Title: BalloonWinds Update Straight to Launch
1BalloonWinds Update--Straight to Launch--
- James M. Ryan
- University of New Hampshire
2BalloonWindsInstrument Overview
Size 8x8x12 Gondola Mass 6000 lbs Power
Requirements 1300 W Power System 26 Lithium-Ion
Batteries Thermal Management Ice and Electric
Heaters Optical Systems Diode-Pumped
NdYAG ½-meter Telescope Direct-Detection
Receivers (2)
3Gondola and Control
42007 TVAC Failure
5Chamber Reviews
- Laser Chamber
- Material 6061-T6 Aluminum
- Volume (empty) 10 cubic feet
- Design Pressure 18 psig
- Test Pressure (Hydrostatic) 28 psig
- Assembly Test Pressure (Pneumatic) 22.5 psig
(1.5? MEOP) - Interferometer Chamber
- Material 304L Stainless Steel
- Volume 14 cubic feet
- Design Pressure 16.5 psig
- Assembly Test Pressure (Pneumatic) 22.5 psig
(1.5? MEOP)
6Chamber Reviews (cont.)
- Coolant Tank
- Material 304L Stainless Steel
- Volume (empty) 18 cubic feet
- Design Pressure 18.75 psig
- Test Pressure (Hydrostatic) 28 psig
- Assembly Test Pressure (Pneumatic) 22.5 psig
(1.5? MEOP) - Electronics Chamber
- Material 304L Stainless Steel
- Volume (empty) 30 cubic feet
- Design Pressure 18.75 psig
- Test Pressure (Hydrostatic) 28 psig
- Assembly Test Pressure (Pneumatic) 22.5 psig
(1.5? MEOP)
7Schedule Delay
- AFRL postponed environmental tests
- Schedule slip by the preceding instrument
- Fixed schedule for the succeeding instrument
- Test window closed
- 6-month slip in launch schedule with rescheduled
test date TBD
8Rescheduling Process
- 2-week window emerged in July-August
- New TVAC Facility cleanliness requirements
- Assessment began
- Flowdown from new requirements
- Risk risk reduction
- Impact of risk-mitigation
- Environmental test objectives
9TVAC Facility
- Large investment in facility for two optical
payloads - Class-100 inside TVAC chamber
- Class-100 outside TVAC chamber
- Select material list
- No particulates
- No liquids or volatiles
- No silicone-based materials
10Flowdown from New Requirements
- Meticulous cleaning of gondola
- Prepare comprehensive material list
- Removal or encapsulation of forbidden materials
- Vacuum grease
- Coolant
- Insulation
- Wood
11Risk Risk Reduction
- Facility contamination was primary risk
- Risk reduction measures included
- Bagging gondola
- Reduced altitude simulation
- Reduced temperature range (tropopause)
- All support equipment located outside facility
- No schedule or admittance guarantee after
completion of all known requirements
12Impact of Risk-Mitigation
- Gondolas thermal properties different from
flight configuration - T-P profile not representative of flight profile
- Consumable state and burn rate not representative
of flight - Limited to one cycle. 2nd cycle logistically
impractical.
13Environmental Test Objectives
- Verification of thermal system operation
- Heating/cooling capacities (duty cycles)
- System performance (temperatures vs set points)
- Time required to equilibrate at final altitude
- Revelation of impacts on opto-mechanical and
detector systems - Laser Power, seeding, frequency tuning
- Telescope Motor control of focus adjustment
- Interferometer Alignment, stability, motor
control - Detectors Chip temperature, Gain, read noise
14Environmental Test Objectives (cont.)
- Estimation of Mission Duration
- Battery power burn rate knee shape
- Coolant system capacity knee shape
- Pressure chamber leak rates
- All impacted by risk mitigation efforts
- Test no longer matched with objectives
15Straight to Launch
- The new facility requirements
- Increased resource requirements
- Increased associated risk
- Decreased benefit of test
- Hindered original test objectives
- Environmental tests were cancelled
- Environmental test objectives rolled into flight
objectives
16Added Flight Objectives Procedures Impacts
- Verification of thermal system operation
- Monitor temperatures and heating/cooling duty
cycles - Modify temperature set points to counteract
temperature and/or duty cycle issues - Raw data will be unusable until thermal
stead-state is attained and the interferometer is
aligned
17Added Flight Objectives Procedures Impacts
- Revelation of impacts on opto-mechanical and
detector systems - Monitor laser power, spectral widths, optical
transmissions, photometric return, etc - Remote adjustments performed to reduce the impact
- Raw data black-outs will occur during such
adjustments
18Added Flight Objectives Procedures Impacts
- Estimation of Mission Duration
- Capacity for an 8-hour mission will be assumed
- Monitor battery bus voltage, coolant temperature
and chamber pressures - Cut-down will be initiated if the following value
estimates are reached - Bus voltage limit- 25V
- Output manifold temperature- 4C
- Chamber pressure limit- 0.8 atm
19Advantages of Not Testing
- Schedule contingency
- Released resources
- Reduced risk of mishandling
20Revised BalloonWinds Schedule
21Additional
22Laser ChamberPre-Failure
Cross-supports
29?47?½-inch lid (0.35-inch eff. thickness)
23Laser ChamberPost-Failure I
Cross-supports
Secondary fractures from gondola impact
Lid bottom
Thermal insulation (yellow)
24Laser ChamberPost-Failure II
Cross-support
Secondary fractures from pipe interference
Lid bottom
Fibertek Laser
25Laser ChamberPost-Failure III
Reverse angle showing the disorder
26Laser ChamberPost-Failure IV
Fragments at the bottom of the thermal-vacuum
chamber