Title: Electronic Subcontracting Reporting System eSRS Status DoD December 8, 2005
1Electronic Subcontracting Reporting System
(eSRS)Status DoD December 8, 2005
Ms. Peg Meehan Assistant Director OUSD (ATL),
SADBU
2Electronic Subcontracting Reporting System (eSRS)
- The eSRS is an electronic, web-based system for
subcontract reporting that will replace the
SF-294 SF-295 paper forms. - When DoD comes on board in FY 2006, it will be a
Government-wide system and the only automated
system authorized for subcontract reporting.
3Organizational Structure
- System Steward
- U.S. Small Business Administration (SBA)
- Contractor
- Symplicity Corporation, Inc.
8(a) firm based in Arlington, Virginia -
4IAE Architecture
5System Features
- Critical Systemic Linkages
- Central Contractor Registration (CCR)
- Federal Procurement Data System
- (FPDS-NG)
- Government-wide agency hierarchy
- DUNS numbers for prime contractors and
subcontractors
6Electronic Subcontract Reporting System (eSRS)
- The eSRS is a downstream FPDS/NG application
- On the Positive Side If a contract contains a
subcontracting plan and has been entered
correctly in FPDS/NG, the eSRS automatically
receives a record of it - Downside If a contract is not in in FPDS/NG or
has not been entered correctly, the contractor
wont be able to enter his ISR (formerly the
SF-294) report at all
7System Features
- Business Processes
- Identifies contracts in FPDS-NG having
subcontracting plan requirements - Automates completion and submission of SF-294 and
SF-295 - Will include the Annual SDB Breakout Report
(3-digit NAICS subsector) - When fully operational, it will also automate the
Optional Form 312
8 Goal Computation on the ISR
- The system calculates the achievements by two
methods - of contract value
- of subcontracting ____________________________
_______ - Note the eSRS will only calculate the
percentage on the achievement side, not the goal
columns. The contractor will input the goals
from the subcontracting plan as they appear in
the plan.
9System Features
- Provides breakout of subcontracting data down to
the buying activity level. (ISR) - Generates standard and ad hoc reports
- Analysis of Subcontracting Plan Goal Attainment
- Five-Year Trend Table
- SBA Goaling Report for Congress the President
- Several other standard reports
- Generates automatic reminder notices and
delinquent notices.
10Critical Milestones
- Beta Testing and Acceptance
- September 2005
- Initial Operating Capability (IOC)
- October 28, 2005
- Full Operating Capability (FOC)
- Target 8 weeks after IOC
- DoD Implementation
- Target April 2006
11Who should be using the eSRS?
- As of October 2005 all civilian agencies and
nearly all civilian contractors should begin
using the eSRS - _________________________________
- The Electronic Subcontract Reporting Systems
developed by NASA, DOE and GSAs FSS cannot be
used for current reporting those three systems
will now be folded into the eSRS
12What Should Contractors Enter into the eSRS?
- FY 04 Year End Reporting
- Except as noted below, all contractors holding
contracts with civilian agencies must enter their
Summary Reports only (formerly called the
SF-295) for FY 04 (the fiscal year ended 9-30-04) - GSA NASA contractors that used the GSA NASA
Electronic Subcontract Reporting Systems,
respectively, for their FY 2004 reports are
exempt from this requirement
13What Should Contractors Enter? (continued)
- FY 05 (year end reporting)
- All contractors holding contracts with civilian
agencies must use the eSRS for both their
Individual Contract Reports (ISRs) and Summary
Subcontract Reports (SSRs) for the period ended
September 30, 2005. - Contractors may not use the NASA, GSA, DoE, or
any other electronic system for the 9-30-05
reports!
14What Should Contractors Enter? (continued)
- Contractors whose contracts are not in FPDS/NG
may have to submit paper reports for now - (e.g., FEHBP contractors such as Blue Cross
Blue Shield, contractors holding Medicare
contracts, USAID contractors, and contractors
with so-called black contracts) - Contact SBA Headquarters for guidance on a
case-by-case basis
15What Should Contractors Enter? (continued)
- SBA will not require mid-year FY 2005 reports
(March 31, 2005) - Some agencies may ask their contractors to submit
these reports anyway - the eSRS does have the capability to accept them.
- Note DoD exception business as usual until
notified otherwise
16Do Contractors Have an Extension for Filing?
- OFPP memo Nov 3, 2005
- authorizing a 60-day extension for filing the
9-30-05 reports (60 days from IOC) - Consistent with the previous OFPP memorandum
dated March 18, 2005, which authorized a similar
extension for the 9-30-04 and 3-31-05 reports - DoD supplement Nov 9, 2005
- Distributed to the SADBU Community
- Distributed to the DoD Acquisition Community
- Found on the OSD SB website
17What About DoD?
