Title: The Practice of Generation Schedule in China Power Market
1CHINA ELECTRIC POWER RESEARCH INSTITUTE
The Practice of Generation Schedule in China
Power Market
Dr. Xiaomin Bai China Electric Power Research
Institute bxm_at_epri.ac.cn
2007-09-19
21. The Status of Power Systems 2. Reform
Procedure 3. Generation schedule method
3System Interconnection
1.1 The Status of Power Systems
NE
AC
NC
XJ
DC
NW
AC
SD
AC
Back to back
Back to back or DC
Back to back
CC
SC
EC
3DC
AC
AC
DC
DC
XZ
Back to back
SC
FJ
sea cable
HaiN
41.2 2004 Max Demand of 7 major systems
Max Demand 285120 MW
51.3 Capacity and yearly Increments
Install Capacity GW
Increment of Capacity
61.4 Major Benchmarks of Generation Capacity
1987 -- 100GW 1995 -- 200GW (1996 Rank 2 in
the world ) 2000 -- 300GW 2004 -- 400GW 2005
-- 500GW 2006 -- 622GW
71.5 Power system development
- The power industry grows in a very fast rate, by
the end of 2006, the total installed generation
capacity reached 622GW,the total annual energy
production reached 2,834.4 TWh ( increased
13.4), both ranked second in the world. - However, China has experienced both energy
surplus and energy shortage in the history.
During 1997-1999, the power capacity in China was
so much that some plant had to shut down half of
their units. - On the other hand, in 2003-2005 China has been
suffered by energy shortages, 26 provinces had to
shed load in the worst situation. - Since large amount of generation plants will be
installed, we expect the energy shortage problem
will be alleviated in 2007.
81.6 Power Systems development
Main reason is owing to the peak demand can not
be satisfied during some periods in some
regions. In year 2003, installed capacity
increased 7.8, however the power demand
increased 7.6 more than the capacity. The
situation of power supply shortage continues in
year 2004. The investment of generation speed up
obviously. The installation of Capacity expected
to increase around 30GW40GW each year. In fact,
it was 65GW in 2005 and 100GW in 2006. The target
of 950GW in 2020 can be reached earlier than
expected.
92.1 Reform Procedure
- Started deregulation in late nineties. 6
provincial power markets were in trial operation
in 1999-2000. Their experience were useful for
further development. - In 2002 an order was issued for power industry
reform. Restructure of Chinese power sector has
been completed in 2003. SGCC, CSGC and 5 power
generation groups are formed, 5 regional grid
companies are established in the SGCC. - Regional grid companies are required to establish
regional Electricity Dispatch and Trading
Centers. In 2004 NE China and E China has
established their dispatch and trading center
and in trial operation, other centers will be
established in 2-3 years.
102.2 Generation status
- The rational of total of 5 generation groups is
38.79 - Other central government controlled enterprise is
about 10 - Local government controlled enterprises is 45
- IPP is 6.21
- Most of units are state owned and controlled, it
is about 90?
112.3 Transmission and Distribution systems
- provincial level 31, regional level 7, monopolize
controlled by SGCC 80 and CSGC 20. - district and county level 3211, most of them are
controlled by SGCC and CSGC. - hierarchical controlled system 5 level, one
national control center, 6 regional control
center, 28 provincial center (except
Beijing,Tianjin, Tibet), about 3000 district and
county center. - 10kV and above customers are reached 1M
122.4 System Install and Load Balance Status
94-97 simulation
98-01 Pilot Provincial
02-simulation Regional PM
132.5 System Install and Load Balance Status
alleviated
Still experience shortage
Serious Energy shortage
2004
2005
2006
2007
0115 NE-PM
Energy saving dispatch
0403 EC-PM
04 SC-PM
CC-PM Construction.
NC, NW PM Research
142.6 regional power market
- NE China Grid Company has been the first regional
power market in China, it is characterized as a
sole wholesale power market in the region. - The second regional power market is East China,
it is characterized as a hierarchical power
market, in which provincial power markets would
coexist with regional power market. - Other regional power markets will fall into
either NE mode or East China mode.
