Title: 4M14E ENVIRONMENTAL IMPACT ASSESSMENT
14M14EENVIRONMENTAL IMPACT ASSESSMENT
2Recommended text books
- Wood, C. (2002). Environmental Impact Assessment
a Comparative Review (2nd Edition). Harlow
Prentice Hall - Therivel, R. and Partidário, M.R. (1996). The
Practice of Strategic Environmental Assessment.
London Earthscan - Glasson, J. Therivel, R. and Chadwick, A. (1999).
Introduction to Environmental Impact Assessment
(2nd Edition). London Spon Press
3What is EIA?
- an important procedure for ensuring that the
likely effects of new development on the
environment are fully understood and taken into
account before the development is allowed to go
ahead - (DETR and National Assembly for Wales, 1999)
4What is it really?
- Environmental Impact Assessment is a process, set
down as a repeatable series of steps to be taken,
to allow the environmental consequences of a
proposed development to be assessed. - The environmental consequences have to be those
INCREMENTAL effects which are due to the proposed
development, and not those which are due to the
passage of time or other developments not
included in the proposal.
5Origins and history of EIA
- 1960s witnessed the emergence of environmentalism
(e.g. publication of Silent Spring by Rachel
Carson in 1962) - First formal system of EIA established in the US
following the National Environmental Policy Act
(NEPA) of 1969
6Origins and history of EIA
- NEPA sought to ensure that environmental concerns
were considered in the decision-making of Federal
Government agencies - Section 102(2)(c) required agencies to prepare a
detailed statement on the environmental impact of
proposals for legislation and other major
Federal actions significantly affecting the
quality of the human environment
7Origins and history of EIA
- The statement referred to as an Environmental
Impact Statement (EIS) - should include details
on - any adverse environmental effects which cannot be
avoided should the proposal be implemented - alternatives to the proposed action
8Origins and history of EIA
- Since 1969 a host of other countries have adopted
EIA legislation - In 1977 the European Commission began drafting a
directive on EIA and finally published a proposal
in 1980 - Directive 85/337/EEC on the assessment of the
effects of certain public and private projects on
the environment the EIA Directive was adopted
in July 1985 and Member States had until 3 July
1988 to implement its requirements
9The EIA Directive
- The EIA Directive requires projects likely to
have significant effects on the environment by
virtue of their nature, size or location to
undergo an environmental assessment before the
competent authority in question grants consent
10The EIA Directive
- The EIA Directive was amended in 1997 (Directive
97/11/EC). Following signature of the Aarhus
Convention on 25 June 1998, Directive 2003/35/EC
was adopted which amends amongst others the EIA
Directive and brings it into line with the public
participation requirements of the Aarhus
Convention
11The EIA Directive
- See the European Commissions web pages on
environmental assessment at - http//europa.eu.int/comm/environment/eia/home.ht
m
12The EIA Directive
- The EIA Directive defines a project as
- the execution of construction works or of other
installations or schemes, - other interventions in the natural surroundings
and landscape including those involving the
extraction of mineral resources
13The EIA Directive
- The EIA should identify, describe and assess the
direct and indirect effects of a project on the
following factors - human beings, fauna and flora
- soil, water, air, climate and the landscape
- material assets and cultural heritage
- the interaction between the above factors
- EIA should therefore have a strong social
dimension
14Screening (does the project require EIA?)
Impact assessment (interpreting the impacts)
Scoping (what issues and impacts should the EIA
address?)
Mitigation (what can be done to alleviate
negative impacts?)
Baseline studies (establish the environmental
baseline)
EIS preparation/review (document the EIA
findings)
Alternatives (consider the different approaches)
Public consultation (consult general public and
NGOs)
Monitoring (monitor impacts of project)
Impact prediction (forecast the environmental
impacts)
15Screening
- Is an EIA needed?
