Title: INTRODUCTION OF HEAVY AXLE LOAD OPERATION ON INDIAN RAILWAYS
1INTRODUCTION OF HEAVY AXLE LOAD OPERATION ON
INDIAN RAILWAYS
- Presentation
- By
- Rakesh Chopra and H L Suthar
- ADDITIONAL MEMBER,and DIRECTOR
- Indian Railway Board
2STRUCTURE OF PRESENTATION
- GROWTH
- _ NATIONAL.
- _ INDIAN RAILWAYS.
-
- INITIATIVES
- _ EXISTING TRACK AND
STRUCTURES. - _ MODERNISATION OF TRACK
AND STRUCTURES. - _ RESIDUAL CAPACITY AND
DESIGN REVIEWS. -
- DEVELOPMENT OF INITIATIVES
- _ INCREASE VOLUMES.
- _ PILOT
PROJECTS ON HIGHER AXLE LOADS. - _ IMPROVE THROUGHPUTS.
-
- EXPERIENCE GAINED.
- CONCLUSIONS.
3GROWTH
- CORE INFRASTRUCTURE INDUSTRY IN INDIA COMPRISES
- CRUDE, REFINED PETROLEUM
PRODUCTS, COAL, - ELECTRICITY, STEEL AND CEMENT.
- ON IR ABOUT 75 OF FREIGHT COMPRISES COAL, STEEL
CEMENT AND PETROLEUM PRODUCTS - GROWTH OF THESE 05-06
06-07 -
5.8 8.4 - GDP GROWTH 9
9.2 - INFLATION 4.4
5.12
4TREND OF EARNING 0N IR
5TRACK UTILISATIONIncrease in Traffic Density
6Freight Projections
7Track structure
- conventional
modern - RAILS 90R/52KG 72UTS
52/60KG 90UTS HH -
ON CURVES - SLEEPERS WOOD/STEEL/CST
PRC - 1310/1540 /PKM
1540/1660/PKM - FITTINGS RIGID
ELASTIC - BALLAST 150/200mm
250/300mm - JOINTS FISH PLATED
WELDED WITH SEJs - SWITCHES STRAIGHT
CURVED/TWS - XINGS BUILT
CMS - SUBBALLAST NONE
DESIGNED BLANKET
8CAPACITY AND DESIGN REVIEWS
- TRACK MODULAS
- RAIL STRESSES
- SLEEPER DESIGNS
- FATIGUE IN RAILS
- IMPACT FACTOR
- BRIDGES SUPERSTRUCTURE
- SUBSTRUCTURE
- BEARINGS
9Track Structure
- Survey of current practices, carried out by
JRP-2, initiated by World Executive Council of
UIC indicates the following relationship between
Rail Section and Axle Load
10Track Structure
- The Survey also indicates that rails with Higher
BHN are being used for higher axle loads
11Brief History of HAL introduction
- Original design of wagons is with 20.32 tonne
axle load - Carrying Capacity (CC) of wagons is derived from
above axle load and same is stenciled on each
wagon - Later
- Loading Tolerance (LT) was permitted upto 2T
- Carrying Capacity has been enhanced by 2T, the
Permissible Carrying Capacity (PCC) thus became
CC2T and total load (TL) including LT as CC22T
i.e. axle load as 21.32T - PCC was enhanced further by 2T in November, 2004,
universally for all wagons designed for 20.32T
axle load and having air brake system i.e. TL as
CC42T and AL 21.82T
12Pilot Projects
- In May 2005, PCC was further enhanced by 4T for
BOXN wagons on identified iron ore routes as a
Pilot Project for one year i.e. TL as CC82T and
AL 22.82T -
- Following precautions have been taken
- Maximum speed restricted to 60 kmph
- Introduced USFD examination to detect Gauge
Corner Fatigue (GCF) defects - Planned, installation of in-motion weigh bridges
as loading points to prevent over loading - Instrumentation of Bridges, planned, to measure
longitudinal forces and stresses in members - Installation of Wheel Impact Load Detectors
(WILD) - Quarterly review at PHODs level
13Pilot Projects contd
- In November, 2005 Pilot Project was extended for
Coal routes of CR in BOXN wagons, TL in this case
was kept as CC62T keeping loadability in view
(AL 22.32T). - Conditions were same as for CC82T
- Pilot Project period extended by one more year
i.e. upto Jun 2007. - More routes have been included gradually in both
the above projects, more commodities and wagons
have also been included - Presently CC62T is in operation nearly on 26000
route kms and CC82T on 5000 kms
14Growth of axle loads
ORE
ALL COMMODITIES
COAL,CEMENT
ORE
PAST
NOV O4
NOV 05
MAY 05
15TRENDS
ORE
NOV 04
MAY 05
16Experience gained from Pilot Project
- Rapid wear of points and xings
- Excessive wearof rails on curves
- Faster crushing of rubber pads
- New formation problem locations
- Rail head pitting because iron ore fall
- Increase in cases of wheel scabbing/wheel burnt
rails - Increase in rail/weld failures especially in weld
failures
17WAGON PROBLEMS
- There has been increase in wagon defects.
