Title: ESA Iris Programme workplan of activities


1
ESA Iris Programme workplan of activities
franco.ongaro_at_esa.int nathalie.ricard_at_esa.int
claude.loisy_at_esa.int
2
SESAR schedule vs Iris schedule
3
Objectives of Iris (ARTES 10) Phase 1
  • Emphasis on
  • Preparation work to support the preparation of
    the SESAR Master Plan
  • Initiate development of the communication
    standard
  • Initiate identification of the satellite system
    architecture
  • Consider non-technical issues from the start
  • Business case
  • Service provision and governance model
  • ESA hand-over after development/deployment
  • Validation and qualification with SESAR
  • Support frequencies allocation
  • Phase A activities timing is aligned with SESAR
    ATM Master Plan release

4
(No Transcript)
5
Communication System Design activity
  • The activity includes
  • Trade-off of existing and possible new standards
  • Analysis and consolidation of user requirements
  • Communication architecture design
  • (incl. security requirements, handover
    procedures with terrestrial network)
  • Interfaces with SESAR terrestrial network
  • (incl. interfaces at physical and networking
    layers)
  • Design of associated hardware and software,
    development, validation and qualification
    procedures.
  • Software simulator for validation
  • Preparation of ICAO standardisation and
    certification activities
  • (Incl. support of ESA-Eurocontrol working group
    set-up to share
  • information on the future standard with
    non-European ICAO Members)
  • Preparation of ICAO standard (technical basis
    and international support)

6
Analysis and Definition of Satellite System
  • The activity includes
  • Analysis and consolidation of user requirements,
    including existing or projected commercial ones,
    and needs for possible ancillary services
  • All trade-offs on architecture, payload,
    platform, ground segment, deployment and
    operations schemes and provision of possible
    ancillary services
  • Assessment of the business case for the provision
    of services
  • Analysis of integration into SESARs overall
    infrastructure
  • Transfer of responsibilities between ESA and
    SESAR
  • Certification issues regarding the operators and
    operation of the satellite system
  • Definition of the operational responsibilities
    and liabilities.
  • Prepare all elements to define the satellite
    service provision

7
Conclusions
  • ESA mandate to support the adoption of satellite
    solutions where justified and for the benefit of
    the European Union policies
  • Justified means a solid cost/benefits case, not
    technology for the sake of technology
  • Although SESAR is the foundation of the
    programme, is very clear that we need to act
    regional but think global we count on this
    group, and possibly a dedicated subgroup to help
    us identify the best new communication standard,
    open and standardised at European and ICAO
  • In waiting for the SESAR JU to fully take its
    system architect role, we are counting on the
    support of an Expert group including Eurocontrol,
    ANSP's, EASA and aviation representatives to help
    us refine our system requirements
  • Our next milestones are the ATM Master Plan and
    our own Ministerial Conference at end 2008.
    Meanwhile the Invitation to Tender for the Ph A
    studies have been issued last week, with KO
    expected in December.