Railway Developments in the BMW Region - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

Railway Developments in the BMW Region

Description:

New Locomotives purchased. Some Track Renewal on Main Routes Funded. Railway Safety Programme ... Good progress being made rebuilding the railway nationally ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 37
Provided by: grou5
Category:

less

Transcript and Presenter's Notes

Title: Railway Developments in the BMW Region


1
Railway Developments in the BMW Region
  • By Tom Finn
  • Manager, Strategic Planning, Iarnród Éireann

2
Presentation Content
  • Iarnród Éireann in context
  • Background to current investemnt
  • Progress on current NDP projects
  • BMW projects
  • National Railway Development Plans
  • BMW Railway Plans
  • Strategic Rail Review
  • Western Rail Corridor

3
(No Transcript)
4
Single Track
Double Track
5
Investment Background
  • Decades of Underinvestment
  • 1987 Government policy of no substantial
    investment
  • Future of network in doubt, options examined
  • EU Funding made available in the 1990's
  • EU Structural, Cohesion and Interreg Funds
  • Dublin / Belfast Upgrading with EU funds
  • New Locomotives purchased
  • Some Track Renewal on Main Routes Funded

6
Railway Safety Programme
  • Knockcroghery Derailment November 1997
  • Independent Safety Reviews conducted
  • High Level Task Force convened
  • 1999 2003 Safety Investment Programme approved
  • 550m Investment
  • Ahead of target, expenditure increased

7
Safety Programme 1999-2003
  • m
  • Track 260
  • Signalling, Electrical 37
  • Terminals 19
  • Fencing 11
  • Structures 41
  • Level Crossings 118
  • Safety Management Systems 65
  • TOTAL 550
  • Actual expenditure higher

8
Progress to Date under NDP
  • Safety Programme on target
  • 400 miles of track
  • 250 bridges
  • 400 level crossings
  • Heuston Station near completion
  • 38 New DART cars in service, 40 ordered
  • 80 Railcars in service
  • Drogheda depot near completion
  • Maynooth line upgrading complete
  • Order placed for 67 InterCity carriages
  • DASH Project commenced 33 increase in DART
    capacity
  • Resignalling of main lines underway

9
(No Transcript)
10
Heuston New Layout
11
(No Transcript)
12
(No Transcript)
13
InterCity Short Term Plans
  • Main plans over next 5 years
  • Replace all rolling stock over 30 years old. (67
    on order)
  • Increase service frequency on key radial routes
    with reduced journey times
  • Introduce seat reservation system with Internet
    booking by 2004
  • Continue development of station facilities e.g.
    Heuston

14
Reduction in Journey Times
15
Frequency Targets
16
(No Transcript)
17
RAILWAY CATCHMENT POPULATION DUBLIN AREA
18
Projects Complete
  • 38 DART Carriages in service
  • 20 Diesel Railcars in service
  • Maynooth line project complete
  • DART Extensions complete
  • New Stations
  • 80 Diesel Railcars in service
  • New Depot at Drogheda

19
DART Upgrade Phase 1
  • Increase DART capacity by 33 from 6 car to 8 car
  • Enhanced power supply, platform lengthening,
    upgrading stations
  • Renewal of OHLE
  • 40 additional DART carriages
  • 180m project, complete autumn 2005

20
Future Suburban Development
  • Resignalling (DASH 2) for extra paths
  • Spencer Dock terminal station
  • Kildare Line staged capacity increases loading
    to quadrupling East West
  • Interconnector tunnel
  • Electrification of entire network
  • 4 Tracking Connolly to Howth Junction
  • Phased expansion in line with available resources.

21
Freight Strategy
  • Volumes in decline, relatively short distances,
    most suitable for bulk traffic
  • Loss making overall with some profitable, units,
    no subsidy available
  • Continue to operate profitable bulk business
  • Prune and re-shape non profitable business
    seeking cost efficiencies full train loads
  • New niche Business opportunities targeted
  • New Ballina-Waterford Container Service

22
Strategic Rail Review 2003
  • Acknowledgement of the period of under-investment
  • Acknowleges the significant progress of the past
    5 years
  • Endorses the overall approach to investment
  • Shows a strong future for rail transport in
    Ireland
  • Shows positive social economic benefits

23
Iarnród Éireann Response to SRR
  • Welcome report, positive recommendations
  • Role of railway recognised
  • Strong economic case for investment
  • Consistent with Iarnród Éireanns own Development
    Plan
  • Financial situation must be addressed,
    transparent contracts are the way forward
  • Quantum improvement in service levels must
    accompany investment
  • Iarnród Éireann is prepared for the enormous
    challenge

24
Lightly Used and Disused Lines
  • Limerick Rosslare and Ballybrophy etc.
  • Examined as part of Strategic Rail Review
  • Major investment required, service levels would
    have to expand
  • Investment should not be at the expense of
    priority investment programme
  • National strategic value may influence future
    role

25
Strategic Rail Review
  • BMW Options Examined
  • Athlone Mullingar
  • Ballinasloe Galway Commuter Services
  • Westport Claremorris Ballina Commuter
  • Claremorris Tuam Galway Commuter
  • Galway LRT
  • Sligo Commuter Services
  • Western Rail Corridor (Sligo Cork)
  • Shannon Airport Link

26
Strategic Rail Review
27
BMW Projects Completed
  • Finalisation of track renewal
  • - Galway
  • - Westport/Ballina
  • - Sligo
  • Ancillary Work all Routes
  • - Bridges
  • - Level Crossings
  • - Fencing
  • Resignalling of Galway line
  • Maintenance Depot Drogheda
  • 80 Railcars for long distance commuters
  • Some Common Expenditure BMW/SE

28
Growth in Passenger Numbers
29
Developments Galway / Dublin Route
  • Resignalling Project Complete 2003
  • Additional Service on Route 2004
  • Replace carriages
  • Shorten Journey time
  • Examine additional passing loops
  • Target hourly Service Frequency

30
Developments Westport/ Dublin Route
  • Reduced Journey time in 2004
  • Increase service frequency in conjunction with
    Galway Dublin Route
  • Introduce new InterCity railcars
  • Resignalling of the line

31
Developments Sligo / Dublin Route
  • Reduced Journey time in 2004
  • Resignalling complete 2005
  • Introduce new regional railcars 2006
  • Increase service frequency to 6 per day plus
    commuter services from Longford and Mullingar

32
Future BMW Rail Priorities
  • Resignalling of Sligo line
  • Resignalling of Westport line
  • Replace old rolling stock with InterCity railcars
  • Increase frequency, smaller trains
  • Further safety investment
  • Automation/elimination of level crossings
  • New Depot in Midlands
  • Additional passing loops
  • Station Upgrade/Passenger Facilities

33
Western Rail Corridor
  • Infrastructure Totally Decayed
  • Full Renewal Required

34
Western Rail Corridor
  • Infrastructure Totally Decayed
  • Full Renewal Required
  • Restoration to higher standard
  • Faster speeds, automation, minimal operating
    costs
  • Frequent services required

35
Re-assessment of Viability of Western Rail
Corridor
  • Iarnród Éireann willing to co-operate with
    working party
  • Regional Planning Guidelines crucial
  • Land Use and settlement policies to create
    critical mass
  • Value for money and prioritisation

36
Conclusions
  • Good progress being made rebuilding the railway
    nationally
  • The InterCity network in the BMW region is now in
    good condition
  • Further significant improvements planned over the
    next 5 years
  • Further feasibility required on Western Rail
    Corridor proposal
  • Iarnród Éireann will co-operate with proposed
    working
Write a Comment
User Comments (0)
About PowerShow.com