Title: City Council Update South Waterfront Central District Project
1City Council UpdateSouth WaterfrontCentral
District Project
March 16, 2006
2Objectives of Work Session
Review South Waterfront Vision for job
creation, housing, and public amenities.
Review collective progress toward that vision.
Review roles and responsibilities for the tram.
Discuss latest tram cost estimates and schedule
Outline PDOT changes to improve project
management and oversight
Brief Council on funding proposal for tram,
affordable housing, greenway, and other
goals.
3Project Context
In November 2002, City Council adopted the South
Waterfront Plan. The Plan gave PDC responsibility
for coordinating the development on behalf of the
City in accordance with a set of agreed upon
goals.
Central District
4South Waterfront Goals
- 10,000 quality jobs
- 3,000 housing units
- 788 affordable units
- Exemplary greenway
- Integrated parks system
- Sustainable development/habitat restoration
- Multi-modal transit
5Central DistrictDevelopment Agreement
- 1.5 M sq .ft. of OHSU research, clinical, and
institutional space - 2,660 housing units - 430 affordable
- OHSU parking garage
- Streetcar to Gibbs Street
- Streets/utility infrastructure
- South Waterfront greenway
- Neighborhood park
- Sustainable development
- M/W/ESB
- Aerial tram to Marquam Hill
6Phase I status
GOALS
STATUS
Research/Office OHSU - 400,000 sq.ft. under
construction to open fall 2006
Market Housing NMI - 750 condos under
construction Affordable Housing PDC Negotiating
site acquisition
Parking Garage OHSU - Site Acquired
Streetcar PDOT - To Gibbs St., complete
Greenway PDC Master Plan adopted
Neighborhood Park PPR Initial improvements open
7/06
Tram PDOT- Under construction
7Central District Aerial
8Tram Saddle
9Rebar Forest
10- As the Citys agent, PDC shall reach agreement
with - our partners in the district that includes
guaranteed funding for - Tram Completion
- Streetcar Extension
- Affordable Housing
- Park Improvements and
- Greenway Improvements.
11CITY COUNCIL MEMORANDUM DECEMBER 2, 2005
12PDC Actions
Commissioned Pinnell/Busch Study
Convened Negotiating Team, Completed
Negotiations
Began Implementing Report Recommendations
13Financial Risks
- Tier I Infrastructure Projects 122.3 million
- Tax Increment Financing (TIF) 30.80m
- Local Improvement District (LID) 30.5m
- Tram 3.05m
- Streetcar 5.02m
-
14Tram Oversight Responsibilities
- Oversight Convene now to initiate and charge
the groups below, meet as necessary. - Leadership Meet quarterly, resolve cost and
responsibility issues. - Steering Monthly review of project schedule,
budget compliance, recommend cost issues.
15Tram Oversight Roles
16Financial Risks
- Tier I Infrastructure Financing Plan
- Interim financing provided by General Fund
- secured lines of credit
- Lines of credit taken out by
- Tax Increment Bonds
- Special Assessment Bonds
17Financial Risks
Project Expenditures to Date TIF 20.6
million Tram 20.0 million
18Upcoming Decisions and Projected Timing
- PDOT Construction Contract Amendment, April
2006
Amend SWF Development Agreement, April 2006
Secure Financing, April 2006
19Proposed Funding Plan
Current New Total
Affordable Housing 7.0m 18.7m
25.7m
Neighborhood Park 8.0m 4.0m
12.0m
Greenway 0m 6.05m 6.05m
Economic Dev. 5.0m 3.5m
8.5m
Trans. Contingency 0m
3.0m 3.0m
Tram 40.0m 10.0m 50.0m Tram
Contingency 0m 3.4m 3.4m
20Proposed Private DA Commitments
Commitment Value
Guarantee (NMI) 33.75m Tram (OHSU)
7.5 m Accelerate LID/Lowell Streetcar 4.8 m
Additional Condo Towers (NMI) 330.0
m Guarantee Purchase of Parks SDCs 3.0 m
21Proposed Tram Funding
2004 2005
2006 Budget Budget Proposed
Contingency
OHSU LID 13.4 M 24.75 M 24.75
M 0 M
OHSU CASH 6.0 M 6.0 M
6.0 M 1.5 M
OHSU ADDL 0 M 0 M
6 M 0 M
SWF PROP LID 5.8 M 5.8M 5.8M
0 M
TIF 3.27 M 3.5 M
7.5 M 1.9 M
TOTAL 28.5 M 40.0 M
50.0 M 3.4 M
Includes 2M Cash Advance for Potential State
Energy Tax Credits
22Tram Funding 2005
23Proposed Tram Funding 2006
24Affordable Housing
Current Funding 7.0 M Proposed Funding
25.7 M
- OUTCOMES
- Site Control
- Acquire Block 49 200-240 unit potential
- Buy Air Rights on Block 33 400 unit potential
- Acquire PDOT/ODOT Sites 400 unit potential
- RFP to be Issued for 200 Units by December 2006
- Construction
- Build 200 units by 2008 (site TBD)
25Greenway
Current Funding 0 M Proposed
Funding 6.05 M
- OUTCOMES
- Final Improvements to Central District
Greenway - (1,300 linear feet)
- Built To Existing City Council Greenway Master
Plan
26Neighborhood Park
Current Funding 8 M Proposed Funding
12 M
- OUTCOMES
- Acquired 2-Acre Park Site (Public Storage)
- Complete Tenant Relocation
- Demolition and Initial Improvements by June 2006
- Complete Design and Construct Final
Improvements by 2009
27Economic Development/ Bioscience Initiative
Current Funding 5.0 M Proposed
Funding 8.5 M
- OUTCOMES
- 400,000 sq. ft. OHSU Research/Clinical Building
(under construction) - Provides Bioscience Recruitment/Jobs Creation
Program - Bioscience Facility Construction
28Transportation Contingency
Current Funding 0 M Proposed Funding
3 M
- OUTCOMES
- Provides Funding To Address Other Non-Tram
- Transportation Improvements
29Streetcar Gibbs to Lowell
Current Funding 0 M Proposed
Funding 11 M
- OUTCOMES
- Completes Streetcar System for the Entire SWF
District - LID 4.8 M
- Connect Oregon 2.1 M
30Tram
Current Funding 40 M Proposed
Funding 50 M ( contingency 3.4M)
- OUTCOMES
- All DA Parties Agree to Funding Plan to Complete
- Tram Construction by December 1, 2006
- Minimizes Financial Risk For City
31(No Transcript)