Some initial thoughts on issues relating to Large Facilities

Description:

Coaching within NSF and outreach to research community will be ... for material and labor rate variances, and schedule slip, =d$/dX ... Coach project ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 24
Provided by: markc79
Category:

less

Transcript and Presenter's Notes

Title: Some initial thoughts on issues relating to Large Facilities


1
Some initial thoughts on issues relating to Large
Facilities
  • Mark Coles
  • DRAFT
  • To review with Tom Cooley

2
High and low level issues
  • Strategic issues maybe use a future revision of
    the facilities guide as a lever to address these
    policy issues
  • Funding for initial planning and technology
    development
  • Parallel development of a user community
  • Narrow definition of scope
  • Life cycle cost accounting
  • Tactical issues
  • Building relationships with the IG and the Hill
  • Project management planning and execution with
    projects now underway or just starting
  • Facilities guide outreach and enhancement to add
    additional topics
  • Procurement strategy and assistance

3
How do large projects receive funding prior to
approval?
  • Some large projects require significant resources
    early in their development to support
  • Enabling technical development
  • accurate bottoms-up cost and contingency
    estimates
  • WBS dictionary and resource loaded schedule
  • Development of mature procurement strategy and
    specification
  • Pre-award funding for technical development can
    be substantial (tens of millions of ), and
    should not tax the base program. Examples of
    programs that have benefited from
    pre-construction awards for significant technical
    development are
  • LIGO (support for 40 meter interferometer on
    Caltech campus),
  • Ice Cube (AMANDA, and further back DUMAND),
  • Ice Cube received specific Congressional funding
    for phase 1, which was not requested by the NSF
  • ALMA (32 million for competitive engineering
    design of antennae).

4
MRE StrategyDevelopment of a user community
  • How does the user community get developed and
    funded?
  • LIGO may have been unique since there was no
    previous broad experimental community. Many
    experimentalists came from other fields, and some
    had not previously had NSF support.
  • Need to have early and sustained participation
    of broader community. Where does funding come
    from to support this, since otherwise there are
    potentially program breaks if community has to
    wait until operation to propose?
  • MRE relationship to base budget,
  • facilities often enable small researchers to do
    research at the facility

5
The colors of money
  • Narrowly defined scopes for individual budgets
    can hamper a project by not permitting
    flexibility to respond to new technical
    developments or other opportunities.
  • Examples
  • grid computing at LHC
  • Participation of community in installation and
    commissioning of a facility
  • EPSCOR funding (NEES)
  • A central feature of successfully reviewed MRE
    projects is the potential for outreach and
    broader societal impacts, yet this is not an
    allowed expense for MRE budget.
  • Is there an opportunity to address these issues?

6
Life Cycle Costs
  • How should full life cycle costs be presented?
  • Successful projects will have significant cost
    growth as user community utilizes and adds scope
    to initial project.
  • This should be represented as success.
  • Cost accounting needs to distinguish this from
    cost and schedule overruns with respect to
    initial scope.
  • Development of formal, visible process for
    project scope, schedule and budget modification
    within NSF maybe this already exists?
  • Full cost accounting should tell an accurate
    story of the project. A stock prospectus provides
    accounting information from which an investor can
    infer the status of the company and where it is
    headed. Life cycle costs should allow one to
    accurately identify successful projects and
    distinguish them from projects that are merely
    expensive.

7
Cost reporting
  • Need a transparent and systematic process within
    NSF to track changes to scope, baseline budgets,
    reportable milestones, etc.
  • How should upgrades be accounted for?
  • Should operations labor be included in upgrade
    cost accounting?
  • Defined process for reporting, addressing, and
    mitigating cost escalation when a project gets
    outside the budget envelope. add to guide?
  • Commissioning and initial operation should be
    included as part of MRE since they are often part
    of the validation of the facility. Since real
    boundaries may not be clear, imposing accounting
    boundaries is artificial. Can this be changed?

8
Future Costs
  • Can a liens list be created and managed within
    the NSF to anticipate and support full life cycle
    costs for each project?
  • This would be a current list of possible future
    expenditures, such as maintenance,contingency
    repairs and spares, upgrades, possible scope
    expansions, etc.
  • Done at project level in LIGO, maybe helpful to
    know at NSF level

9
Tactical Issues
  • Facilities Guide revision after some initial
    period to include policy issues
  • Seed money to develop project before it goes
    forward phase 1 funding.
  • Funds for development of user community. When an
    MRE project enables a community, a lot of small
    research grants will utilize the facility and
    increase proposal demand on the base program
  • Greater guidance on mitigation options when
    projects do go off track
  • Coaching within NSF and outreach to research
    community will be needed to help projects develop
    reasonable WBS and resource loaded schedules and
    procurement strategies, and to use them to manage
    what they do.

10
Development of cooperative agreements
  • Work with awardee to develop
  • Scope
  • WBS requirements
  • Staffing plan
  • Integrated resource loaded schedule and major
    milestones
  • Reporting strategies to NSF
  • What is reported
  • Reporting periods
  • Review schedule for major procurements, design,
    demonstration, and construction,

11
Project Management Strategies
  • Should minimize risk include in Facilities
    guide some how-to and follow up with on-site
    coaching on additional topics
  • Structure projects so that there is a tiering of
    authority with a central management. A single
    awardee holds financial and managerial authority
    over subawardees, and holds project contingency
    at the highest level
  • Examples
  • LIGO has Caltech as awardee and MIT as subaward
    worked well
  • NEES 18 awards(!), one critical award to system
    integrator has encountered some problems
  • Earthscope 4 awards, plus USGS (unbudgeted)
  • Not simple when foreign or external agency
    participation
  • Provide coaching to project where appropriate

12
Procurement Strategy
  • Work with awardee to develop procurement
    strategy, schedule, cost and schedule contingency
    estimates.
  • Tiering of subcontracts to maximize FFP use with
    well defined deliverables.
  • Minimize subcontractor couplings (GFE, schedule
    linkage) to avoid interference.
  • Limit in-house work to areas where scope and
    uncertainty are within capabilities of performing
    organization
  • Major procurements require timely evaluation and
    approval at NSF
  • LIGO received excellent assistance from Dave
    Berley plus Aaron Asrael, Jesse Laskin, Karen
    Sandberg, Carol Langguth. Who are the present
    equivalents?
  • Assemble an A Team of equivalent personnel to
    provide rapid project response? (Maybe already
    exists, but need to get to know these staff and
    process for working together.)

