Cleanroom DesignBuild - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Cleanroom DesignBuild

Description:

Cleanroom Design-Build. Charles Davidson. Columbus, Ohio ... Construction/Project Costs $3.6 million. Lab Equipment, Tools, Furniture ... air grille filter ... – PowerPoint PPT presentation

Number of Views:84
Avg rating:3.0/5.0
Slides: 12
Provided by: michel121
Category:

less

Transcript and Presenter's Notes

Title: Cleanroom DesignBuild


1
Cleanroom Design-Build
  • Charles Davidson
  • Columbus, Ohio

2
Project Team Charles Davidson Project
Manager Hodess Building Co. Construction BHDP
Architect Vanderweil Engineers
Engineering AdvanceTEC, LLC Cleanroom
Specialists Duration April 2001 November
2002 Cost Construction/Project Costs 3.6
million Lab Equipment, Tools, Furniture 1.8
million Total 5.4 million
3
Cleanroom Layout
Building 13
M O D U L A R C L E A N R O O M R E N O V A
T I O N
Class 100 Class 1,000 Class 10,000 Office
Support Mechanical Electrical
The 9,200-square foot Cleanroom in Building 13-0
went from design to build to tool hook-up to
move-in and operational status in about 15
months. It includes approximately 1600 sf of
mechanical and electrical support space 2200 sf
of office, bulk utilities, prep area, washroom,
and storage space and 5400 sf of cleanroom area.
4
(No Transcript)
5
(No Transcript)
6
Execution
Work started with asbestos abatement and
demolition by in-house crews in April 2001. The
conceptual design and rough order of magnitude
cost was completed in early May, followed by
preliminary drawing for review by staff in early
July. By mid-July drawings were submitted for
permitting, and construction was under way by
mid-August. The installation of quick response
sprinkler heads followed the establishment of
Protocol Level 2 and perimeter sealing in early
January. The intake airway was completed in early
February following establishment of Protocol
Level 3 and perimeter sealing. Process piping
analytical testing was completed by the last week
of February and the City of Columbus conducted
its final inspection on March 18. Final
occupancy permit was received on May 24 and staff
began move-in on June 26. The Cleanroom was
operational the following week, with final tool
hook-up completed before mid-August.
Miscellaneous concerns extended into late
December.
7
Total Square Feet 9,200 sf
  • 1,600 s.f. of Mechanical and Electrical support
    space
  • 2,200 s.f. of Office, bulk utilities,
    prep-area, washroom, storage
  • 5,400 s.f. of Cleanroom
  • Class 100 1,000 s.f.
  • Class 1,000 2,100 s.f.
  • Class 10,000 2,300 s.f. (primarily maintenance
    access)

8
Timeline 15 Months
  • CM contracted to perform Design-Build on or about
    4/4/01
  • Submitted Drawings for Permitting on or about
    7/11/01
  • Protocol Level 3 established on or about 1/23/02
  • Obtained Temporary Occupancy Permit on 3/19/02
  • Research group started Move-in on 6/26/02
  • Research Operational on 7/3/02

9
Total Cost 5.4 Million
  • Construction/Project Cost 3.6 Million
  • Includes 167K of In-house Coordination and
    In-house PM
  • Includes 725K of AE, PM, General Conditions,
    and CM Fee
  • Includes 140K of Demolition Costs
  • Includes 426K of Bulk-heading and Tool Hook-up
    Costs
  • Includes 47K of Interest Capitalization
  • Research Equipment, Tools, Furniture Costs
    1.8 Million
  • Furniture cost primarily for Wet Benches and
    Spray Coat Hoods

10
Lessons learned
  • DI water
  • Process cooling loop
  • FM approved FRP ductwork
  • Orbital welded stainless steel process piping
  • Estimated energy costs vs. actual
  • Vacuum system static issue w/hose and connection
    ports
  • Light Levels lamp type, amber lens/sleeves
  • Return air grille filter frames
  • Tool drops vs. Standards/Sticks Racking vs.
    Bulk-Heading vs. Final Tool Hook-up
  • Multiple issues with CM and their subs from out
    of state
  • Neutralization System Current new issue

11
Bldg 13-0 Cleanroom Project
  • Battelle Facilities contracted with Hodess
    Building Company for a turn-key Design-Build.
    Hodess contracted with Vanderweil Engineers,
    Inc., BHDP Architecture, and AdvanceTEC, LLC.
  • Tom Sens with BHDP was Battelles preferred
    architectural consultant on site
    (1-513-271-1634).
  • Declan O'Riordan was our primary contact at
    Vanderweil Engineers, Inc. (1-617-423-7423) and
    is very knowledgeable with regard to the
    engineering disciplines.
  • The real expert regarding Cleanrooms is Tim
    Loughran with AdvanceTEC, LLC (1-804-378-1550).
    If planning on building a Cleanroom, Tim should
    be the first person contacted.
    www.advancetecllc.com lthttp//www.advancetecllc.co
    m
Write a Comment
User Comments (0)
About PowerShow.com