152.7 North China Power Market
- By the end of 2002, capacity of the region is
39400MW,with hydro 5410MW,about 13.7,thermal
33990MW,about 86.3?peak unit, frequency adjust
units and security reserve units is
4282.5MW,about 11.10. - The installed capacities for different Generation
groups 5 groups 19429.5MW,50.35. Huaneng
5025MW,13.02 Datang1925MW,4.99Huadian
5757MW,14.92Guodian 3261.5MW,8.45Zongdiantou34
61MW,8.97. - By the end of 2005, capacity of the region is
43840MW,with hydro 5780MW,about 13.7,thermal
37730MW,about 86.3?Wind power 340MW.
162.8 The Main Features of NE
- Initiated simulation operation on Jan. 15, 2004
- Unified control system for the regional system,
the three provincial system are considered as
settlement center - Annual and monthly bidding for generations are
tested. - Three stages for the market model single buyer
model, 20 of total generation competition, two
part tariff and full generation competition, in
the future, one part tariff and full generation
competition,
172.9 East China Power Market
- In end of 2006, capacity of the region is
97184.1MW,with hydro 1234.45MW,about 12.7,
thermal 7748.84MW, about 79.7,others 7.55,
including wind, pump, nuclear and gas turbine. - 79 utilities with 229 units, the differences of
installed capacities for Generation groups are
not too much, the largest group, Zhejiang energy
group 12.3
182.10 Installed Capacity EC
192.11 East China Power Market
- Initiated simulation operation on May 2004
- 171 registered units, 59 power plant, bid for
power, others (41 unit maintains, 21 without
bidding systems and 3 do not attend competition),
43388MW , about half of total capacity.
Provincial system buy power from regional market.
About 10 generation is settled according market
price. Partial generation competition, 85 annual
contract, and 15 by competition. - Trial operation on April 2006
- 221 registered units belong to more than 70
utilities, 156 of them bid for power, 60000MW,
Full generation competition plus CFD model. About
10 generation is settled according market price.
202.12 The Main Features of EC
- Regional market system, the three provincial
systems are considered as settlement center. - Provincial systems act as buyer to purchase
generation from regional control center. - Mainly contract trading, auxiliary spot trade.
Annual and monthly contract bidding, day ahead
spot market and real time system balance. - Regional trade center and provincial settlement
center, monthly contract bidding performed at
regional trade center, annual contract and real
time balance are performed in provinces
respectively. - Initial stage market model single buyer model,
20 of total generation competition, two part
tariff and full generation competition, are
considered in the future.
212.13 The Main Differences
- North China system mode annual and monthly
trading, full generation competition, two part
tariff. - East China system mode annual contract and
monthly trading, day ahead trading, full
generation competition, however only part of
generation are settled according to biding(90 by
approved price, 10 by competition, one part
tariff.
22Main feature of 3 Power markets
23Main feature of 3 Power markets
243. Generation Schedule Methods
- The 11th five years national plan, energy
consumption of the unit GDP and pollution would
decrease 20 and 10 respectively compared with
year 2005. - Two important dispatch ideas along with the
limitation of small units, and economic dispatch
method - Generation right trading
- Energy saving dispatch method
253.1 Generation Right Trading
- Small units (capacity less then 100MW) has
reached 115 GW in China. The average coal
consuming for 25MW units is more then
500-510g/kWh, but the average coal consuming of
generator with the capacity more then 600MW is
only 350 g/kWh. - Shunt down small units for energy saving and
environment protection - The ongoing dispatch method is based on
generation hours determined according different
units. It may cause some problems. to solve the
problem of un-economic results owing to
generation bidding. - Generation right trading is to adjust the
generation allocation among different units
263.2 Generation Right Trading
- Two ways for generation right trading
- Small units negotiate with large units to
transfer its generation rights based on the
market rules. - Automatic generation right transfer, that is, in
order to perform scheduled generation amount or
contract quantity, when the market clearing price
is lower than that of the contract, buy the
generation from the market, it own units are
shutdown, therefore the high efficiency units can
generate more. - The main features of generation right trade
- Generation resources configuration optimization
- Promote the shunt down of the small units and
proper compensation for the staff of small units - Energy saving and cost reduction. with the
transfer of generation rights trade, the
efficient thermal units and hydro units can gain
more generation amount which is benefit for
environment and utilize of renewable energy
sources.