18Experience from Pilot Project yet to be completed
- Wheel Impact Load Detectors are to be installed
to know the impact loads and to decide the
dynamic coefficient - Longitudinal forces on bridges and stresses in
members of superstructure of girder bridges are
yet to be measured
19HAL future scenario
- It is envisaged that 25T axle load operation will
start from this year (2006-07) - Presently in BOBS wagons which are designed for
22.9T axle load - Future plans
- Nearly 7000 route km on iron routes have been
identified for upgradation for 25T AL - Nearly 4200 route km identified as feeder routes
to DFC. These will also be upgraded for 25T AL
20Provision in XIth five year plan
- Age cum condition basis renewals are planned
(costing Rs 23085cr) - Upgradation of iron ore routes and feeder routes
to DFC costing Rs 1800 cr are also planned
21Integrated Railway Modernization Plan
- Modernisation of track structure along with track
renewals - Cent percent mechanisation of track maintenance
and renewal activities - Improved and mechanised USFD technology (SPURT
cars) - Data loggers on existing SRT and DRT
- Improved AT weld technology
22 - STRATEGY FOR THE FUTURE
- Improve through put
- Take care of Pilot Project experiences
- Create future capacity.
- Wagon design.
23IMPROVE THROUGH PUTS
- FASTER TRAINS ON EXISTING SECTIONS
- HIGHER SPEEDS ON TURNOUTS
- REMOVAL OF PERMANENT SPEED RESTRICTIONS PROGRAMME
- MECHANISATION OF TRACK WORKS AND REDUCTION OF
WORK SITES - HIGHER SPEEDS AFTER WORKINCREASE OF TRAIN PATHS
- REDUCTION IN NUMBER OF LEVEL CROSSINGS
- GO FOR NEED BASED MAINTENANCE-IMLPEMENT ON LINE
TRACK AND BRIDGES MANAGEMENT INFORMATION SYSTEMS - IMPROVE TERMINAL HANDLING FACILITIES.
24Take care Pilot Project experiences
- AT welds reduced,
- Roll longer rails
- Thick Web Switches
- Cleaner rails
- Introduce Rail grinding
25Contd---
- Proper power needs to be provided for trains to
prevent cases of stalling/scabbing etc - To identify these trains from Normal goods trains
special name (SUMO) is being given - Induct new materials and technology
- Improve wagon designs
- Redo Feeder routes for above wagons and DFC
- Need Based Track maintenance and 6 hr possessions
for track works
26Create Future Capacity
- Construction of Dedicated Freight Corridor.
