Measurement, Verification, - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Measurement, Verification,

Description:

If large changes in the operation of the building occur, it may be necessary to ... Verify installation and correct operation. Verify ongoing potential to ... – PowerPoint PPT presentation

Number of Views:92
Avg rating:3.0/5.0
Slides: 31
Provided by: IPD2
Category:

less

Transcript and Presenter's Notes

Title: Measurement, Verification,


1
  • Measurement, Verification,
  • and Commissioning

2
Why You Need MV
  • To assure yourself that the project is performing
    as expected
  • To report achieved savings to HUD
  • To assure savings persistence
  • To verify a savings guarantee or calculate the
    ESCO payment
  • To establish basis for savings adjustments if
    needed

3
MV Needs to Address 3 Things
  • How baseline of energy use or costs will be
    established
  • How energy savings after project installation
    will be determined
  • How the baseline will be adjusted if large
    changes in the operation of the building occur
    after project installation

4
The Concept of MV Can be Simple
  • For Example
  • Average of energy bills for last 3 years gives a
    baseline of energy use or energy costs
  • Compare energy bills after project installation
    to baseline to determine savings
  • If large changes in the operation of the building
    occur, it may be necessary to adjust the baseline

5
Measurement and Verification Steps
  • Pre-ECM Installation
  • Establish baseline energy use established with
    most recent 3 years of utility data (usually the
    rolling base for contract)
  • Verify baseline conditions occupancy patterns,
    vacancy rates, equipment usage
  • Determine appropriate MV methodology to use and
    necessary details for data collection and
    reporting

6
Measurement and Verification Steps (cont.)
  • Post-ECM Installation
  • Verify installation and correct operation
  • Verify ongoing potential to generate savings
  • Adjust baseline energy use for material and
    weather changes, if necessary
  • Quantify post-installation energy use
  • Quantify energy and cost savings
  • Report savings to HA on monthly or quarterly
    basis (annually to HUD)

7
Elements of Savings Determination
ECMs Installed Here
2) Baseline or Adjusted Baseline
1) Baseline
Energy Usage
Contracted Savings
3) Post-ECM Performance
Apparent Savings
Time
8
Definitions
  • Baseline mutually agreed upon, calculated or
    measured energy use and cost, usually an average
    of most previous 3 years of utility data
  • Post-ECM performance post-ECM calculated or
    measured energy use and cost
  • Adjusted baseline adjustments due to changes
    beyond the ESCOs control, such as
  • Occupancy, equipment loading or efficiencies, or
    building usage changes
  • Set point changes
  • Physical changes to a building
  • Weather

9
Definitions (cont.)
  • Adjusted baseline adjustments due to changes
    beyond the ESCOs control, such as
  • Occupancy or building usage
  • Set point temperatures or scheduling
  • Physical changes to building envelope or
    structure
  • Weather conditions
  • Equipment loading and/or operating efficiency
  • Recent maintenance work that affects equipment
    operation or performance
  • Utility rate adjustment

10
Calculating Savings
Baseline
Apparent Savings
Measured/ Calculated/ Stipulated Post-ECM Performa
nce


Measured/ Calculated/ Stipulated Post-ECM Performa
nce
Contracted Savings
Adjusted Baseline


11
Use Standard MV Protocols
  • International Performance Measurement and
    Verification Protocol (IPMVP, formerly NEMVP)
  • The general guideline a living document
  • 1-800-DOE-EREC or http//www.eren.doe.gov
  • Federal Energy Management Program (FEMP) MV
    Guidelines
  • Application of IPMVP for federal sector
  • 1-800-DOE-EREC or http//www.eren.doe.gov
  • American Society of Heating, Refrigeration and
    Air Conditioning Engineers (ASHRAE) Guideline 14
  • Technical foundation
  • http//www.ashrae.org

12
MV Options
  • A - Estimate performance operation by ECM
  • B - Measure performance operation by ECM
  • C - Measure combined performance/operation for
    whole building or site
  • D - Calibrate a model to Option B and/or C data,
    estimate performance operation

13
MV Options Cost vs. Accuracy
Customer and ESCO balance cost and accuracy
14
MV Reporting Requirements
  • Submitted monthly or quarterly (reports should
    clearly indicate performance period)
  • Data from reports will be used for annual
    reconciliation with HUD (ensure that all
    necessary data is available)
  • ESCOs should review reports quarterly with
    appropriate HA representative and request written
    acknowledgement/acceptance of report from HA
  • Reports should have a summary page of savings
    followed by details on approach used,
    assumptions, data sources, and calculations

