September 2003 Shutdown - Results - PowerPoint PPT Presentation

1 / 3
About This Presentation
Title:

September 2003 Shutdown - Results

Description:

Modifications of AFE boards to remove un-used SVX inputs ... running all AFE boards at 53MHz data transfer rate vs 40MHz we were running before the shutdown ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 4
Provided by: Deni150
Category:

less

Transcript and Presenter's Notes

Title: September 2003 Shutdown - Results


1
September 2003 Shutdown - Results
  • Luminosity system
  • Spare cables installations - finished
  • Commissioning of new electronics finished
  • No changes to the D0 luminosity numbers reported
    to ACNET yet
  • Silicon
  • Repairs of failed HDIs and relevant electronics
    finished
  • Up to 90 of working channels
  • Coherent noise and grass noise studies
    finished
  • Installation of coolant lines resistivity
    monitors - finished
  • Replacement of TLDs for radiation dose monitoring
    finished
  • Expecting results soon
  • Separation of power supplies with fiber tracker
    system - finished
  • Fiber tracker and preshowers
  • Maintenance of LVPSs and installation of upgraded
    LVPS - finished
  • Modifications of AFE boards to remove un-used SVX
    inputs from the readout and increase readout
    speed - finished
  • Having some issues running all AFE boards at
    53MHz data transfer rate vs 40MHz we were running
    before the shutdown
  • Maintenance of the VLPC cooling system
  • finished

2
September 2003 Shutdown - Results
  • Calorimeter
  • Replacement of all large cooling fans for
    preamplifiers cooling - finished
  • Modifications and tests of all Rack Monitor
    Interfaces - finished
  • Study (and hopefully fix) noises finished for
    now
  • 3 sources of noise have been identified and ways
    to reduce noises are under investigation
  • Muon A-layer electronics
  • Silicon electronics
  • LAr monitoring connections welder noise
    resolved
  • Detector grounding has been substantially
    improved
  • Muon
  • Access to A layer forward muon tracker
    replacement of preamplifiers, gas leaks, gas
    monitors - finished
  • Installation of extra trigger counters - finished
  • Installation of 144 remote power cycle relays for
    front-end electronics and all relevant cabling -
    finished
  • Forward proton detector
  • Maintenance and installation of
    electronics/detectors for full system operation
  • finished
  • General detector maintenance
  • Air handlers, hydraulic systems, vacuum jackets,
    cooling water systems, ODH heads, etc.- finished

3
D0 Summary
  • Shutdown is in its final stage
  • Progressed safely and on schedule
  • Good support from the D0 mechanical and
    electrical groups as well as many Collaborators
    involved
  • All critical jobs planned for this shutdown have
    been accomplished
  • We expect data taking with fewer interruptions
    (higher reliability) and better detectors (data
    quality) after the shutdown
  • Our short term plan
  • Tuesday (tomorrow) closing detector
  • Wednesday magnets tests
  • Thursday and Friday final commissioning of full
    detector with cosmic (day time access only)
  • Friday final survey of the closed detector
  • We are ready for beam circulation in the Tevatron
  • Silicon protection is up and running
  • Tunnel shielding is re-installed
  • We have 24/7 shifts for all sub-systems starting
    this Thursday with initial goal of detector
    commissioning and then physics data taking
  • Looking forward for great Tevatron performance
    after extended shutdown
  • Will be ready for collisions early next week
Write a Comment
User Comments (0)
About PowerShow.com