- OUSD(ATL) DPAP and SADBU joint memo, April 1,
2005. - The interim direction unchanged.
- DoD will implement eSRS after the system is
successfully delivered and tested. - Appropriate DoD personnel and contractors will be
formally notified in advance of the system
becoming available for use by DoD contractors.
(via DoD Implementation Team member) - Target Implementation April 2006.
- DoD contractors should continue to submit paper
SF-294s and SF-295s to IAW the instructions until
advised otherwise.
18Why isnt DoD Implementing eSRS Now?
- DoD is _at_ 70 of the Federal Govt subcontracting
reports - DoD is not fully on-board with FPDS-NG yet
- Hierarchy Issues
- e.g. We have DCMA as our contract mgmt activity
where most agencies manage their own contracts - For FPDS-NG we have _at_ 7 levels as opposed to _at_ 2
for other agencies -
- Working with e-SRS Federal team SBA to resolve
DoD concerns - FOC e.g. Comprehensive Test Participants,
System to System Interface
19When will the eSRS be fully operational?
- The Statement of Work requires the contractor to
deliver Full Operating Capability (FOC) within 8
weeks of IOC - This could still be changed by contract
modification the eSRS Team may want to
prioritize certain tasks and postpone others - Discussions are on-going
20What will FOC give us that IOC doesnt?
- FOC will provide
- an application interface so that contractors
with electronic systems of their own can simply
upload their data into the eSRS (as opposed to
keypunching it into the eSRS one report at a time)
21What will FOC give us that IOC doesnt?
(continued)
- FOC will
- be able to provide the reports that SBAs CMRs
need (the 5-year trend table and SBA Form 1907
used for Desk Reviews, among other things) - address the unique needs of DoD (e.g., the SSR
reports for the comprehensive test plan reports)
22Is the FAR being changed?
- SBA is finalizing a FAR case that includes
changes to subpart 19.7 and the related clauses,
especially 52.219-9. -
- In the interim, SBAs Office of General Counsel
has ruled that the eSRS is the electronic
equivalent of the SF-294 SF-295 - DoD will also initiate a DFARS case after/in
tandem with the FAR case
23FAR Case
- Revises subpart 19.7, clauses at 52.219-9
52.219-25 - replaces all references to SF-294, SF-295, and
Optional Form 312 with eSRS. - Revises the flow-down provision at 19.704(a)(9)
and 52.219-9(d)(9) to require the prime
contractor to flow the prime contract number down
to the subcontractors at lower tiers. - prime contract number now becomes a mandatory
field in the eSRS, even for subcontractors, in
order to
facilitate lower-tier reporting.
24FAR Case (cont.)
- Moves General Instructions from the paper forms
to the clause at 52.219-9. - Requires contractors to print a hard copy of the
Summary Report(s) and have them signed by the
CEO. - Contractor will be required to keep hard copy
with CEOs signature on file for 4 years. - SF-294, SF-295, Optional Form 312 will all be
deleted from Part 53
25FAR / DFARS Case
- SB Committee of the FAR Council will review and
discuss the specific provisions in the proposal - The regulation will be issued as a Proposed Rule
or Interim Final Rule - 60-day public comment period
- Final Rule will reflect changes resulting from
public comments, as appropriate - DFARS case to be worked to address DoD specific
changes (e.g. Comp. Test, Mentor Protégé Program)
26REVIEW OF REPORTS
- Government will review
- Primes Individual Subcontracting Reports
- All Summary Subcontracting Reports
- Prime Contractor/Higher-Tier Subcontractors will
review - Lower-Tier Individual Subcontracting Reports
27How will the eSRS Help Desk work?
- The Help Desk will handle all technical questions
regarding the use of the eSRS - Questions regarding subcontracting policy will be
referred to SBA - Other problems/issues will be forwarded to the
Agency Coordinator of the agency that awarded the
contract
28TROUBLESHOOTING
- CCR ISSUES-
- CCR Assistance Center 888-227-2423
- FPDS-NG ISSUES
- Call the Contracting Officer
- eSRS ISSUES
- Contact the eSRS Helpdesk
29TROUBLESHOOTING
- Log in or Register (Govt and Contractors)
- Frequently Asked Questions
- www.esrs.gov
- www.sba.gov (News Release)
- Specific Questions SBA CMR
- http//www.sba.gov/GC/cmr.html
30Implementation as of December 2005
- Federal-wide Implementation Team
- DoD Member Lisa Romney
- Alternates Sharon Drago
- Peg Meehan
- DoD Implementation Team
- Members from each of the Military Services
- Members from most of the larger Defense Agencies.
- Contact your Subcontracting Representative if you
dont know who your member is.
31