15
MV Reporting Requirements (cont.)
  • Reports should thoroughly document baseline
    adjustments, modifications to ECMs and resulting
    savings impacts, duration of impacts, and
    reasoning for variations in performance
  • ESCOs should provide contact information for MV
    inquiries by HAs
  • Both cost and energy savings should be provided
    for each measure, where appropriate
  • Details on changes in utility costs should be
    provided

16
MV Lessons Learned
  • Pick the right option(s)
  • Balance cost, accuracy, and technical
    appropriateness
  • Baselines
  • KISS (keep it simple stupid)
  • If you have historical data, use it
  • If not, collect what you need during project
    development
  • Address baselines for every budget on the table
  • Energy, maintenance, etc.

17
MV Lessons Learned (cont.)
  • Energy savings determination
  • KISS (keep it simple stupid)
  • Live up to your obligations (e.g., baseline
    adjustments)
  • Establish means of addressing unreported material
    changes and other savings disputes

18
Three Keys to Successful MV
  • Keep it as simple as possible
  • (1) It does need to provide a reasonable basis
    for determining the savings from your particular
    project
  • (2) It does need to provide a reasonable basis
    for verifying guarantees or determining payments
  • (3) It does not need to do more than (1) and (2)

19
Retrofit Commissioning
  • What is it?
  • Systematic process that ensures that retrofit
    systems are designed, installed, tested, and
    capable of being operated and maintained
    according to the owners needs
  • Insurance policy ensures owners that projects
    will have expected (or higher) benefit-to-cost
    ratios and that buildings are safe and comfortable

20
Performance Frustrations
  • 1994 study of 60 existing buildings
  • 50 suffered from control problems
  • 40 had problems with HVAC equipment
  • 33 experienced sensor malfunction
  • 25 had inoperable EMCS, economizers, and/or
    variable-speed drives
  • 15 were missing specified equipment

21
Benefits of Commissioning
  • Quality Assurance
  • prevents problems from developing (fewer
    maintenance headaches)
  • anticipates and regulates system interaction
  • implements a method of meeting mechanical,
    electrical, and control requirements (incl.
    maintenance of equipment warranties)

22
Benefits of Commissioning (cont.)
  • Confirms Owners/Design Intent
  • resolves design problems
  • improves performance of building equipment
  • improves interactions between building systems
  • improves IAQ and occupant comfort

23
TAB and Commissioning
  • Testing, adjusting and balancing (TAB)
  • adjustment of building air and water flows to
    meet design specifications
  • does not ensure operational performance
    (efficiency, control, system interaction)
  • a component of Commissioning
  • Commissioning is broader in scope
  • diagnostic tests collect operational data to
    determine whether problems exist
  • functional tests apply procedures that may
    reveal causes of problems (efficiency,
    operational flaws)

24
The Commissioning Team
  • Building Owner or Owners Representative
  • Commissioning Agent (ESCO Representative or 3rd
    Party)
  • Designers
  • Installation Contractor/Manufacturers
    Representative
  • Building Operator
  • Testing Specialist

25
Commissioning Plan
  • Drafted by Cx Agent (included in ESA), finalized
    with input from Cx team
  • Addresses the following issues
  • Scope or level of commissioning
  • Commissioning schedule
  • Team member responsibilities
  • Communication, reporting, and management
    protocols
  • Documentation requirements
  • Detailed scope of testing
  • Detailed scope of monitoring
  • Recommended training format

26
Design Intent Documentation
  • Occupants assumed intention of the design and of
    the operation of the building
  • Detailed explanation and documentation of ideas,
    concepts, and criteria that define acceptable
    building operation
  • Defined by bid specifications for each system
  • The commissioning agent must ensure that actual
    performance of the building meets the design
    intent

27
Design Intent Documentation (cont.)
  • Addresses the following issues
  • System description
  • Objectives and functional use of system
  • Occupancy requirements
  • IAQ
  • Performance criteria (efficiency, energy,
    tolerances of IAQ)
  • Budget considerations and limitations
  • Restrictions and limitations of the facilitys
    systems

28
Commissioning Costs
29
Commissioning Costs (cont.)
30
Must-Commission Retrofits
  • Lighting control (daylighting, occupancy sensors)
  • Energy management control systems/strategies
  • Pneumatic equipment
  • HVAC-related plant equipment
  • Air-distribution systems
Write a Comment
User Comments (0)
About PowerShow.com