- Many projects may have no significant
environmental effects - A screening mechanism seeks to identify those
projects with potentially significant adverse
environmental effects
16Screening
- Two principal approaches to screening
- the use of thresholds
- case-by-case examination against criteria
- Under the EIA Directive
- EIA is mandatory for projects listed in Annex I
of the Directive - EIA is required subject to Member States
thresholds and criteria for projects listed in
Annex II of the Directive
17Scoping
- The scope of an EIA is the issues and impacts it
addresses - Scoping is the process of deciding which of a
projects possible alternatives and impacts
should be addressed in the EIA - An EIA should focus only on the significant
issues and impacts
18Scoping
- Scoping is carried out in discussions between the
developer, the competent authority, relevant
agencies and, ideally, the public - Effective scoping enables limited resources to be
allocated to best effect (i.e. through
investigation of only the most significant
impacts) - Scoping is not mandatory under the EIA Directive
19Baseline studies
- Following the scoping phase, it is essential to
assemble all the relevant information on the
current status of the environment - The baseline study should anticipate the future
state of the environment assuming the project is
not undertaken - the no action alternative - This provides the baseline against which future
impacts can be assessed
20Baseline studies
- Baseline studies should be undertaken for each
alternative site so that the relative severity of
the impacts for each alternative can be assessed - New field work may necessary (e.g. ecological
survey) if relevant data is not already available
21Alternatives
- EIA is ideally undertaken for a project and its
alternatives (e.g. different locations, scales,
designs) - Alternatives are the raw material of EIA
- The US Council on Environmental Quality (CEQ) has
described the discussion of alternatives as the
heart of the EIS - Many EISs fail to consider alternatives
22Impact assessment
- Impact assessment involves evaluating the
significance of the impacts identified - Significance can be determined through
professional judgement, reference to regulations
etc. - Potential for bias in determining what is
significant - The conclusions of the impact assessment can
ultimately be used by decision-makers when
determining the fate of the project application
23Mitigation
- Negative impacts on the environment identified
during the EIA can be alleviated through
mitigation measures - The mitigation hierarchy Avoid - Reduce - Remedy
- Compensate - Enhance - Impacts remaining after mitigation are known as
residual impacts - The legislation obstructs the proper process of
design development
24EIS preparation / review
- The Environmental Impact Statement (EIS) is a
formal document which includes information on the
development and information relating to
screening, scoping, baseline studies,
alternatives etc. - Common requirement to include a non-technical
summary
25EIS preparation / review
- Once complete, the EIS is submitted to the
competent authority (along with the planning
application) - The EIS is often reviewed (either formally or
informally) - The review enables the competent authority to
decide whether the EIA is adequate, accurate and
unbiased
26Public consultation
- The EIA Directive provides for public
consultation on the application for development
and the EIS
27Post-project monitoring
- Monitoring should determine
- the accuracy of the original predictions
- the degree of deviation from the predictions
- the possible reasons for any deviations
- the extent to which mitigation measures have
achieved their objectives
28What is in an ES?
- Non Technical Summary
- Description of the proposals
- Assessment of Baseline conditions
- Assessment of no development conditions
- Assessment of conditions with development
- Mitigation proposals
29What is in an ES?
