Title: Nodal Program Update


1
Nodal Program Update
  • Mike Cleary
  • Sr. VP and Chief Technology Officer

2
Agenda
  • SEM Go-Live
  • Program Planning
  • Nodal Applications
  • Integration Testing
  • Traceability
  • Market Readiness

3
Nodal Timeline
4
Nodal Program Planning
  • Ground-Up Analysis to Determine Remaining Work
  • People, processes, technology
  • Ensure program has effort-based, resource-loaded,
    integrated and dependent work plans
  • SEM Go-Live (NMMS)
  • Integration/Go-Live
  • Readiness/Market Trials
  • ERCOT Readiness
  • Future Measurements
  • Earned Value effort based on remaining work

5
Nodal Program Risks
  • Program risks to be prioritized by temporal order
    as they pertain to next major market deliverable
  • October market trials
  • Subsequent functional deliveries for MP testing
  • General programmatic risks, proposed mitigations
    and impact assessments
  • Included in daily PMO discussions
  • Escalated to marketplace when needed
  • For example
  • CMMs delivery status would have low impact to
    current program deliverables
  • Issues related to Web Services would have
    relatively high impact

6
Risks Issues to Achieving Nodal Go-Live
  • High (Potential Show-Stoppers)
  • Risk Reconciling protocols, systems and market
    expectations
  • Medium (Mitigation Plan in Place)
  • Issue Resource constraints for Nodal Program
  • Risk Data Center capacity concerns
  • Low (Mitigation Plan in Place, No Impact to
    Go-Live)
  • Issue Handling CMM delays for program
  • Risk Integrity of network model data from market
    participants

7
Nodal Applications
  • Final Applications Delivered
  • MMS 5
  • Completed FAT Aug. 21
  • 11 of 14 interfaces completed Level 2 testing
  • Market Manager UI addressing defects in iTest
    through Aug. 31
  • CMM 4.1
  • All major issues addressed and key risks
    mitigated
  • Exited FAT Aug. 21
  • 5 of 6 interfaces currently in iTest
  • Vendor re-work has pushed Twelve Trailing Month
    to Aug. 31
  • Phase II (CMM 4.2) targeted for Feb. 10, 2010
  • No impact to End-to-End schedule

8
Integration Testing Status
  • Less Deferred count (items that cannot be
    tested in the iTest environment
  • Target Completion
  • Levels 1 2 ? September 22, 2009 On Target
  • Level 3 ? November 13, 2009 On Target
  • Risks Issues

9
Market Verification Update
10
Traceability Status Update
11
Market Readiness Update
12
Questions ?
13
Appendix
14
Market Systems Update
15
Reliability Systems Update
16
Market Verification Update