13
Contracting
  • Specific provisions for contracting in LIGO went
    well beyond standard provisions required in OMB.
    These were negotiated by Aaron Asrael and Ed
    Jasnow and cooperative agreement was amended
    appropriately
  • Monthly cost/schedule reporting, formal reviews,
    CDRLs, etc.

14
Other items addressed in LIGO that might be
discussed in contracting part of Facilities Guide
  • Establishment of cash-neutral payment milestones
    in contract schedule of values
  • Minimize Level of Effort contracts and time and
    materials contracts
  • Construct a resource loaded schedule that allows
    one to extract estimates of cost impact for
    material and labor rate variances, and schedule
    slip, d/dX
  • How to construct set of project milestones that
    is sensible tells an accurate story of the
    development plan and minimizes false alarms.
  • Develop a project QA strategy that includes
    witnessing key subcontract activities, material
    acceptance testing,
  • Subcontractor development, submittal, and
    acceptance of a subcontractor QA plan
  • Transition plans for going from
    construction/commissioning to operation.

15
More guide topics
  • Define when and how external Technical Review
    Boards should be created by awardee to develop
    and update plans, specifications, award
    contracts, etc.
  • Same for Contract Review Boards
  • Define when a field manager is required to
    oversee various activities such as construction
    management
  • Define relations between contractor and next
    lower tier
  • Materials receiving and qualification
  • Travelers and other in-process documentation
  • Policy on drawing and specification release,
    control, and revision

16
WBS Development
  • Guide should address
  • Methodology for development of WBS
  • Methodology for development of contingency.
  • A clear definition of what is meant by
    contingency
  • work detail that is more effective to address
    through field changes or in process changes than
    it is to design in advance.
  • Average uncertainties in cost estimating
  • Guidelines for estimating contingency
  • Define how contingency should be held within a
    project at the top level and not distributed
    over the WBS elements.

17
Guide Enhancements
  • Coach project management to set up
  • CCB process within project that is transparent to
    all interested parties
  • Monthly (when appropriate) cost/schedule
    reporting within project and disseminated within
    NSF
  • Document Control Center that seamlessly links
    project documentation and NSF documentation
    electronically
  • Use Cooperative Agreement as framework to
    introduce these commitments within each MRE
    program

18
Additional ideas for additions to the Facilities
Guide
  • How a project gets started and how the NSF wants
    to work with the community in the early phase of
    development
  • Elaboration on the Internal Management Plan - How
    a project is managed inside the NSF scope
    additions, EHR involvement, interdivisional
    interactions, what the program officer does, PO
    oversight within the NSF, etc.
  • NSF expectations for how project should be
    managed during construction
  • Guidelines for development of a cooperative
    agreement reporting, procurement guidelines and
    approvals, definition and visibility of
    milestones, etc.
  • How is overall procurement strategy developed and
    reviewed?
  • QA, safety, elaboration on property management
  • How to handle overruns and deficiencies
  • Guidance structuring reviews during various
    phases of project life composition of review
    board, financial, technical, management reviews

19
More ideas
  • Preparation for operation
  • Within NSF advance budget planning, impact on
    user community
  • By performing org
  • Operational readiness review (include safety)
  • Acceptance test
  • Pre-ops
  • Thoughtful choice of milestones to identify key
    activities
  • Operations
  • What NSF expects of the performing org to begin
    ops
  • Budget and staffing exercises
  • There is no operational contingency, yet major
    repairs are a fact of life and appropriate
    management reserve needs to be held somewhere,
    even though this is a hot button issue with IG
  • What happens within NSF to enable a community
    through operation of a facility
  • Termination process lots to cover here just
    one page in guide

20
Relationships
  • Build a constructive relationship with Cheh Kim
    and others on the Hill
  • Gary Sanders impression that there is an
    opportunity to build on the very positive view
    Kim has of Tom and BFA
  • A heads up where appropriate, to let Cheh know
    what activities are going on with respect to MRE
    would be very helpful, according to Gary
  • Be open and transparent to OIG
  • Develop visible management information system of
    tracking cost, scope, and schedule to allow rapid
    and easily obtained assessments of project
    status, funds expended, etc.
  • Proactive interactions?

21
Existing issues
  • NEES is in trouble NCSA is under-performing and
    scope/schedule/deliverables are not defined. If I
    were PO Id ask for an audit before continuing.
  • Earthscope project management looks troublesome
    since structure replicates deficiencies of NEES
  • Michigan State Superconducting Cyclotron ops
    budget is way out of line (40), and on-site
    review provided little information to
    substantiate why they need more money.
  • What should be my involvement in these issues?

22
New programs I need to become familiar with
  • Not yet met with
  • Underground Lab
  • Oceans
  • Antarctic
  • Observe Lehman review at DOE
  • Get to know Jim Yeck - Observe DOE LHC monthly
    review at FNAL
  • ALMA visit prior to construction start

23
Budget planning
  • How does budget process work for this position?
  • FTEs
  • Travel money
  • Supplies
  • Office space, etc.
  • Do I need to develop a plan for next FY?