273.3 Energy saving dispatch method
- Proposed in Aug.28, 2007.
- Units are dispatched according to the priority
within provincial system, and optimized within
the regional system, and will be coordinated
amount regional systems. - The principle of the method energy saving,
environment protection and economic. According
the determined priority, the units are
dispatched. First for renewable energy, then
synthesized energy utilization units, then the
coal units based their cost and pollution level.
Wind power, solar power, tide power, hydro power,
biologic power and nuclear power are dispatched
in high priority. - The thermal power units are dispatched according
marginal cost of coal consumption. Parts of
provincial system are selected for trial
operation. will be promoted after the experiences
are obtained.
283.4 Energy saving dispatch method
- The priority of the generation for different
units - Wind power, solar power, tide power, hydro power,
etc. the renewable units without adjust
capability. - hydro power,biologic power and earth thermal,
etc. the renewable units with the adjust
capability and waste generation units satisfied
environment requirements. - nuclear power
- cogeneration units, generation according to
thermal requirements for generation, and the
units using the abundant thermal, gas, pressure
synthesized utilization generation units. - nature gas and IGCC units
- other thermal units, including cogeneration units
without thermal load - Oil units
- The same type units are ranked according to unit
consumption of energy cost, the same level unit,
the lower of the pollution, the higher of the
priority - The generation price is not changed temporarily..
293.5 The meaning of the method
- Energy saving dispatch plus closed 50GW small
units, it is expected that the saving of the coal
for each year before 2010 is about 90M ton,the
associated emission of SO2, CO2 and NOx can be
reduced greatly. - The generation hours for low efficiency and high
pollution units should be reduced. Small units
and oil units may face the difficulty to run for
generation. The modern high efficiency large
units may have higher utilization rate.
30- Since energy resources are concentrated in the
western part of China, and most industrial areas
are located in the eastern part of China, huge
blocks of power will be transmitted from the west
to the east via long distance transmission
corridors.
31- Two important things may affect power system
pattern and its perspective of power market - By installing more generation and transmission
lines and limiting of investment for energy
intensive industries as well as by implementation
of various demand elasticity measures, it is
predicted that the energy shortage problems will
be alleviated by 2006-2007 (rate of progress). - The construction of Ultra-high voltage
transmission line and system (system management
pattern).
32An example for market price
33The market price
- NC market
- 2005.5 month competition, 27plant, bidding
generation 3785 MWh for the generation of
1884MWh. The average 270.092 / MWh - EC market
- Generation biding by units, 96 time periods, 10
section generation bidding for each time period. - Market clear price just higher than marginal cost
of average cost of the generation untilitis. - Price for generation of 5 generation groups
317.93 /MWh, Transmission and distribution 153.4/
MWh, 30.72 of sale price,the average sale price
is 499.04/ MWh,uplift funds not included, average
27.83/ MWh)
34(No Transcript)
35Contract price and competition price
The market clearing price for competed generation
may different from contract price, higher or
lower. For example in Longjiang system, the
average power generation for competition is
3270MWh. Contract price RMB300.74/MWh, competed
generation price is RMB111.5/Mwh. The price for
generation in competitive market may higher than
the times compared with the cases in normal
system operation.
36Contract allocation method may affect competition
results Allocate contract generation with the
rate of load demand
37Contract allocation method may affect competition
results Allocate contract generation by
optimization
?????????????
38Thank You Dr. Xiaomin Bai China Electric Power