Title: Railway Developments in the BMW Region
1Railway Developments in the BMW Region
- By Tom Finn
- Manager, Strategic Planning, Iarnród Éireann
2Presentation Content
- Iarnród Éireann in context
- Background to current investemnt
- Progress on current NDP projects
- BMW projects
- National Railway Development Plans
- BMW Railway Plans
- Strategic Rail Review
- Western Rail Corridor
3(No Transcript)
4Single Track
Double Track
5Investment Background
- Decades of Underinvestment
- 1987 Government policy of no substantial
investment - Future of network in doubt, options examined
- EU Funding made available in the 1990's
- EU Structural, Cohesion and Interreg Funds
- Dublin / Belfast Upgrading with EU funds
- New Locomotives purchased
- Some Track Renewal on Main Routes Funded
6Railway Safety Programme
- Knockcroghery Derailment November 1997
- Independent Safety Reviews conducted
- High Level Task Force convened
- 1999 2003 Safety Investment Programme approved
- 550m Investment
- Ahead of target, expenditure increased
7Safety Programme 1999-2003
- m
- Track 260
- Signalling, Electrical 37
- Terminals 19
- Fencing 11
- Structures 41
- Level Crossings 118
- Safety Management Systems 65
- TOTAL 550
- Actual expenditure higher
8Progress to Date under NDP
- Safety Programme on target
- 400 miles of track
- 250 bridges
- 400 level crossings
- Heuston Station near completion
- 38 New DART cars in service, 40 ordered
- 80 Railcars in service
- Drogheda depot near completion
- Maynooth line upgrading complete
- Order placed for 67 InterCity carriages
- DASH Project commenced 33 increase in DART
capacity - Resignalling of main lines underway
9(No Transcript)
10Heuston New Layout
11(No Transcript)
12(No Transcript)
13InterCity Short Term Plans
- Main plans over next 5 years
- Replace all rolling stock over 30 years old. (67
on order) - Increase service frequency on key radial routes
with reduced journey times - Introduce seat reservation system with Internet
booking by 2004 - Continue development of station facilities e.g.
Heuston
14Reduction in Journey Times
15Frequency Targets
16(No Transcript)
17RAILWAY CATCHMENT POPULATION DUBLIN AREA
18Projects Complete
- 38 DART Carriages in service
- 20 Diesel Railcars in service
- Maynooth line project complete
- DART Extensions complete
- New Stations
- 80 Diesel Railcars in service
- New Depot at Drogheda
19DART Upgrade Phase 1
- Increase DART capacity by 33 from 6 car to 8 car
- Enhanced power supply, platform lengthening,
upgrading stations - Renewal of OHLE
- 40 additional DART carriages
- 180m project, complete autumn 2005
20Future Suburban Development
- Resignalling (DASH 2) for extra paths
- Spencer Dock terminal station
- Kildare Line staged capacity increases loading
to quadrupling East West - Interconnector tunnel
- Electrification of entire network
- 4 Tracking Connolly to Howth Junction
- Phased expansion in line with available resources.
21Freight Strategy
- Volumes in decline, relatively short distances,
most suitable for bulk traffic - Loss making overall with some profitable, units,
no subsidy available - Continue to operate profitable bulk business
- Prune and re-shape non profitable business
seeking cost efficiencies full train loads - New niche Business opportunities targeted
- New Ballina-Waterford Container Service
22Strategic Rail Review 2003
- Acknowledgement of the period of under-investment
- Acknowleges the significant progress of the past
5 years - Endorses the overall approach to investment
- Shows a strong future for rail transport in
Ireland - Shows positive social economic benefits
23Iarnród Éireann Response to SRR
- Welcome report, positive recommendations
- Role of railway recognised
- Strong economic case for investment
- Consistent with Iarnród Éireanns own Development
Plan - Financial situation must be addressed,
transparent contracts are the way forward - Quantum improvement in service levels must
accompany investment - Iarnród Éireann is prepared for the enormous
challenge
24Lightly Used and Disused Lines
- Limerick Rosslare and Ballybrophy etc.
- Examined as part of Strategic Rail Review
- Major investment required, service levels would
have to expand - Investment should not be at the expense of
priority investment programme - National strategic value may influence future
role
25Strategic Rail Review
- BMW Options Examined
- Athlone Mullingar
- Ballinasloe Galway Commuter Services
- Westport Claremorris Ballina Commuter
- Claremorris Tuam Galway Commuter
- Galway LRT
- Sligo Commuter Services
- Western Rail Corridor (Sligo Cork)
- Shannon Airport Link
26Strategic Rail Review
27BMW Projects Completed
- Finalisation of track renewal
- - Galway
- - Westport/Ballina
- - Sligo
- Ancillary Work all Routes
- - Bridges
- - Level Crossings
- - Fencing
- Resignalling of Galway line
- Maintenance Depot Drogheda
- 80 Railcars for long distance commuters
- Some Common Expenditure BMW/SE
28Growth in Passenger Numbers
29Developments Galway / Dublin Route
- Resignalling Project Complete 2003
- Additional Service on Route 2004
- Replace carriages
- Shorten Journey time
- Examine additional passing loops
- Target hourly Service Frequency
30Developments Westport/ Dublin Route
- Reduced Journey time in 2004
- Increase service frequency in conjunction with
Galway Dublin Route - Introduce new InterCity railcars
- Resignalling of the line
31Developments Sligo / Dublin Route
- Reduced Journey time in 2004
- Resignalling complete 2005
- Introduce new regional railcars 2006
- Increase service frequency to 6 per day plus
commuter services from Longford and Mullingar
32Future BMW Rail Priorities
- Resignalling of Sligo line
- Resignalling of Westport line
- Replace old rolling stock with InterCity railcars
- Increase frequency, smaller trains
- Further safety investment
- Automation/elimination of level crossings
- New Depot in Midlands
- Additional passing loops
- Station Upgrade/Passenger Facilities
33Western Rail Corridor
- Infrastructure Totally Decayed
- Full Renewal Required
34Western Rail Corridor
- Infrastructure Totally Decayed
- Full Renewal Required
- Restoration to higher standard
- Faster speeds, automation, minimal operating
costs - Frequent services required
35Re-assessment of Viability of Western Rail
Corridor
- Iarnród Éireann willing to co-operate with
working party - Regional Planning Guidelines crucial
- Land Use and settlement policies to create
critical mass - Value for money and prioritisation
36Conclusions
- Good progress being made rebuilding the railway
nationally - The InterCity network in the BMW region is now in
good condition - Further significant improvements planned over the
next 5 years - Further feasibility required on Western Rail
Corridor proposal - Iarnród Éireann will co-operate with proposed
working