- All conditions assessed for
- Construction phase
- Operation phase
30Construction Phase
- Temporary
- Higher levels of impact usually deemed acceptable
- Difficult to predict
- VERY difficult to enforce conditions
- Usually well influenced by effective consultation
31Operation Phase
- Long Term
- Much less room for compromise on standards
- Relatively simpler to predict
- Less difficult to enforce conditions, as the
conditions are on the project owner - Usually less influenced by effective consultation
at scheme level, more at detailed level
32Operation Phase
- Can be several phases
- Project itself may be developed in stages
- Sometimes need to look at
- Commissioning
- Opening
- Operation after period
- Operation once landscaping mature
- Operation at design capacity
- Operation at ultimate capacity
33Consents Process
- ES generally accompanies an application for
permission to proceed - May be at Local, Regional, or National level
- Local and regional levels usually can refer
upwards - Application will be at outline or detailed stage
increasingly difficult to get approval on outline
applications
34Secretary of State Inspectors / Reporters
(Scotland) Councillors (District, County or
Borough) Chief or Senior Planning Officers
35But
- At local level, Councillors (elected members),
may be capricious and driven by political
considerations
36Consents Process
- Planning Authority will impose conditions on
acceptance eg for UK - S106 Conditions of TCP Act
- S38 Agreement Highways Act
- Parts of other Acts eg Ports and Harbours Act
(Harbour Revision Orders) - Contributions to development outside site
boundary - Contributions to local government initiatives
- Limits to levels of activity (difficult to
enforce)
37(No Transcript)
38Consents Process
- Refusal leads to appeal process
- If significant objections, Planning Authority may
refer the application to higher level of
government (in England and Wales, the Secretary
of State) - In UK, 98 of all planning applications are
granted, eventually albeit in amended form
39Acoustics and Vibration
- Roads well established methodology
- Airports widely accepted contours for
- LA EQ 16 hour and 8 hour
- Railways façade measurements and predictions
- Night time noise often critical
- Vibration threshold (usually threshold of
perception)
40- More than half of Europe's citizens live in noisy
surroundings - One third of Europeans have disturbed sleep due
to noise - Prolonged exposure to noise can cause
hypertension and heart disease - Noise above 80db may cause aggressive behaviour
- A link between noise and mental health is
suggested by the demand for sleeping pills and
tranquillizers - An adult's ear can tolerate an occasional noise
level of up to 140db - A child's ear should never be exposed to noise
above 120db - Source bbc.co.uk
41Air Quality
- Looking for
- Oxides of nitrogen (NOx)
- Oxides of sulphur (SOx)
- Ozone O3
- Particulates PM10 and now PM2.5
- Dioxins and Furans for Incinerators
- Particulates (dust)
- Odour
42Air Quality
- No legal standards
- Most projects have very limited impact
- Dioxins and Furans have become significant
concerns since the extremely low levels could be
measured - Roads schemes always show improvement in air
quality over next twenty years
43Forestry and Agriculture
- Classification of land (Grade 1, 2, 3)
- Severance and viability
- Orphaning of land parcels
- Isolating buildings from fields etc
- Opportunities for landscaping on isolated pieces
of land
44Water Quality
- Aquifer protection zones
- River designations
- Ecology impacts
- Hazard assessment from spills etc
45Landscape and Visual Amenity
- Visual assessment
- Site categorisation (AONB, Conservation area)
- Inter visibility plots
- Landscape description
- Landscape value
- Opportunities for landscaping
46Twyford Down
47Heritage and Archaeology
- Site categorisation (SAM, Grade I, II, II)
(World Heritage Site, Conservation Area) - Locally important buildings without designation
- English Heritage
- National Trust
- County Archaeologist
48Ecology
- Assessment of ecological value
- Site categorisation (SSSI,SNCI, SAC,SPA)
- Inventory of flora and fauna
- Rare species
- Protected species (incl Red List)
- Impact of severance, disruption etc
- English Nature, RSPB, Wildlife Trusts etc
49Geology and Soils
- Assessment of geological value
- Pedology characterisation
- Site protection (SSSI)
50Traffic Impact Assessment
- Traffic flows generally on roads
- Cars, taxis, trucks, buses, cycles
- Pedestrian journeys
- Public/private transport split
- Congestion/traffic management
- Proposed mitigation measures
51Sustainability Assessment
- Currently part of EIA
- Should be the over-arching process
- No current guidelines
52Construction Impacts
- Traffic movements
- Dust
- Mud
- Social impacts itinerant workers
- Business generation
- Spoil heaps
- Contamination of rivers streams
53Construction Impacts
- Light pollution
- Noise
- Vibration of piling plant
- Materials stockpiles
- Construction sites
54How does EIA actually contribute to Sustainable
Development?