Basic Factory Dynamics - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Basic Factory Dynamics

Description:

1) Bottleneck Rate (rb): Rate (parts/unit time or jobs/unit time) of the process ... simple assessment based on rb, T0, actual WIP,actual TH ... – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 22
Provided by: wall155
Category:

less

Transcript and Presenter's Notes

Title: Basic Factory Dynamics


1
Chapter 7
  • Basic Factory Dynamics

2
Definitions
  • Workstations a collection of one or more
    identical machines.
  • Parts a component, sub-assembly, or an assembly
    that moves through the workstations.
  • End Items parts sold directly to customers
    relationship to constituent parts defined in bill
    of material.
  • Consumables bits, chemicals, gasses, etc., used
    in process but do not become part of the product
    that is sold.
  • Routing sequence of workstations needed to make
    a part.
  • Order request from customer.
  • Job transfer quantity on the line.

3
Definitions (cont.)
  • Throughput (TH) for a line, throughput is the
    average quantity of good (non-defective) parts
    produced per unit time.
  • Work in Process (WIP) inventory between the
    start and endpoints of a product routing.
  • Raw Material Inventory (RMI) material stocked at
    beginning of routing.
  • Crib and Finished Goods Inventory (FGI) crib
    inventory is material held in a stockpoint at the
    end of a routing FGI is material held in
    inventory prior to shipping to the customer.
  • Cycle Time (CT) time between release of the job
    at the beginning of the routing until it reaches
    an inventory point at the end of the routing.

4
Factory Physics
  • Definition A manufacturing system is a
    goal-oriented network of processes through which
    parts flow.
  • Structure Plant is made up of routings (lines),
    which in turn are made up of processes.
  • Focus Factory Physics is concerned with the
    network and flows at the routing (line) level.

5
Parameters
  • Descriptors of a Line
  • 1) Bottleneck Rate (rb) Rate (parts/unit
    time or jobs/unit time) of the process center
    having the highest long-term utilization.
  • 2) Raw Process Time (T0) Sum of the
    long-term average process times of each station
    in the line.

6
Parameters (cont.)
  • Relationship
  • Critical WIP (W0) WIP level in which a line
    having no congestion would achieve maximum
    throughput (i.e., rb) with minimum cycle time
    (i.e., T0).
  • W0 rb T0

7
A Manufacturing Law
  • Little's Law The fundamental relation between
    WIP, CT, and TH over the long-term is
  • Insights
  • Fundamental relationship
  • Simple units transformation
  • Definition of cycle time (CT WIP/TH)

8
Penny Fab One
  • Review Examples in Text

9
Best Case Performance
  • Best Case Law The minimum cycle time (CTbest)
    for a given WIP level, w, is given by
  • The maximum throughput (THbest) for a given WIP
    level, w is given by,

10
Best Case Performance
  • Example For Penny Fab, rb 0.5 and T0 8, so
    W0 0.5 ? 8 4,

11
Worst Case Performance
  • Worst Case Law The worst case cycle time for a
    given WIP level, w, is given by,
  • CTworst w T0
  • The worst case throughput for a given WIP level,
    w, is given by,
  • THworst 1 / T0

12
TH vs. WIP Worst Case
Best Case
rb
Worst Case
1/T0
W0
13
CT vs. WIP Worst Case
Worst Case
Best Case
T0
W0
14
Practical Worst Case
  • Observation There is a BIG GAP between the Best
    Case and Worst Case performance.
  • Question Can we find an intermediate case that
  • divides good and bad lines, and
  • is computable?

15
Practical Worst Case Performance
  • Practical Worst Case Definition The practical
    worst case (PWC) cycle time for a given WIP
    level, w, is given by,
  • The PWC throughput for a given WIP level, w, is
    given by,
  • where W0 is the critical WIP.

16
TH vs. WIP Practical Worst Case
Best Case
rb
PWC
Good (lean)
Worst Case
Bad (fat)
1/T0
W0
17
CT vs. WIP Practical Worst Case
Worst Case
PWC
Bad (fat)
Best Case
Good
(lean)
T0
W0
18
Penny Fab Two Performance
Best Case
rb
Penny Fab 2
Practical Worst Case
1/T0
Worst Case
W0
19
Penny Fab Two Performance (cont.)
Worst Case
Practical Worst Case
Penny Fab 2
1/rb
T0
Best Case
W0
20
Take-Aways
  • Key points
  • Littles Law, although not always exact can be
    used to approximate a single workstation, line or
    entire plant
  • When there is a bottleneck the WIP THR at
    bottleneck (rb) times To CT for entire flow
  • Critical Wip number of machines in system
    this is ALWAYS the case for a balanced line all
    machines have same output rate no wip buildup
  • Single machine or balanced line the capacity
    is the reciprocal of the CT ie CT 2 hours
    Capacity ½ piece per hour
  • Station capacity can be calculated by
    machines/Process time for both balanced and
    unbalanced

21
Factory Dynamics
  • Performance Measures
  • throughput
  • WIP
  • cycle time
  • service
  • Range of Cases
  • best case
  • practical worst case
  • worst case
  • Diagnostics
  • simple assessment based on rb, T0, actual
    WIP,actual TH
  • evaluate relative to practical worst case
Write a Comment
User Comments (0)
About PowerShow.com