Title: Measurement, Verification,
1- Measurement, Verification,
- and Commissioning
2Why You Need MV
- To assure yourself that the project is performing
as expected - To report achieved savings to HUD
- To assure savings persistence
- To verify a savings guarantee or calculate the
ESCO payment - To establish basis for savings adjustments if
needed
3MV Needs to Address 3 Things
- How baseline of energy use or costs will be
established - How energy savings after project installation
will be determined - How the baseline will be adjusted if large
changes in the operation of the building occur
after project installation
4The Concept of MV Can be Simple
- For Example
- Average of energy bills for last 3 years gives a
baseline of energy use or energy costs - Compare energy bills after project installation
to baseline to determine savings - If large changes in the operation of the building
occur, it may be necessary to adjust the baseline
5Measurement and Verification Steps
- Pre-ECM Installation
- Establish baseline energy use established with
most recent 3 years of utility data (usually the
rolling base for contract) - Verify baseline conditions occupancy patterns,
vacancy rates, equipment usage - Determine appropriate MV methodology to use and
necessary details for data collection and
reporting
6Measurement and Verification Steps (cont.)
- Post-ECM Installation
- Verify installation and correct operation
- Verify ongoing potential to generate savings
- Adjust baseline energy use for material and
weather changes, if necessary - Quantify post-installation energy use
- Quantify energy and cost savings
- Report savings to HA on monthly or quarterly
basis (annually to HUD)
7Elements of Savings Determination
ECMs Installed Here
2) Baseline or Adjusted Baseline
1) Baseline
Energy Usage
Contracted Savings
3) Post-ECM Performance
Apparent Savings
Time
8Definitions
- Baseline mutually agreed upon, calculated or
measured energy use and cost, usually an average
of most previous 3 years of utility data - Post-ECM performance post-ECM calculated or
measured energy use and cost - Adjusted baseline adjustments due to changes
beyond the ESCOs control, such as - Occupancy, equipment loading or efficiencies, or
building usage changes - Set point changes
- Physical changes to a building
- Weather
9Definitions (cont.)
- Adjusted baseline adjustments due to changes
beyond the ESCOs control, such as - Occupancy or building usage
- Set point temperatures or scheduling
- Physical changes to building envelope or
structure - Weather conditions
- Equipment loading and/or operating efficiency
- Recent maintenance work that affects equipment
operation or performance - Utility rate adjustment
10Calculating Savings
Baseline
Apparent Savings
Measured/ Calculated/ Stipulated Post-ECM Performa
nce
Measured/ Calculated/ Stipulated Post-ECM Performa
nce
Contracted Savings
Adjusted Baseline
11Use Standard MV Protocols
- International Performance Measurement and
Verification Protocol (IPMVP, formerly NEMVP) - The general guideline a living document
- 1-800-DOE-EREC or http//www.eren.doe.gov
- Federal Energy Management Program (FEMP) MV
Guidelines - Application of IPMVP for federal sector
- 1-800-DOE-EREC or http//www.eren.doe.gov
- American Society of Heating, Refrigeration and
Air Conditioning Engineers (ASHRAE) Guideline 14 - Technical foundation
- http//www.ashrae.org
12MV Options
- A - Estimate performance operation by ECM
- B - Measure performance operation by ECM
- C - Measure combined performance/operation for
whole building or site - D - Calibrate a model to Option B and/or C data,
estimate performance operation
13MV Options Cost vs. Accuracy
Customer and ESCO balance cost and accuracy
14MV Reporting Requirements
- Submitted monthly or quarterly (reports should
clearly indicate performance period) - Data from reports will be used for annual
reconciliation with HUD (ensure that all
necessary data is available) - ESCOs should review reports quarterly with
appropriate HA representative and request written
acknowledgement/acceptance of report from HA - Reports should have a summary page of savings
followed by details on approach used,
assumptions, data sources, and calculations
15MV Reporting Requirements (cont.)