- Eastern
- Western
- -Expected Investment Rs 30,000 cr
- -Expected period of
- completion 5 yrs from start
dt
27PROPOSED FREIGHT CORRIDORS
LUDHIANA
Sanctioned projects
DELHI
KOLKATA
MUMBAI
VIJAYAWADA
VASCO
CHENNAI
28Dedicated Freight Corridors- Planning Parameters
- First Phase Eastern and Western Routes
- 2700 km Double Line Corridor
- Fit for Speeds up to 100 Kmph
- Capable of 30-32.5 Tonnes Axle Load
- Capable of Double Stack Container operation.
- Computerized Train Control System
29Dedicated Freight Corridors- Planning Parameters
- Adoption of liberal MMD
- Tare to pay load ratio of 4-5
- Longer loops of 1.5 km
- Feeder routes fit for 25 tonne axle load
- Mineral routes for 25 tonne axle load
30Wagon design
- Presently most of the wagons are designed with
20.32T AL - Wagons are being designed with 22.9T and 25T AL
- To maximise the output track loading density
(TLD) is being enhanced (from lt8.25t/m to nearly
9.33t/m and finally upto 12t/m for 30/32.5T AL)
i.e. wider and high wagons will be used - Production likely to start by end of next
financial year
31Infringements on Feeder Routes, Inside Stations
32Proposed MMD for Dedicated freight Corridor
9 FEET 6 INCH CONTAINER HT 6.81mt WHEEL DIA
860mm ?
33Proposed SOD for Feeder Routes on Eastern Corridor
Clearance for Electrification is yet to be
decided?
34Proposed SOD for Double Stack Containers on
Feeder Routes
7300
7300
Clearance for Electrification is yet to be
decided?
35CONCLUSION
- PENDING COMPLETE VALIDATION OF PILOT PROJECTS
PATH CHOSEN APPEARS CORRECT - CONSOLIDATE PILOT PROJECT RESULTS AND PREPARE
FUTURE ACTION PLAN - QUICK INDUCTION OF TRIED AND TESTED TECHNOLOGY
- 4. PUT IN PLACE QUICKLY CIVIL ENGINEERING MIS
ON LINE SYSTEMS. - 5. DEVELOP NEW DESIGNS FOR COSTRUCTION,
OPERATION AND MAINTENANCE OF DEDICATED FREIGHT
CORRIDOR AND FEEDER ROUTES. - 6. PLAN AND MAKE AVAILABLE RESOURCE INPUTS
FOR ABOVE.
36 37Track structure design
- For 25T AL operation following are considered
- Rails 60kg 90UTS (HH on curves)
- Sleepers PSC with 1660nos per km
- Fastening- elatsic fastening (ERC, GRP, liners)
- PC - fan shaped (PSC) layout curved
switches (TWS prefered) - Ballast cushion- 300mm, 350mm (recommended)
38Track structure design
- To achieve economy existing track structure
consisting of following track structure is
considered adequate for speeds upto 60kmph - Rails 52kg 90UTS
- Sleepers PSC with 1540 nos per km
- Ballast cushion- 250mm
39Structure of presentation
- Track structure
- Track modulus and Rail stresses
- Brief history of HAL
- HAL operation
- Planning in XIth five year plan and IRMP
- Wagon design
- Experience gained
- Track structure design for 25T AL
- Track Management System
40Track modulus
- As the track structure has undergone lot of
changes, it become necessary to reassess the
track modulus - Studies were conducted by RDSO and based on
results track modulus has been modified as under
41Rail stresses
- Based on modified track modulus, track stresses
have been calculated - Different methodology is adopted to find
suitability of existing infrastructure and design
for new structures
42Track structure change
- Change in track structure could be possible due
to creation of SRSF fund (2001-02) and sufficient
provision of funds under DRF thereafter - In previous 6-7 years large number of track
renewal works have been executed. - Modern track structure is provided alon with
renewals, depending on route classification and
annual traffic density - Especially during Primary renewals
43Track Mangement System
- IR has introduced Track Management System (TMS)
quite early (1990-91) - It was introduced as Pilot Project
- It however could not be implemented fully
- Lot of changes has taken place in IT and
communication technology, since then - Now proposes to introduce TMS cum Management
Information System