Title: Regals New Rigs Delivered as Advertised
1Regals New RigsDelivered as Advertised
2Index
- 3 Commitment
- 4 Background
- 6 Rig Assembly in USA
- 8 Rig Commissioning in USA
- 9 Shipment of 1st Rig
- 10 1st Rig Arrival in the Ukraine
- 11 Arrival of 2nd Rig
- 12 Base Camp Construction
- 15 Camp Facilities
- 16 Equipment Arriving on Location
- 18 Erection of 1st Rig in Ukraine
- 23 Assembly of 2nd Rig in Ukraine
2
Regals New Rigs 2008
3Commitment
- In the first quarter of 2008 Regal Petroleum
committed to a 5-year contract with Saipem SpA
for 2 new-build 2000 horse power drilling rigs
as the first step towards further development of
the Companys assets in the Ukraine.
Kiev ____
3
Regals New Rigs 2008
4Background
- Regal Petroleum decided to change over from
locally available rigs to new-build
high-performance rigs to improve overall drilling
performance in the Ukraine and thus realise the
full potential of the Companys assets. - Previously a typical 5000m well would take
between 10 to 11 months drilling time while the
expectation for the new-build rigs is to
eventually be able to drill to 5000m in less
than 6 months. - Reducing the drilling time has a significant
impact on the economics of the field development,
including accelerating production, which has a
direct, positive impact on the net present value
(NPV) of the project.
Regals New Rigs 2008
5Background
- The new rigs will also be able to explore the
deeper objectives beyond 6000m, which are part of
the current development plan. - The rigs will be managed by Saipem SpA, a well
known international drilling contractor
(www.saipem.eni.it). - The new rigs have been built by LeTourneau in
Houston, USA. During the construction of the
rigs, both Saipem and Regal have been actively
involved in the design. - To meet the Companys targets, reduce the lead
time on the construction of the rigs and prevent
slippage, the manufacturing and assembly process
was carried out around the clock.
Regals New Rigs 2008
6Rig Assembly
- LeTourneau Factory, Houston
- Completed drilling rig components ready for
transportation to designated site for testing and
commissioning
? Each rig is supplied with a total of 3 mud pumps
? Hinged A-Frame mast section ready to be
assembled for commissioning and testing
Regals New Rigs 2008
7Rig Assembly
- To prevent any delay during the erection of the
rigs in the Ukraine and down-time during
operations, a significant amount of key Saipem
personnel were trained by LeTourneau in Houston.
In addition, prior to the shipment to the
Ukraine, both rigs were fully assembled and
tested with the key Saipem personnel present on a
designated site in Houston. - The total time from start of the build to the
last item loaded for shipment for 2 rigs was
approx. 5 months a record performance for both
LeTourneau and Saipem. - The first rig arrived in the Ukraine on the 23th
September 2008.
Regals New Rigs 2008
8Rig Commissioning in Houston
- LeTourneau (Lewco) Assembly Yard, Houston
-
- Prior to shipment, both rigs and all the
equipment were fully assembled and commissioned
in the presence of Saipem and all the different
suppliers and manufacturers. - Any required rectifications and interface issues
were immediately addressed and completed prior to
shipment.
Regals New Rigs 2008
9Shipment of 1st Rig
- First rig loaded on the MV Peru in Houston
Regals New Rigs 2008
10Arrival of 1st Rig
- First rig arrived in the Ukraine on the 23rd
September 2008
Regals New Rigs 2008
11Arrival of 2nd Rig
- The second rig arrived in the Ukraine on the 23rd
October 2008 and erection commenced on the 17th
November. - In addition to the two rigs, a drilling base camp
had to be constructed to house approx. 200
people. Purpose built accommodation units were
imported from Italy. - This base camp is fully equipped with messing
facilities, recreation facilities and a clinic
with a full-time doctor. Both the camp and the
rig are fully winterised to ensure continuous
operations during severe winter conditions. - Saipem obtained a drilling licence for the
Ukraine and are operating as a Ukrainian
Licensed Drilling Company Saipem Ukraine LLC.
Regals New Rigs 2008
12Base Camp Under Construction
- The Saipem Base Camp includes a recreation area
and a permanently staffed medical clinic
Regals New Rigs 2008
13Base Camp Completed
The living quarters are near completion and
waiting for staff to move in during December 2008
13
Regals New Rigs 2008
14Base Camp Completed
- Junior accommodation facilities
- ? Paramedics are permanently stationed on the rig
site for support
14
Regals New Rigs 2008
15Camp Facilities
Catering facility for 200 people
15
Regals New Rigs 2008
16Equipment Arriving on Location
Regals New Rigs 2008
17Equipment Arriving on Location
Draw Works, Mud Pumps and Generators
Regals New Rigs 2008
18Erection of 1st Rig in Ukraine
Top Drive, Casing Stabbing Board and Derrickman
Working Platform (Monkey Board) being rigged up
Regals New Rigs 2008
19Erection of 1st Rig in Ukraine
Assembly of the Substructure Mast and Top Drive
Regals New Rigs 2008
20Erection of 1st Rig in Ukraine
Regals Supervisor, Gregoriy Lekhwar,
overseeing the assembly of the Mast and
inspecting the instrumentation in the Drillers
Cabin.
Regals New Rigs 2008
21Erection of 1st Rig in Ukraine
- First time raising of the mast (Well MEX-106 Rig
5914)
Regals New Rigs 2008
22Erection of 1st Rig in Ukraine
Installation of Winterisation (Well MEX-106 Rig
5914)
- Winterisation is the covering and protection of
the main parts of the rig against snow and frost
to ensure operations can continue during winter. - A steam plant permanently heats the rig and
rig systems during the winter. - The winterisation has been designed to stand up
to a temperature of -20 Celsius.
Regals New Rigs 2008
23Assembly of 2nd Rig in Ukraine
- Key components being positioned for assembly of
Rig 2 (Well SV-58 Rig 5915)
Regals New Rigs 2008