present procedure should not be considered as a
finalized design
L.Simonetti
2Y-Z plane cut-view of the ITSFMD services and of
their support chariots
Cylindrical section of the service chariot
Conical section of the service chariot
Fixation between conical and cylindrical sections
of the service chariot
Clearance between the TPC and the service chariot
1st patch panel for ITS FMD
Fixation of the service chariot to the TPC
service wheel
TPC cone
Support of 1st patch panel (fixed to the
cylindrical section of the service chariot)
2nd patch panel
PMD
Maximum radius of ITS services support to allow
for TPC sliding-in
Temporary cylindrical support of the movable
section of the services
ITS rails
beam axis
Int. Point
3Interferences with the PMD
- The minimum clearance with respect to the TPC
thermal screen (20mm), - the radial thickness of the services (50mm),
- the presently estimated thickness of the conical
section of the chariot (30mm), - seem to limit the opening angle of the services
to 11.6º
11.6º
4Axonometric view of the service trays (upper half
chariot)
2 lowered cable trays to allow the TPC sliding-in
(room for the tools used for hanging ITS to the
TPC)
Fixed cylindrical section of the ITS FMD
services
TPC
1 out of 11 cable trays per quadrant
ITS
Hinges of the cable trays 1st problem they
require flexible pipes (plastic or metal bellows)
and prevent tight fastening of cables
- Movable section of the ITS FMD service trays
- cylindrical during TPC sliding-in
- conical when TPC is on Int. Point
5View of the support chariot and of its tools
Cylindrical support of the 1st patch panel for
ITS and FMD services (fixed to the cylindrical
section of the ITS-service chariot)
Tool to lift the whole chariot in cantilever mode
by pushing onto the TPC service wheel
Cylindrical section of the service chariot with
its wheels
Conical section of the service chariot with its
wheels
Tools to link the base plane of the conical
section with the plane of the TPC service wheel.
It also lifts the outer end of the chariot.
Temporary cylindrical support of the (closed)
service trays, with its wheels rolling on ITS
rails
Temporary arms supporting the conical section
onto the ITS rails
6View of ITS FMD services assembled onto the
whole support chariot
7Chariot installation step 1
1st patch panel for ITS FMD
- In laboratory, for both the upper and lower
half-chariots - Services are assembled into their trays
- Fixed section of the trays are assembled onto the
chariot cylindrical section - Movable section of the trays are fixed to the
temporary cylindrical support
Support of 1st patch panel (fixed to the
cylindrical section of the service chariot)
8Chariot installation step 2
TPC Service Support Wheels (SSW)
TPC
- Both the upper and lower (not shown)
half-chariots are mounted onto the ITS rails and
slid through the TPC - Services are then connected to ITS and FMD at the
1st patch panel
9Chariot installation step 2 (cut view on Y-Z
plane)
TPC
RB26 TPC SSW
280 mm
160 mm
C3 and C4 fixation points of ITS rails
10Chariot installation step 3
- The TPC slides to the nominal position
beam pipe chariot
vacuum valve with its chariot
11Chariot installation step 4
- For both the upper and lower (not shown)
half-chariots - the conical section of the chariot is slid in
- with appropriate tools it is bolted to the
cylindrical section
12Chariot installation step 4 (cut view on Y-Z
plane)
RB24 TPC SSW
TPC
430 mm
320 mm
13Chariot installation step 5
- Two adjustment tools with hinges, mounted on the
conical section, are used to find the effective
position of the TPC SSW and, then, to bolt the
conical section to the SSW. - They allow to require an SSW positioning accuracy
of ?2mm
14Chariot installation step 6
- The service trays are opened and fixed to the
conical section of the upper and lower chariots - The temporay cylindrical support of the service
trays are removed
15Chariot installation step 6 - problem
- The service trails are opened and fixed to the
conical section of the chariot.2nd problem the
trails nearest to the horizontal plane clash with
the C4 support of the ITS rails - 1 trails out of 11 should be removed and the
services redistributed into 10 trays feasibility
to be verified.
C4
16Chariot installation step 7a
- The third support-point of the beam pipe is fixed
by means of the usual 4 wires and collar3rd
problem the procedure to execute this step has
not yet been completely defined. In particular - Fixations of the wires to the TPC face (which has
good positioning accuracy) have to be agreed
upon with the TPC group (for both the position
and the compatibility with the 400 N wire
tension preliminarily requested by the beam pipe
group) - Space between two cable trays has to be provided
for the wire feed-through - Angles of the wires have to be agreed upon with
the beam pipe group
17Chariot installation step 7b
- The chariot of the beam pipe and the one of the
vacuum valve are removed
18Chariot installation step 8
- The upper and lower chariots are raised in
cantilever mode by using the tool (1), pushing
onto the TPC SSW, and by exploiting the hinges
included in the tools (2)4th problem The
stiffness of the TPC SSW has to be verified
together with the TPC group
19Chariot installation step 9
- The ITS rails are removed
20PMD installation