- Reports should thoroughly document baseline
adjustments, modifications to ECMs and resulting
savings impacts, duration of impacts, and
reasoning for variations in performance - ESCOs should provide contact information for MV
inquiries by HAs - Both cost and energy savings should be provided
for each measure, where appropriate - Details on changes in utility costs should be
provided
16MV Lessons Learned
- Pick the right option(s)
- Balance cost, accuracy, and technical
appropriateness - Baselines
- KISS (keep it simple stupid)
- If you have historical data, use it
- If not, collect what you need during project
development - Address baselines for every budget on the table
- Energy, maintenance, etc.
17MV Lessons Learned (cont.)
- Energy savings determination
- KISS (keep it simple stupid)
- Live up to your obligations (e.g., baseline
adjustments) - Establish means of addressing unreported material
changes and other savings disputes
18Three Keys to Successful MV
- Keep it as simple as possible
- (1) It does need to provide a reasonable basis
for determining the savings from your particular
project - (2) It does need to provide a reasonable basis
for verifying guarantees or determining payments - (3) It does not need to do more than (1) and (2)
19Retrofit Commissioning
- What is it?
- Systematic process that ensures that retrofit
systems are designed, installed, tested, and
capable of being operated and maintained
according to the owners needs - Insurance policy ensures owners that projects
will have expected (or higher) benefit-to-cost
ratios and that buildings are safe and comfortable
20Performance Frustrations
- 1994 study of 60 existing buildings
- 50 suffered from control problems
- 40 had problems with HVAC equipment
- 33 experienced sensor malfunction
- 25 had inoperable EMCS, economizers, and/or
variable-speed drives - 15 were missing specified equipment
21Benefits of Commissioning
- Quality Assurance
- prevents problems from developing (fewer
maintenance headaches) - anticipates and regulates system interaction
- implements a method of meeting mechanical,
electrical, and control requirements (incl.
maintenance of equipment warranties)
22Benefits of Commissioning (cont.)
- Confirms Owners/Design Intent
- resolves design problems
- improves performance of building equipment
- improves interactions between building systems
- improves IAQ and occupant comfort
23TAB and Commissioning
- Testing, adjusting and balancing (TAB)
- adjustment of building air and water flows to
meet design specifications - does not ensure operational performance
(efficiency, control, system interaction) - a component of Commissioning
- Commissioning is broader in scope
- diagnostic tests collect operational data to
determine whether problems exist - functional tests apply procedures that may
reveal causes of problems (efficiency,
operational flaws)
24The Commissioning Team
- Building Owner or Owners Representative
- Commissioning Agent (ESCO Representative or 3rd
Party) - Designers
- Installation Contractor/Manufacturers
Representative - Building Operator
- Testing Specialist
25Commissioning Plan
- Drafted by Cx Agent (included in ESA), finalized
with input from Cx team - Addresses the following issues
- Scope or level of commissioning
- Commissioning schedule
- Team member responsibilities
- Communication, reporting, and management
protocols - Documentation requirements
- Detailed scope of testing
- Detailed scope of monitoring
- Recommended training format
26Design Intent Documentation
- Occupants assumed intention of the design and of
the operation of the building - Detailed explanation and documentation of ideas,
concepts, and criteria that define acceptable
building operation - Defined by bid specifications for each system
- The commissioning agent must ensure that actual
performance of the building meets the design
intent
27Design Intent Documentation (cont.)
- Addresses the following issues
- System description
- Objectives and functional use of system
- Occupancy requirements
- IAQ
- Performance criteria (efficiency, energy,
tolerances of IAQ) - Budget considerations and limitations
- Restrictions and limitations of the facilitys
systems
28Commissioning Costs
29Commissioning Costs (cont.)
30Must-Commission Retrofits
- Lighting control (daylighting, occupancy sensors)
- Energy management control systems/strategies
- Pneumatic equipment
- HVAC-related plant equipment
- Air-distribution systems